An accepted deadline for a project approaches. However, the project manager
realizes only 75% percent of the work has been completed. The project manager then
issues a change request.
What should the change request authorize?
Corrective action based on causes
The project manager develops a process improvement plan to encourage continuous
process improvement during the life of the project. Which of the following is a valid tool
or technique to assist the project manager to assure the success of the process
improvement plan?
Process analysis
The project manager meets with the project team to review lessons learned from
previous projects. In what activity is the team involved?
Risk identification
A project manager leads a software development project in a hybrid environment. During project
planning, the project manager identified a risk where a technical resource for a critical path item
may not be available when needed. One week before the resource is needed, the technical
engineer had a personal emergency and had to take a leave.
What should the project manager do next?
A.
Consult the risk register for an appropriate planned risk response and implement.
B.
Revise the project management plan and move the task to a time when the technical resource will
be available.
C.
Review the business requirement with stakeholders and exclude the task assigned to the technical
resource.
D.
Update the lessons learned report and the risk log to reflect that this risk has materialized.
A.
Consult the risk register for an appropriate planned risk response and implemen
A team has just adopted an agile approach. During daily standup meetings, the team expressed
concerns about task delays. The project leader worked with the product owner to get clarity on the
features. The project leader asked the team to fast-track all product features to ensure delivery.
Sprints are being completed but with either fewer features or low quality.
What should the project leader have done to ensure success?
A.
Asked the team to create an impediment log and keep it updated for use in the next sprint
planning
B.
Directed teams to possible solutions that help in removing the impediments and contribute to a
timely delivery
C.
Suggested to the team to add impediments as work items in the product backlog to be fixed in the
PMI PMP Exam
“Everything is under control” - www.pass4sure.com 2
next sprints
D.
Empowered the team to improve their processes, tools, and interactions to be more effective in
delivery and removing impediments
D.
Empowered the team to improve their processes, tools, and interactions to be more effective in
delivery and removing impediments
A team is delivering features to a customer at every iteration. After completing each iteration, the
customer is invited for a review. However, the customer is frequently not available and the review
is often delayed, which results in increased rework for the team.
What should the project manager do?
A.
Include the customer in daily project activities to gain the required guidance
B.
Plan ahead and define the best way to review the deliverables with the customer
C.
Request the customer to clarify all requirements at the start of each iteration
D.
Ask the customer to review the deliverables in each iteration based on their availability
B.
Plan ahead and define the best way to review the deliverables with the customer
A project manager is part of a team that is launching a series of features to comply with a new
regulation. The team has only 6 weeks to release the features to the legacy applications. During
the standup meeting, a software engineer indicated that the development of an important feature
is on hold until the assigned designer completes a specific task. This delay is a serious road block
to meeting the release date.
What should the project manager do?
A.
Meet with the design team manager to inform them of the current status and request an additional
designer
B.
Ask the software engineer to move forward without completing the important feature
C.
Contact the design team manager and ask to reconsider the priority list based on the latest
situation
D.
Meet with the designer to share the current status and develop a solution to complete the task
D.
Meet with the designer to share the current status and develop a solution to complete the task
A project manager is working with a customer’s team on a new project. Some product definitions
and requirements are still not clear, but the customer wants to start activities as soon as possible.
The organization is also expecting product delivery for a specific date due to a regulatory
requirement. Due to the nature of the project, the project manager has decided to use a hybrid
approach.
Why did the project manager choose a hybrid approach?
A.
A hybrid approach will enable project activities to start immediately and allow for a plan for the
requirements definitions
B.
A hybrid approach will allow the project manager to revise the product specifications
C.
A hybrid approach will allow for management of the requirement uncertainties as well as the date
restriction
D.
A hybrid approach will ensure the delivery date is accomplished and will eliminate product
uncertainties
A.
A hybrid approach will enable project activities to start immediately and allow for a plan for the
requirements definitions
A project team has expressed concern that certain remote team members are not able to
collaborate with the larger project team due to their work schedule. The project manager is
confused since the entire team is located in the same time zone and believes there are other
factors at play.
What should the project manager do next?
A.
Implement new options
B.
Examine the team’s virtual needs
C.
Rectify ground rule violations
D.
Review performance formally
B.
Examine the team’s virtual needs
A company is implementing a project with team members located in different countries and time
zones. Individual performance is satisfactory, but the team’s performance as a whole is low,
especially in terms of group activities.
What should the project manager do?
A.
Review and reassign team assignments
B.
Facilitate communication and team building
C.
Negotiate for new team members
D.
Review and update the communications management plan
B.
Facilitate communication and team building
During the third iteration of a project, the product owner requests another mandatory feature. This
also happened in the previous two sprints, which resulted in failure and caused frustration within
the team.
What should the project manager do next?
A.
Request the scrum team to prioritize the product backlog
B.
Ask the product owner to prioritize the backlog with the project team
C.
Call for an internal meeting to discuss the changes and their value
D.
Incorporate the changes in the last sprint before the first release
C.
Call for an internal meeting to discuss the changes and their value
Five agile teams working together on a product recently performed release planning. Midway
through the project, each team showed that their progress was on track. When all of the teams
integrated at the product level, many integration issues were observed. The overall product
release progress declined with predictions showing the committed content will not be able to be
accomplished.
What should the project manager have done differently?
A.
Performed a Scrum of Scrums on a regular basis to help the teams remove impediments
B.
Formed a separate quality assurance team to test all items coming from each team at the end of
each sprint
C.
Arranged an online session on the integration concept and suggested tools to the teams
D.
Ensured frequent and continuous integration of work to obtain early feedback and continuous learning
D.
Ensured frequent and continuous integration of work to obtain early feedback and continuous learning
A project team member is having difficulty delivering assigned tasks for a project that is at risk of
being delayed. The main issue is that the team member does not understand a new system that
was recently implemented.
What should the project manager do?
A.
Ask the team member to learn the new system as on-the-job training.
B.
Issue a change request to extend the project schedule.
C.
Escalate the team member’s performance to the project sponsor.
D.
Assign an experienced resource to support the team member.
A.
Ask the team member to learn the new system as on-the-job training.
A project team consisting of four team members will be rolling out a company-wide application to
both staff and contractors in a country. To deliver within strict the time lines, a local company
skilled in application deployment and change management will need to be contracted.
What should the project manager do to empower the local company?
A.
Manage expectations and agree on the requirements that the contractor will deliver under the
supervision of the project manager
B.
Begin to roll out the application by micromanaging the contractor
C.
PMI PMP Exam
“Everything is under control” - www.pass4sure.com 7
Set expectations and agree on the requirements that the contractor will deliver with periodic
progress reports
D.
Deploy the contractor’s staff under the supervision of the project manager
A.
Manage expectations and agree on the requirements that the contractor will deliver under the
supervision of the project manager
A project manager is managing a construction project that is facing challenges. There is schedule
overrun, cost overrun, and the client is unhappy with the specific scope progress.
What should the project manager do first?
A.
Review the scope and project objectives.
B.
Enforce the penalty clause on the supplier.
C.
Take action to reduce the cost overrun.
D.
Work with the client on the scope completion.
A.
Review the scope and project objectives.
In a geographically distributed project team, the project team members continue to email status
reports and update schedules after their weekly meeting discussions. However, the team is having
difficulty tracking the changes and progress made.
What should the project manager do?
A.
Facilitate training on version control and project artifacts.
B.
Maintain separate document control via regions to avoid discrepancies.
PMI PMP Exam
C.
Maintain a central repository of artifacts with a version control system.
D.
Develop a document management software for version control.
C.
Maintain a central repository of artifacts with a version control system.
A project manager has been assigned to a project where collaboration with the business is a
critical key factor. The project manager is not sure about which approach to use. A senior project
manager has been assigned to help the project manager.
What advice should the senior project manager provide?
A.
Work with the project manager to develop a new approach that will bring benefits to the project
B.
Suggest using an agile approach since customer and team collaboration is critical for project
success
C.
Establish a project management methodology that requires the customer to provide daily updates
to the team
D.
Provide a project management template for the project manager to follow as a guide
B.
Suggest using an agile approach since customer and team collaboration is critical for project
success
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart
is shown below.
What should the team do next?
A.
Ask the product owner if some low-priority stories could be cut from the sprint
PMI PMP Exam
“Everything is under control” - www.pass4sure.com 10
B.
Continue with the sprint as the progress shows buffers for potential interruptions
C.
Ask the project team to select any additional stories as they have additional capacity than planned
D.
Continue with the sprint work as planned and keep monitoring
D.
Continue with the sprint work as planned and keep monitoring
A project manager is managing a large project. A stakeholder has just discovered a new risk that
has not been identified in earlier stages.
What should the project manager do?
A.
Confirm to the stakeholder that the risk register has been completed and validated by all
stakeholders
B.
Perform a risk analysis directly with the stakeholder who raised the risk and update the risk
register
C.
Communicate the risk to the steering committee and request a mitigation plan from senior
management
D.
Add the risk to the risk register and reevaluate the register with help from the project team and
stakeholders
D.
Add the risk to the risk register and reevaluate the register with help from the project team and
stakeholders
A project manager is assigned to a critical software development project. The team is using a
hybrid approach and has divided development into four sprints. At the end of sprint three, the
project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV)
is US$550,000.
What should the project manager do?
A.
Fast track the project
B.
Adjust the budget
C.
Introduce a float
D.
Adjust the project time line
A.
Fast track the project
A project manager is closing a project and preparing to hand it over to the operations team. During
handover, a delayed invoice was submitted with a higher-than-planned cost against the project
work. Consequently, project handover was delayed and the project’s reported completion costs
were increased.
What should the project manager have done to avoid this situation?
A.
Notified all vendors about the invoicing and nonpayment deadlines
B.
Reviewed the total committed cost against the cost invoiced at project closing
C.
Involved the finance team and discussed the issue with the vendor
D.
Captured and reviewed all of the project work and related costs regularly
D.
Captured and reviewed all of the project work and related costs regularly
QUESTION NO: 19
A project manager is working with a co-located agile project team that has worked together long
enough to be in the performing phase of team development. An unforeseen event has caused the
team to be dispersed and they are now unable to co-locate.
What should the project manager do to keep the team performing as effectively as possible?
A.
Ask the project sponsor and executive stakeholders to encourage the team to maintain their
performance
B.
Provide the team with virtual collaboration software and training on the software to minimize
disruption
C.
Transition the team from an agile approach to a predictive approach for better performance control
D.
Evaluate project performance and step in if performance decreases to an unacceptable level
D.
Evaluate project performance and step in if performance decreases to an unacceptable level
A project manager is reviewing the requirements of a large program.
Which requirements should the project team prioritize to avoid getting fines?
A.
Certifying sustainable products
B.
Establishing company processes
C.
Complying with new regulations
D.
Developing new product lines
C.
Complying with new regulations
During the lessons learned workshop, one stakeholder mentioned that the project was
unsuccessful as it did not deliver the expected business value.
What should the project manager do to address this concern?
A.
Review the project management plan tasks with the stakeholders.
B.
Review the business benefits realization plan with the stakeholders.
C.
Review the project management plan budget with the stakeholders.
D.
Review the communications management plan with the stakeholders.
B.
Review the business benefits realization plan with the stakeholders.