Test 2 Flashcards
(100 cards)
Which AIA document will you find the mediation and arbitration clauses?
A. AIA B102
B. AIA B201
C. AIA G710
D. AIA G701
A. AIA B102
Feedback:
AIA B102, Standard Form of Agreement Between Owner & Architect, Articles 4.2. & 4.3, contain the mediation and arbitration clauses.
Which is not a method of historic preservation?
A. Preservation
B. Replication
C. Restoration
D. Reconstruction
B. Replication
Feedback:
Rehabilitation, not replication, is the fourth approach to preserving a historic building.
According to the General Conditions what is a modification?
A. A written amendment to the Contract signed by both parties, Change Order, Preliminary Notice
B. A written amendment to the Contract signed by both parties, A Change Order, A Construction Change Directive, A written order for a minor change in the Work
C. A written amendment to the Contract signed by both parties, Change Order, A Construction Change Directive, Certificate of Substantial Completion
D. A written amendment to the Contract signed by both parties, A Change Order, A written order for a minor change in the Work
B. A written amendment to the Contract signed by both parties, A Change Order, A Construction Change Directive, A written order for a minor change in the Work
Feedback:
A written amendment to the Contract signed by both parties, A Change Order, A Construction Change Directive, A written order for a minor change in the Work are all considered modifications.
See AIA A201 General Conditions, Article 1.1.1 under General Provisions.
Which of the following consultants deals with topography and existing site features?
A. Geotechnical Engineer
B. Civil Engineer
C. Arborist
D. Landscape Designer
B. Civil Engineer
Feedback:
Civil engineering focuses on site related issues such as existing topography, sewer and water lines, retaining walls, drainage, and water features. Geotechnical engineers analyze sub surface site features, Arborists deal with trees and Landscape designers typically develop new site plan designs.
A pristine piece of undeveloped land is called?
A. Brownfield
B. Greenfield
C. Public way
D. Scenic easement
B. Greenfield
Feedback:
Environmentalist argue that cleaning up a chemically polluted brownfield is better and more important than developing on a pristine piece of undeveloped land (called a “greenfield”).
At the completion of the Schematic Design Phase, you will have the Owner sign off on
A. Single design strategy, Preliminary estimate of the cost of the work
B. Multiple design strategies, Preliminary estimate of the cost of the work
C. Single design strategy, Preliminary estimate of the cost of the work, Project Manual
D. Multiple design strategies, Preliminary estimate of the cost of the work, Project Manual
A. Single design strategy, Preliminary estimate of the cost of the work
Feedback:
At the completion of the Schematic Design Phase, you will have the Owner sign off on Single design strategy, Preliminary estimate of the cost of the work.
Completion is the key term. During the Schematic Design Phase, you may explore multiple design strategies.
Project Manual is not assembled until the Construction Documents Phase.
Who has the authority to stop work at a construction site?
A. Architect, Owner
B. Architect, Local Building Official
C. Owner, Local Building Official
D. Architect, Owner, Local Building Official
C. Owner, Local Building Official
Feedback:
Owner, Local Building Official.
See AIA A201 General Conditions, Article 2.3, Owner’s Right to Stop the Work.
Remember, Architects have no authority to stop work.
Who decides on the structural system for a project?
A. Structural Engineer
B. Architect
C. Owner
D. General Contractor
C. Owner
Feedback:
Owner.
The Architect can meet with the Structural Engineer to discuss the different structural systems that could work and present them to the Owner along with anticipated costs, and even make a recommendation, but it is ultimately the Owner who makes the final decision.
A corner convenience store that was built prior to a neighborhood being rezoned entirely residential is an example of what?
A. Non-conditional use
B. Variance
C. Conditional use
D. Non-conforming use
D. Non-conforming use
Feedback:
Non-Conforming Use: where the current use of the building is no longer permitted by the zoning ordinance (but once was). The use is typically allowed to continue unless it’s unsafe.
Which act regulates existing chemicals that pose an unreasonable health risk?
A. CERCLA
B. TSCA
C. SARA
D. OSHA
B. TSCA
Feedback:
The objective of the Toxic Substances Control Act (TSCA) is to allow EPA to regulate new commercial chemicals before they enter the market, to regulate existing chemicals when they pose an unreasonable risk to health or to the environment, and to regulate their distribution and use.
During the bidding phase of the project the Architect would normally be involved with all of the following except?
A. Attend a pre bid conference
B. Create and distribute addenda
C. Assist Owner in establishing a list of qualified sub contractors
D. Assist in prequalification of bidders
C. Assist Owner in establishing a list of qualified sub contractors
Feedback:
Assist Owner in establishing a list of qualified sub contractors is the correct answer as the Owner does not generally establish a list of sub-contractors, rather a list of General Contractors (which the Architect may help with).
Increasing the amount of insulation in a building’s walls would primarily help optimize what?
A. Energy use
B. Material use
C. Indoor air quality
D. Operations and maintenance
A. Energy use
Feedback:
Increased insulation directly effects the heating and cooling requirements of a building.
Physical examples that illustrate materials, equipment or workmanship and establish standards by which the work will be judged are known as
A. Shop Drawings
B. Samples
C. Product Data
D. Pretty To Look At
B. Samples
Feedback:
Samples are physical examples that illustrate materials, equipment or workmanship and establish standards by which the work will be judged.
See AIA A201 General Conditions, Article 3.12.3 under Shop Drawings, Product Data and Samples.
What is the required width for exit stairs in a building with an occupant load of 300?
A. 60”
B. 90”
C. 100”
D. 150”
B. 90”
Feedback:
Stair width = (occupant load * 0.3) inches = 300 * 0.3 = 90”
Which of the following is not a consideration during the construction documents phase for energy efficiency?
A. Lighting control
B. Solar orientation
C. Programmable Thermostats and Zones
D. Insulated windows
B. Solar orientation
Feedback:
A buildings solar orientation should be considered during the schematic design phase. By the construction documents phase it is too late to change the buildings orientation.
The project is half-way through construction and the Owner decides to change the plumbing fixtures in the toilet rooms. During the weekly construction meeting the contractor determines the cost will be the same and agrees to install the new fixture at no additional cost. How should you proceed?
A. Issue a Change Order
B. Issue a Construction Change Directive
C. Issue an Architect’s Supplemental Instruction
D. Issue a Request for Information
C. Issue an Architect’s Supplemental Instruction
Feedback:
Issue an Architect’s Supplemental Instruction. This is also considered a substitution and the Owner should approve the change in writing.
AIA G710 Architects Supplemental Instructions is used when there is not a change to the time or cost, typically for minor clarifications or instructions.
How can the Owner verify the subcontractor has been paid by the Contractor?
A. The Owner can request written evidence from the Contractor
B. The Architect can Issue an AIA G706 Contractor’s Affidavit of Release of Liens
C. The Owner should require the contractor to carry liability insurance
D. The Owner should obtain a payment bond
A. The Owner can request written evidence from the Contractor
Feedback:
The Owner can request written evidence from the Contractor.
See AIA A201 General Conditions, Article 9.6.4 under Progress Payments.
According to AIA B101, Article 3.2, the Architect shall submit the following to the Owner at the end of the Schematic Design Phase
A. An outline specification
B. A list of Subcontractors for the project
C. A list of General Contractors for the project
D. An estimate of the Cost of Work
D. An estimate of the Cost of Work
Feedback:
According to AIA B101, Article 3.2, the Architect shall submit the following to the Owner at the end of the Schematic Design Phase an estimate of the cost of work. See Article 3.2.6.
The project is under construction and you realize the Contractor has discovered missing information in the drawings and as a result, did not include the missing information in his bid. You show the Contractor where the missing information is included in the specification. How do you resolve this?
A. Request the Contractor include the missing information in his base bid as it was included in the specifications
B. Explain to the Contractor that the specifications take precedence over the drawings and he should have included the missing information in his base bid
C. Issue a change order for the missing information
D. Issue a construction change directive for the missing information
A. Request the Contractor include the missing information in his base bid as it was included in the specifications
Feedback:
Request the Contractor include the missing information in his base bid as it was included in the specifications.
Specifications do not take precedence over the drawings and vice versa. The drawings and specs are complimentary. See AIA A201 General Conditions, Article 1.2 Correlation and Intent of the Contract Documents & Article 3.2.2 under Review of Contract Documents and Field Conditions by Contractor.
The Schedule of Values is prepared by whom?
A. Contractor
B. Architect
C. Owner
D. Subcontractor
Feedback:
The Schedule of Values is prepared by the Contractor.
See AIA A201 General Conditions, Article 9.2 Schedule of Values.
What is determined by a building’s Occupancy Group?
A. Occupant Load Factor, construction classification, exit stair width
B. Fire resistance rating, egress path length, size of exits
C. Need for sprinklers, fire resistance rating, construction classification
D. Size of room, size of exits, need for sprinklers
D. Size of room, size of exits, need for sprinklers
Feedback:
Occupancy Group is the intended use of the building that will determine certain requirements for fire safety and egress, including the size of the room, size of exits, and need for sprinklers.
Which of the following are responsibilities of the Architect during project completion?
A. Determine dates of substantial completion and final completion, Receive documents such as warranties from the Contractor and turn them over to the Owner, Issue a certificate for final payment, File Certificate of Substantial Completion
B. Receive documents such as warranties from the Contractor and turn them over to the Owner, Issue a certificate for final payment
C. Determine dates of substantial completion and final completion, Receive documents such as warranties from the Contractor and turn them over to the Owner, Issue a certificate for final payment, Issue Certificate of Occupancy
D. Determine dates of substantial completion and final completion, Receive documents such as warranties from the Contractor and turn them over to the Owner, Issue a certificate for final payment
D. Determine dates of substantial completion and final completion, Receive documents such as warranties from the Contractor and turn them over to the Owner, Issue a certificate for final payment
Feedback:
Determine dates of substantial completion and final completion, Receive documents such as warranties from the Contractor and turn them over to the Owner, Issue a certificate for final payment.
See AIA A201 General Conditions, Article 4 Architect.
Name two criteria you would use in qualifying the General Contractor
A. Is the General Contractor licensed, References
B. Does the General Contractor carry the proper types and amounts of insurance, Experience in building type
C. References, Experience in building type
D. It is not the responsibility of the Architect to qualify the General Contractor
D. It is not the responsibility of the Architect to qualify the General Contractor
Feedback:
It is not the responsibility of the Architect to qualify the General Contractor is the correct answer. It is the Owner’s responsibility to qualify the General Contractor.
Some of the items the Owner could check would be;
Is the contractor licensed
Experience in that building type
References
Carries the correct types/amounts of insurance
Check with Contractors State License Board for history/complaints
The project manual is the written portion of the Construction Documents. The project manual consists of the following
A. Invitation to Bid, Instruction to Bidders, Specifications
B. Invitation to Bid, Instruction to Bidders, Specifications, Owner/Architect Agreement
C. Invitation to Bid, Instruction to Bidders, Specifications, Owner/Architect Agreement, General Conditions
D. Invitation to Bid, Instruction to Bidders, Specifications, Owner/Architect Agreement, General Conditions, Supplementary Conditions
A. Invitation to Bid, Instruction to Bidders, Specifications
Feedback:
Invitation to Bid, Instruction to Bidders, Specifications is the correct answer.
The other choices contain the Owner/Architect Agreement which is not part of the project manual, however, the Owner/Contractor Agreement is part of the project manual.