Test 3 Flashcards
(100 cards)
What is the required fire rating of the walls around the exit stairs in a three story building with a mezzanine in the lobby?
A. 2-hours
B. 1 1/2-hours
C. 1-hour
D. 3-hour
A. 2-hours
Feedback:
2-hour rated walls are required for buildings 1, 2 or 3 stories. Mezzanines are not counted as stories (basements are counted).
Arbitration is a form of alternative dispute resolution. The decision of the arbitrator is
A. Final
B. Non-Binding
C. A recommendation only
D. Delivered within 14 days of the hearing
A. Final
Feedback:
Final.
See AIA A201 General Conditions, Article 15.4.2 under Arbitration.
Which is not a best practice for indoor air quality during occupancy?
A. Building flushing
B. Controllability
C. Daylighting
D. Thermal comfort
A. Building flushing
Feedback:
Building flushing is a process of removing toxins from a building after constructing and before occupancy.
What is the most proper method for apportioning monetary value of the work by the Contractor?
A. Owner cost estimate
B. Architect cost estimate
C. Schedule of values
D. Standard value index
C. Schedule of values
Feedback:
The Schedule of Values is a detailed statement furnished by the General Contractor, outlining the portions of the contract sum. It allocates values for the various parts of the work and is also used as the basis for submitting and reviewing progress payments.
Note. The AIA does not have a form for the Schedule of Values.
Using the earth as a heat source (in the winter) or a heat sink (in the summer) is what kind of energy?
A. Fuel cells
B. Micro hydro
C. Solar thermal
D. Geo-thermal
D. Geo-thermal
Feedback:
Geothermal drills pipes deep into the ground to produce warm water that can be used for heating or cooling.
If you were replacing windows in an office constructed in the 1970s which hazardous material should you be most concerned about?
A. Asbestos
B. Lead paint
C. Mold
D. Radon
B. Lead paint
Feedback:
Lead paint was likely used on the window sills. Asbestos would be a concern if the walls or ceilings were being modified. Radon is a hazardous gas that can be present in below grade spaces. Mold may become an issue due to a defect in the windows (and may be a cause for replacing the windows) but the act of replacing the windows would not cause anyone to be at risk.
Which of the following is not produced during the Design Development Phase?
A. Site evaluation
B. Preliminary construction details
C. Updated outline specification
D. Plans, sections, and elevations
A. Site evaluation
Feedback:
Site evaluation is typically performed before the Basic Scope of Services commences.
Who issues the Certificate of Substantial Completion?
A. Architect
B. Owner
C. Building Official
D. Surety
A. Architect
Feedback:
Architect.
The Architect issues the Certificate of Substantial Completion (not to be confused with the Certificate of Occupancy which is issued by the local Building Official).
See AIA A201 General Conditions, Article 9.8 Substantial Completion.
An allowance is
A. Used in lieu of specifying a product or particular portion of the work when that product or scope of work is not specified, such as door hardware (i.e. allow $5000 for door hardware, we’ll pick it out later)
B. The amount added or deducted to the based bid for a specified product, i.e. hardwood floor is specified in the based bid, but carpet is specified as an option
C. Typically utilized during construction when a product is substituted for the one specified in the Construction Documents, i.e. no longer available, long lead time. Substitutions must be approved in writing by Architect & Owner
D. Calls out or specifies three or more trade names with a provision “or approved equal” often included
A. Used in lieu of specifying a product or particular portion of the work when that product or scope of work is not specified, such as door hardware (i.e. allow $5000 for door hardware, we’ll pick it out later)
Feedback:
An allowance is used in lieu of specifying a product or particular portion of the work when that product or scope of work is not specified, such as door hardware (i.e. allow $5000 for door hardware, we’ll pick it out later).
Can a conference room with a maximum occupancy of 25 have egress doors that open into the room?
A. Yes
B. Yes, if the door is fire rated
C. Yes, if the door is metal
D. No
A. Yes
Feedback:
50 people is the minimum occupancy requiring 2 egress doors.
The total cost to the Owner to construct all elements of the project designed or specified by the Architect and shall include contractors’ general conditions costs & overhead and profit is known as
A. Cost of Work
B. Cost to Build
C. Cost Plus
D. Cost Breakdown
A. Cost of Work
Feedback:
Cost of Work is the total cost to the Owner to construct all elements of the project designed or specified by the Architect and shall include contractors’ general conditions costs & overhead and profit.
See AIA B101 Article 6.1
What techniques are useful to maintain project quality assurance and quality control (QA/QC) on a project?
A. Team meetings to review design and progress, Checklists and documentation of key approvals
B. Checklists and documentation of key approvals
C. Standards for CAD and design document, Team meetings to review design and progress
D. Team meetings to review design and progress, Checklists and documentation of key approvals, Standards for CAD and design documents
D. Team meetings to review design and progress, Checklists and documentation of key approvals, Standards for CAD and design documents
Feedback:
Team meetings to review design and progress, Checklists and documentation of key approvals, Standards for CAD and design documents.
Quality assurance and quality control is very important in order to deliver a satisfactory project to the owner. This not only assures that the client is happy, it increases the odds of repeat or referred business. The above techniques are useful for this process.
If the Occupant Load Factor for a 9,000 sq. ft. warehouse is 300 sq. ft. per person how many exits are required?
A. 1
B. 2
C. 3
D. 4
A. 1
Feedback:
9,000 sq. ft. / 300 sq. ft. per person = 30 people < 50 people minimum requirement for 2 exits.
The Contractor’s responsibility in regards to code compliance of the project is as follows?
A. The Contractor is responsible to make sure the contract documents are in full compliance with all codes and regulations
B. The Contractor is not required to review the contract documents for code compliance. However, if the Contractor notices or is informed of elements not conforming to code, he should notify the Architect promptly
C. The Contractor has no responsibility pertaining to codes and regulations. That is the Architect’s role
D. The Contractor is responsible only to codes and regulations that pertain to work performed directly by his staff but not to work performed by sub Contractors
B. The Contractor is not required to review the contract documents for code compliance. However, if the Contractor notices or is informed of elements not conforming to code, he should notify the Architect promptly
Feedback:
The Contractor is not required to review the contract documents for code compliance. However, if the Contractor notices or is informed of elements not conforming to code, he should notify the Architect promptly.
See AIA A201 General Conditions, Article 3.2.3 under Contractor.
A landscape architect has been hired for the project. Select the BEST four issues/items you would discuss with the landscape architect
A. Budget, Contract requirements, Overall design Intent, Types of planting to be used
B. Budget, Overall design intent, Types of planting to be used, Schedule
C. Overall design intent, Types of planting to be used, Water conservation methods, Shading requirements
D. Budget, Overall design intent, Schedule, Previous experience of the landscape architect
C. Overall design intent, Types of planting to be used, Water conservation methods, Shading requirements
Feedback:
Overall design intent, Types of planting to be used, Water conservation methods, Shading requirements are the BEST four issues/items with the landscape architect.
Budget, Schedule, and Contract requirements are also relevant topics of discussion, but the most important thing is to look at the type of consultant and what is most applicable or unique to that particular consultant.
Budget, Schedule and Contract requirements are applicable to any consultant and as a result are not considered the BEST answer for this question.
According to the Standard Form of Architect’s Services, AIA B101, which is not a customary service provided by the Architect?
A. Mechanical Engineering
B. Structural Engineering
C. Architectural Interior Design
D. Electrical Engineering
C. Architectural Interior Design
Feedback:
Architectural Interior Design is not considered a Basic Scope of Service according to AIA document B101, rather is considered an additional service per Article 4.1.9.
If the foundation of a building is damaged by blocks of soil separating from one another this is the result of what?
A. Fault rupture
B. Lateral spreading
C. Landslide
D. Liquefaction
B. Lateral spreading
Feedback:
Lateral Spreading: Intense shaking during an earthquake can cause the soil to break into blocks which separate from each other. This can cause damage to the building foundation
Neurological brain damage, reproductive problems and nerve damage are know to be caused by what?
A. Asbestos
B. Formaldehyde
C. Lead paint
D. Volatile organic compounds
C. Lead paint
Feedback:
Lead has been found to cause permanent neurological brain damage, reproductive problems and nerve damage.
What is a continuous vertical or horizontal shield with a minimum fire-resistant rating of 1 hour?
A. Fire Barrier
B. Fire Partition
C. Smoke Barrier
D. Fire Wall
C. Smoke Barrier
Feedback:
A smoke barrier is a continuous vertical or horizontal shield with a minimum fire-resistant rating of 1 hour that is designed and constructed to restrict movement of smoke.
During the course of renovation of an old office building, the Contractor encounters what he believes to be asbestos. Which is NOT a correct statement?
A. The Contractor, upon finding the asbestos, must immediately stop work in the affected area and arrange for the removal or encapsulation of the asbestos
B. The Contractor, upon finding the asbestos, must immediately stop work in the affected area and report the condition to Owner and Architect
C. The Owner is responsible for hiring a testing company to test for the presence of asbestos
D. When the material or substance has been rendered harmless, work in the affected area shall resume upon written agreement of the Owner and Contractor.
A. The Contractor, upon finding the asbestos, must immediately stop work in the affected area and arrange for the removal or encapsulation of the asbestos
Feedback:
The Contractor, upon finding the asbestos, must immediately stop work in the affected area and arrange for the removal or encapsulation of the asbestos is the incorrect statement.
If the Contractor encounters asbestos or other hazardous material, the first step is to notify the Architect and Owner in writing.
See AIA A201 General Conditions, Article 10.3 Hazardous Materials.
The Owner has changed the scope of work during the Construction Documents Phase after written approval at the end of the Design Development Phase to increase the size of the auditorium an additional 1,000s.f. This change would be considered
A. Part of Basic Services
B. An additional service
C. A change order request
D. A supplemental instruction
B. An additional service
Feedback:
If the Owner makes a change in the scope of work during one of the Phases, it would generally be considered and additional service and the Architect should receive written approval before proceeding with the change.
According to AIA B201, which statement is true?
A. The Architect shall coordinate its services with those services provided by the Owner and the Owner’s consultants
B. The Architect shall coordinate its services with those services provided by the Owner and the Owner’s consultants only when agreed in writing and the Architect receives additional compensation
C. The Architect is not responsible for coordinating with the Owner’s consultants
D. The Owner is responsible for coordinating the work of its consultants with that work of the Architect’s
A. The Architect shall coordinate its services with those services provided by the Owner and the Owner’s consultants
Feedback:
The Architect shall coordinate its services with those services provided by the Owner and the Owner’s consultants is the correct statement according to AIA B201, Article 2.1.2
An Architect’s Contract Administration responsibilities begin at ________and end at ________.
A. Award of contract for construction, issuance of certificate for final payment to Owner
B. Arrival of bids, Substantial Completion
C. Groundbreaking, 60 days after Substantial Completion
D. First site visit, Final Completion
A. Award of contract for construction, issuance of certificate for final payment to Owner
Feedback:
Award of contract for construction, issuance of certificate for final payment to Owner.
See AIA B101 Standard Form of Architect’s Services, Article 3.6.1.3.
Which is not a principle of sustainable design?
A. Optimize a building’s operations and maintenance
B. The conservation of on site water use
C. Preserve the historic character of a building
D. Optimize the use of space and material in a building
C. Preserve the historic character of a building
Feedback:
The 6 Principles of Sustainable Design are: Optimize Site Potential; Optimize Energy Use; Protect and Conserve Water; Optimize Building Space and Material Use; Enhance Indoor Environmental Quality; Optimize Operational and Maintenance Practices.