Test Reivew Flashcards
(38 cards)
While the __________ identifies the work to be done, the _________ identifies the people who will do the work
- Work Breakdown Structure (WBS)
* Organizational Breakdown Structure (OBS)
__________= BCWP – ACWP
Cost Variance
Contracts of _____ or more require a formal EVM system validation.
$50M
For contracts awarded after July 1, 2012 the _______________________ has replaced the Contractor performance reports and and Integrated Master Schedule (IMS) contractual requirements.
Integrated Program Management Report (IPMR)
There are _____ formats for the integrated program management report (IPMR)
7
The ____________________ is the contractor’s time-phased plan for accomplishing the work on the contract. It establishes the scope, schedule, and budget targets for the program.
Performance Measurement Baseline (PMB)
For the EVM accounting system the PM must be able to account for both labor and ___________ costs
Material
The _______________________ is a formal review conducted jointly between the government and the contractor to assess the validity of control account budgets, resources, and time phasing. It is mandatory for all EVM contracts
The Integrated Baseline Review (IBR)
_____________ provide a forum for communicating across different functional areas, used to clarify design requirements and design maturity, helps determine whether to proceed with development, establishes common baselines and is event, not calendar driven
Technical Reviews
During the ______________ top-level design for each configuration item function and interface is evaluated to determine if it is ready for detailed design
Preliminary Design Review (PDR).
What are the three configuration baselines.
- functional baseline
- allocated baseline
- ***product baseline
The overall system level baseline which is established during the Technology Maturation and Risk Reduction Phase is the _____________ Baseline
Functional
The _________________ baseline is established latter in the EMD Phase and is the basis for a production contract
Product Baseline
The Acquisition Program Baseline (APB) is developed by the __________for Milestone B, and is updated prior to each Milestone.
PM
Only the _________________________ can approve changes to the APB.
Milestone Decision Authority (MDA)
Performance parameters considered by the user to be the most essential, and expressed in threshold and objective values
Key Performance Parameters (KPPs).
The PM has the flexibility tot work within the _________________ between threshold and objective parameters.
trade space.
When a program deviation occurs the PM must notify the MDA _________ and has __________ to explain the reasons for the deviation and the steps taken to get the program back on track
- Immediately
* 30 Days
A Significant Breach occurs when you exceed the current baseline by __________ or the original baseline by __________
- +15%
* +30%
For a ___________ Breach, the service secretary notifies congress within 45 days of unit cost report (eg program deviation report) DOD submits a Selcected Action Report (SAR) with required unit cost breach information
Significant
The sustainment logistics function begins after production has started and ______________ has been declared
Initial Operational Capability.
What are the three reasons for Loss of vendors for older systems
- Obsolescence
- ***Diminished Manufacturing Source (DMS)
- Material shortages
__________________includes those logistics support activities that start as soon as the warfighter in the field receives the first system.
Sustainment Logistics
What are the Three levels of maintenance
- Organizational – Personnel from the using unit make the repair
- ***Intermediate – The repair is completed at a facility in the field
- Depot – The repair is made at a major facility for repair by contractor or Government civilian personnel