Q
Define activities - TT
A
Rolling Experts Decompose Templates
- Rolling wave planning
- Experts j.
- Decomposition
- Templates
1
Q
Define activities - Inputs
A
SOE
- Scope baseline
- EEF
- OPA
2
Q
Define activities - Ouputs
A
AMA
- Activity List
- Activ Attributes
- Milestone list
3
Q
Sequence activities - Inputs
A
AMAPO
- Activity List
- Milestone List
- Activ attributes
- Project Scope Statement
- OPA
4
Q
Sequence activities - TT
A
PADS
- PDM
- Applying lead and lags
- Dependency determination
- Schedule Network Templates
5
Q
Sequence activities - Outputs
A
Psnd Du
- Project Schedule Network Diagrams
- Proj docs updates
6
Q
Estimate Activity Resources - Inputs
A
AAREO
- Activity List
- Activ Attributes
- Resource Calendars
- EEF
- OPA
7
Q
Estimate Activity Resources - TT
A
PEPAB
- Project mgmt sw
- Experts j.
- Published estimating data
- Alternative Analysis
- Bottom-up estimating
8
Q
Estimate Activity Resources - Outputs
A
RA Du
- RBS
- Activity resource requirements
- Proj docs updates
9
Q
Estimate Activity Durations - Inputs
A
AARPAEO
- Activity List
- Activity Attributes
- Resource Calendars
- Project scope statement
- Activity Resource Requirements
- EEF
- OPA
10
Q
Estimate Activity Durations - TT
A
PETRA
- Parametric estimating
- Experts j.
- Three-point estimates
- Reserve Analysis
- Analogous estimating
11
Q
Estimate Activity Durations - Outputs
A
A Du
- Activity Durations Estimates
- Du
12
Q
Develop Schedule - Inputs
A
AARPAPAEO
- Activity List
- Activity Attributes
- Resource Calendars
- Project scope statement
- Activ Resource Requirements
- Proj Schedule Network Diagrams
- Activ Durations Estimates
- EEF
- OPA
13
Q
Develop Schedule - TT
A
SCC WARSS
- Schedule network analysis
- Critical path method
- Critical chain method
- What-if scenario analysis
- Applying leads and lags
- Resource leveling
- Scheduling Tool
- Schedule Compression
14
Q
Develop Schedule - Outputs
A
Project Baseline Data Du
- Project schedule
- Schedule baseline
- Schedule data
- Project docs update
15
Q
Control Schedule - Inputs
A
Schedule POW
- Project schedule
- PMP
- WPI
- OPA
16
Q
Control Schedule - TT
A
PVP WARSS
- Performance reviews
- Variance analysis
- Project mgmt sw
- What-if scenario analysis
- Adjusting lead and lags
- Resource leveling
- Schedule compression
- Scheduling tool
17
Q
Control Schedule - Outputs
A
W X
- Work performance measurements
- Change requests
- PMP updates
- Proj docs updates
- OPA updates