Unit 4 Flashcards

(52 cards)

1
Q

Damages for Breach of Contract

A

Right to claim for any breach. Claimant must prove loss. Aim is compensation, not punishment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Right to Damages & Requirement for Recovery

A

Breach of any term gives right to claim. Claimant must prove loss as a result of the breach.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Nominal Damages

A

Awarded if breach proven but no actual loss shown (small sum).
Case: Obagi v Stanborough (breach of “best endeavours” but no loss caused)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Compensation, Not Punishment

A

Fundamental aim is to compensate claimant’s loss, not punish defendant. Punitive/exemplary damages generally not available for pure contract claims. Damages based on claimant’s loss, not defendant’s gain.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Aim of Damages: Expectation Interest

A

To put claimant in the same situation as if contract performed.
Case: Robinson v Harman
Often protects claimant’s “expectation interest”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Expectation Loss: Concept & Calculation

A

This is the usual measure. Damages are awarded to compensate the claimant for the benefit they would have received had the contract been properly performed (their lost expectation).

Aims to provide the claimant with the monetary equivalent of the expected outcome.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Expectation Loss: Examples (Goods)

A

Fake Goods: Value if genuine - Actual value.
Seller Fails to Deliver: Cost of buying elsewhere - Contract price.
Buyer Refuses to Accept: Contract price - Price received elsewhere.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Claimant prevented from performing service/work:

A

Damages = Contract price - Expenses claimant would have incurred to perform. (e.g., Jason the gardener: £250 - £30 = £220 lost profit).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Expectation Loss: Defective (Traditional)

A

When goods or services provided under a contract are not up to the agreed standard (they are defective), the way damages are traditionally calculated depends on whether it’s goods or services:
Defective Goods: The usual measure is the difference in value between the goods as they were delivered (in their defective state) and what their value would have been if they had been as promised in the contract (not defective).

Defective Services/Work: The typical way to calculate damages is the cost of cure, which is the amount of money it would take to fix the defective work or services so that they meet the required standard.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Expectation Loss - Defective Goods/Services (Modern / Loss of Amenity / Consumer Surplus)

A

More recently, courts have recognized that sometimes the traditional measures of difference in value or cost of cure don’t properly compensate the claimant for their actual loss, especially in cases where the contract was about personal preference or enjoyment. In such situations, the court might award damages for “loss of amenity” or “consumer surplus”. This acknowledges that the claimant has lost something beyond just the market value or the cost of fixing a defect.

Ruxley Electronics v Forsyth - swimming pool. Facts: Swimming pool built shallower than specified (6ft 9in instead of 7ft 6in). No difference in value, but cost of cure was high (£21,560).
Holding: The House of Lords refused the disproportionate cost of cure and the zero difference in value. They reinstated the trial judge’s award (£2,500) for loss of amenity or consumer surplus, recognising Mr Forsyth’s personal preference had not been met, even though it didn’t affect the pool’s market value or basic function. This is particularly relevant where the contract is for pleasure or amenity (like a swimming pool).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Reliance Loss: Concept & When Used

A

Reliance loss is a different way of calculating damages. Instead of trying to put the claimant in the position they expected to be in, it aims to put them back in the position they were in before the contract was made. This is done by compensating them for the expenses they have already incurred because they relied on the contract being performed. Reliance loss is often claimed when it’s too difficult or impossible to accurately calculate the potential profit or benefit the claimant would have gained from the contract (expectation loss is too “speculative”).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Reliance Loss: Example

A

Anglia Television v Reed. Anglia Television hired the actor Robert Reed to star in a TV play. Reed pulled out of the contract at the last minute, and Anglia had to abandon the entire production. It was very difficult for Anglia to prove how much profit the play would have made if Reed had participated (expectation loss was too speculative). However, Anglia had already spent money on things like hiring directors, designers, and studio space before Reed signed the contract. The Court of Appeal allowed Anglia to claim for these “wasted expenditure” costs (reliance loss). This shows that even costs incurred before the contract was finalized can sometimes be recovered as reliance loss if the defendant knew about them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Expectation vs. Reliance: Choice

A

Generally, the claimant gets to choose whether they want to claim for expectation loss (what they would have gained) or reliance loss (what they’ve spent). However, the court might step in and say that damages should be assessed on a reliance basis if the expectation loss is simply too uncertain to calculate reliably.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Reliance Loss: Limitations

A

They cannot recover reliance loss if doing so would put them in a better financial position than if the contract had actually been performed. For example, if the contract they entered into was a bad deal from the start (a “bad bargain”), and they would have lost money even if it was performed, they can’t use reliance loss to recover all their expenses and end up better off than they would have been.

Also, if the claimant hasn’t actually suffered any overall loss as a result of the breach (for example, if they managed to make more money through a replacement contract), they can’t claim reliance loss for expenses that were ultimately covered by their new profits. - Omak Maritime Ltd v Mamola Challenger Shipping Co (The Mamola Challenger).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Types of Loss Recoverable in Contract Damages

A

Contract damages can cover harm to person, property, and economic position. Unlike tort, pure economic loss is generally recoverable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Examples of Recoverable Loss

A

Loss of Profit: Breach prevents expected earnings (e.g., defective machine leading to lost production).
Damage to Property: Physical harm to claimant’s assets due to breach (e.g., defective machine causes fire).
Physical Injury: Personal harm to claimant caused by breach (e.g., defective machine injures operator).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Damages for Lost Opportunity

A

Courts may compensate for the loss of a chance, even if success wasn’t guaranteed (less than 100% probability).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Damages for Lost Opportunity: Cases

A

Case: Chaplin v Hicks (contestant lost chance to be a winner due to breach - damages awarded for lost chance).
Principle: Damages for loss of chance awarded even if success not certain.
Case: Blackpool and Fylde Aero Club v Blackpool BC (tender not considered due to breach - damages for lost opportunity to have tender assessed).
Principle: Loss of opportunity to have a process followed can be compensated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Damages for Mental Distress: General Rule

A

Generally not awarded for mental distress, annoyance, disappointment, or upset caused by breach. Traditional stance to avoid “floodgates” of claims.
Case: Addis v Gramophone Co Ltd (distress from harsh dismissal not recoverable).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Damages for Mental Distress: Exception

A

Can be awarded if a main object (not necessarily sole) of the contract was to provide pleasure, entertainment, enjoyment, peace of mind, or freedom from distress.

21
Q

Damages for Mental Distress - Case Examples (Holiday) Jarvis v Swans Tours

A

Holiday significantly failed to meet brochure description, causing misery.
Principle (Lord Denning MR): Damages for disappointment, distress, upset, and frustration recoverable for breach of contracts for holidays/enjoyment. Compensates for lost pleasure/amenity.

22
Q

Damages for Mental Distress - Case Examples (Surveyor) Farley v Skinner

A

Surveyor failed to report on noise affecting property purchase, where peace of mind about noise was important object (not just the sole object).

Principle: Damages for non-pecuniary loss (distress/disappointment) awarded if important object was pleasure, enjoyment, peace of mind, or freedom from distress.

23
Q

The claimant may obtain damages for:

A

Loss of profit (economic loss).

Damage to property.

Physical injury.

Loss of opportunity/chance.

Mental distress and disappointment (but only in limited situations, primarily where a main object of the contract was pleasure, enjoyment, or peace of mind).

Limitation: Not all loss suffered is recoverable. The loss or damage must not be too remote a consequence of the breach (linking to the next topic: Remoteness).

24
The Remoteness Rule
A party will not be awarded damages for loss which is too remote a consequence of the breach. The remoteness rule limits the damages that can be recovered for a breach of contract. Its purpose is to prevent a party from being held liable for every single consequence of their breach, which could be unfairly extensive.
25
The Rule from Hadley v Baxendale (Establishing Case)
Mill shaft broke, carrier delayed delivery of replacement. Mill idle, lost profit. Carrier unaware of no spare shaft. The Rule (Alderson B): Damages recoverable for breach of contract are such as may fairly and reasonably be considered: Arising naturally (i.e., according to the usual course of things) from the breach itself. (This is often referred to as Limb 1). Or such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract, as the probable result of the breach,1 because of special circumstances known to them. (This is often referred to as Limb 2).  
26
Hadley v Baxendale: Decision
Loss of profit not recoverable. Limb 1: Not natural as mills usually have spares. Limb 2: Carrier unaware of no spare shaft (special circumstance not communicated at contract formation). Key Requirement: Knowledge of the special circumstances must exist at the time the contract is made. Knowledge acquired after contract formation is irrelevant for the remoteness rule. The reason is that parties might adjust terms (e.g., price, liability clauses) based on known risks.
27
Knowledge of Business Practices (Balfour Beatty v Scottish Power)
No general presumption of knowing all techniques in each other's businesses. Implied knowledge easier for simpler activities. Need for continuous concrete pour was complex, electricity supplier not deemed to know.
28
How has the Hadley rule been refined?
Victoria Laundry v Newman (1949) - Test: "Reasonably foreseeable as liable to result from the breach" (criticised later). - Imputed Knowledge: Everyone assumed to possess (Limb 1 - natural loss). - Actual Knowledge: Specific knowledge of special circumstances (Limb 2). Koufos v Czarnikow (The Heron II) (Clarifying the Test) - Approved Victoria Laundry outcome, disapproved "reasonably foreseeable." Reinstated "within the reasonable contemplation of the parties" as correct test.
29
Degree of Probability: Lord Reid stated the question for contract remoteness is ...
whether the loss was "of a kind which the defendant, when he made the contract, ought to have realised was not unlikely to result from [the] breach…"
30
Parsons v Uttley Ingham (1978)
Defective pig food hopper, mouldy food, pigs died from rare infection. Loss of pigs not too remote.
31
Parsons v Uttley Ingham: Reasoning
Was the type of consequence (loss of profit, physical injury) a serious possibility in the parties' contemplation at the time of the contract? If defendant can contemplate the type/kind of loss as a serious possibility, all loss of that type is recoverable, even if extent greater than expected. Some harm to pigs from mouldy food was foreseeable.
32
Transfield Shipping v Mercator (The Achilleas) (Assumption of Responsibility)
Late ship return, owners lost lucrative follow-on charter due to volatile market. Lost profit held too remote. Lord Hoffman / Lord Hope: Focused on "assumption of responsibility". Did the defendant charterer, in the particular commercial context of the charterparty market, implicitly assume responsibility for this type of potentially large loss arising from the owner's follow-on contracts? They concluded that, based on market understanding, charterers were typically only responsible for the difference between the contract rate and the market rate during the period of overrun, not for losses on subsequent fixtures. This represented a potential departure from the strict Hadley v Baxendale "contemplation" test towards a test based on what risks the parties commercially intended to undertake.
33
John Grimes Partnership Ltd v Gubbins [2013] EWCA Civ 37
The Court of Appeal stated that the standard rule for remoteness remains the Hadley v Baxendale test as interpreted in The Heron II – loss is recoverable if it was of a kind that was "not unlikely" to result from the breach, within the parties' reasonable contemplation at the time of contract. the "assumption of responsibility" approach may be a relevant consideration in exceptional circumstances, but the "not unlikely" contemplation test remains the general rule.
34
Remoteness - Summary
Loss not too remote if of a kind within reasonable contemplation at contract formation as "not unlikely" to result from breach (Hadley, Heron II). Commercial context/assumed responsibilities relevant in unusual cases (Achilleas, John Grimes).
35
Limitations on Damages
Even if loss is caused by breach and not too remote, damages may be limited by mitigation and contributory negligence rules.
36
Mitigation: The Rule
Claimant has a duty to take reasonable steps to minimise losses resulting from defendant's breach. Case: British Westinghouse v Underground Electric Railway
37
Mitigation - Effect of Failure
Claimant cannot recover damages for losses they could have avoided by taking reasonable steps. Avoidable loss deemed caused by failure to mitigate, not the breach.
38
Mitigation: Expenses & Burden
If the claimant takes reasonable steps to mitigate, they can recover any expenses incurred in doing so, even if the mitigation attempt is ultimately unsuccessful. Burden on defendant to prove claimant failed to take reasonable steps.
39
Mitigation: Examples of Reasonable Steps
Depends on circumstances (e.g., dismissed employee seeking work, buyer/seller seeking alternative transactions, obtaining quotes for incomplete work).
40
Contributory Negligence - General Position & Application in Contract
Tort: Damages reduced if claimant's negligence contributed to loss (Law Reform (Contributory Negligence) Act 1945). Contract: Act applies only if breach of contract is also a claimable tort of negligence (e.g., breach of contractual duty of reasonable care & skill). (e.g., the term implied by s. 13 of the SGSA 1982 in B2B service contracts). If applicable, the claimant's damages for breach of contract may be reduced to reflect the extent to which their own negligence contributed to the loss.
41
Time for Assessment of Damages - Basic Rule
Damages are generally assessed by reference to the time of the breach. If goods were due on Jan 31st for £5,000 but not delivered, and replacement goods cost £7,000 on Jan 31st, damages are £2,000, even if the price rose further by the time of the court hearing.
42
Time for Assessment of Damages - Reasoning & Exceptions
There are exceptions where assessing at the date of breach would not accurately reflect the true loss suffered. Golden Strait Corporation v Nippon Yusen Kubishiki Kaisha (The Golden Victory) [2007] 1 CLC 352 HL Principle: The majority held that the most important principle is that damages should reflect the actual loss suffered. While assessment at the date of breach normally achieves this, it should not be applied rigidly if it fails to do so.
43
Specified Damages and Penalty Clauses - Purpose
Parties may include clauses in their contract specifying a fixed amount of compensation to be paid upon a particular breach. This provides certainty and can avoid litigation.
44
Specified Damages and Penalty Clauses - Types of Clauses:
Specified Damages Clause (also called Liquidated Damages or Agreed Damages Clause): A genuine attempt to pre-estimate the loss likely to be caused by the breach at the time the contract is made. Penalty Clause: Primarily deters breach or punishes, not genuine pre-estimate.
45
Specified Damages clause: Effect
Binding. Innocent party receives specified amount, regardless of actual loss. Usual rules of measure, remoteness, mitigation do not apply to calculation within the clause.
46
Penalty Clause - Effect
A penalty clause is unenforceable. Where the clause is a penalty, the innocent party must prove their loss and damages will be assessed in the usual way, applying the normal principles of measure, remoteness, and mitigation.
47
Distinguishing a penalty from specified damages clause - Traditional Approach (Dunlop)
Question of construction, parties' intentions at contract formation. (a) Extravagant/Unconscionable Sum: Penalty if disproportionate to greatest conceivable loss. (b) Greater Sum for Non-Payment: If the breach is simply failing to pay money, and the sum specified is greater than the amount that should have been paid, it is a penalty. (c) Single Lump Sum for Multiple Events: A single lump sum payable upon the occurrence of one or more events, some potentially causing serious damage and others minor, is presumed to be a penalty. This presumption can be rebutted. (d) Difficulty in Pre-estimating: A clause can be a specified damages clause even if it is difficult or impossible to precisely pre-estimate the loss
48
Distinguishing: Modern (Cavendish/ParkingEye)
The penalty rule is concerned with two questions: The first was the circumstances in which the rule was engaged. The Supreme Court said a provision could not be a penalty unless it provided an exorbitant alternative to ordinary damages. The second question was concerned with whether the clause was penal and not whether it was a pre- estimate of loss. whether the clause imposed a detriment on the contract-breaker out of all proportion to any legitimate interest of the innocent party in the enforcement of the contract.
49
Where can the Dunlop guidelines still be used?
Where compensation for breach is the only legitimate interest, the Dunlop guidelines are usually sufficient to determine if the clause is penal (i.e., if the sum is disproportionate to the likely loss). However, where other legitimate interests exist, the broader Cavendish/ParkingEye test is needed.
50
is damages a common remedy?
Yes, it is the most common remedy, and should be considered first. Then, termination of contract: where there is a breach of a condition of a contract, or very serious breach of innominate term. Mainly used when there are future obligations. Specific performance/ injunction: only available if damages are inadequate. Cannot be ordered in employment contracts. Restitution as well.
51
What else of importance was stated in the Ruxley case?
Lord Mustill stressed that the judge’s award was a question of everyday practical importance to all householders who engage contractors to carry out small building works on their property. Whatever the proper basis of such an award the point is that the employer will get something, even if it’s not the full cost of cure.