Unit 6 Flashcards

(36 cards)

1
Q

Discharge by Frustration

A

Legal doctrine terminating a contract when an unforeseen event renders performance impossible or radically different from original intent. It acts as an exception to the general rule of pacta sunt servanda (agreements must be kept).

Construction Theory - Davis Contractors v Fareham UDC - Frustration occurs when a supervening event, considered in light of the “true construction” of the contract, makes performance radically different from what the parties originally intended. The court assesses whether a reasonable person would view the contract as essentially a new and different undertaking due to the changed circumstances. This theory gives courts more control over the application of frustration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Frustration: Delay vs. Breach

A

A simple delay in performance (e.g., late delivery) is typically considered a breach of contract, not frustration. The contract remains in force, and remedies for breach may be available.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Frustration: Delay as Frustration

A

Delay will only frustrate a contract if it is so significant in its nature or likely duration that it causes a fundamental change in the nature of the contractual obligation, making performance radically different.
Metropolitan Water Board v Dick Kerr: Extreme and unforeseen delay due to wartime government intervention frustrated the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Frustration: Delay - Relevant Factors

A

Courts consider several factors when assessing if delay frustrates a contract:
Contractual provisions addressing delay and its consequences.
Likely duration of the delay.
Timeframes specified within the contract.
Whether the contract, if resumed after the delay, would be radically different from the original agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Frustration: Difficulty/Expense

A

Mere increased difficulty or expense in performing the contract, even if substantial, is generally not sufficient to cause frustration. The core obligation must be fundamentally altered.
Tsakiroglou v Noblee Thorl [1962]: Increased shipping costs due to Suez Canal closure did not frustrate the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Frustration: Delay - Davis v Fareham

A

Significant labor and material shortages caused substantial delays and increased costs for contractors. Held: This amounted to hardship and inconvenience, but the obligation to build was not rendered “radically different,” so the contract was not frustrated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

pacta sunt servanda

A

agreements must be kept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Elements of Frustration

A

Supervening event must:
Make performance impossible or radically different (substantial change, not mere inconvenience).

Be beyond the ordinary risks (unforeseen, not reasonably anticipated).

Be beyond the control of either party (not self-induced).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

‘Radically Different’: Courts have categorized common frustrating events:
Government Intervention:

Frustration: Government Intervention

A

Changes in law or government actions making performance illegal or impossible.
Example: Sudden export ban.
Metropolitan Water Board v Dick Kerr [1918]: Extreme, unforeseen delay due to government intervention frustrated contract despite delay clause.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

‘Radically Different’: Courts have categorized common frustrating events -
Frustration: Unavailability of Specific Person

A

Incapacity (illness, death) of a specific individual essential for personal performance can frustrate contract.
Factors: following factors that will determine if a person’s unavailability will frustrate a contract: The length of the contract, The length of the period of absence, Whether or not a substitute can be used.

Morgan v Manser [1948]: Manager’s long absence due to war frustrated contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

‘Radically Different’: Courts have categorized common frustrating events - Illegality

A

Change in law making performance illegal.
Fibrosa v Fairbairn [1943]: Trading with the enemy during wartime frustrated contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

‘Radically Different’ - Destruction of Subject Matter

A

Physical destruction of the essential subject matter makes performance impossible.
Taylor v Caldwell (1863): Fire destroying music hall frustrated hiring contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

why else is Taylor v Caldwell important?

A

The modern law of frustration is often said to date from the decision in the case of
Taylor v
Caldwell (1863) 3 B & S 826. Blackburn J justified the decision by saying that the existence of the music hall was essential
for the fulfilment of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

‘Radically Different’ - Non-Occurrence of Fundamental Event (Frustration)

A

If a contract’s purpose is based on a specific event that does not occur, the contract may be frustrated. Krell v Henry [1903] 2 KB 740: A room hired to view a coronation procession was frustrated when the procession was cancelled. The coronation was the foundation of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

‘Radically Different’ - Non-Occurrence of Fundamental Event (No Frustration)

A

If contract has multiple purposes and some remain achievable despite event non-occurrence.

Herne Bay Steamboat Co v Hutton [1903] 2 KB 683: In contrast, a boat trip to view a naval review was not frustrated when the review was cancelled, as the cruise itself was still possible. The contract had multiple purposes, one of which remained achievable. This highlights the importance of the contract’s primary purpose.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Possible restrictions for frustration: Limitations - Foreseeability

A

If parties foresaw or should have reasonably foreseen the event, frustration is less likely. Can arise through express provision or lack thereof.

The Eugenia [1964] 2 QB 226: A ship trapped in the Suez Canal during the Suez Crisis was not frustrated, as the risk of closure was foreseeable.

17
Q

Foreseeability - Express Provision (Force Majeure Clause) - General

A

Clauses dealing with events outside parties’ control (war, strikes, disasters). If clause covers the specific event, contract usually not frustrated; clause governs consequences.

Note, however, that a clause cannot prevent frustration applying in the event of the contract becoming illegal, eg because of outbreak of war as in the case of Fibrosa which we looked at earlier

18
Q

Foreseeability: Force Majeure Advantages

A

Flexibility: Can cover more events than legal frustration (e.g., shortages of labour). Yet Davis Contractors v Fareham
UDC showed that shortage of labour and materials did not cause the contract to be frustrated as
the contract had not become radically different

Control over Consequences: Parties decide outcomes (suspension, termination, loss allocation - greater certainty than Frustrated Contracts Act).

Certainty: Clear list of “force majeure” events reduces ambiguity.

19
Q

Foreseeability: Force Majeure Drafting & UCTA

A

Drafting: Must be carefully worded to cover intended events (Metropolitan Water Board v Dick Kerr - delay clause insufficient).
UCTA 1977 s. 3: In B2B, force majeure clauses limiting/excluding liability subject to reasonableness test.

20
Q

Foreseeability: Foreseen but No Clause

A

Conflict in case law:
Lord Radcliffe (Davis v Fareham): Foreseen event prevents frustration.
Lord Denning (The Eugenia - obiter): Foresight doesn’t necessarily prevent frustration if no specific provision made.

21
Q

Restriction 2 - The Event Must Be Beyond the Control of the Parties (Not Self-Induced)

A

Frustration cannot be caused by a party’s own act or election. “Self-induced frustration” does not discharge the contract.

22
Q

Self-Induced Frustration: Effect & Rationale

A

Effect: Contract not ended. Party causing the event is in breach for non-performance.
Rationale: Prevents parties escaping liability through their own fault.

23
Q

Self-Induced Frustration: Maritime Fish v Ocean Trawlers

A

Limited licenses allocated to own vessels, leaving hired vessel unusable. Held: Frustration was self-induced by claimant’s choice.

24
Q

Self-Induced Frustration: The Super Servant Two

A

One transport vessel sank (no fault). Defendant chose to allocate remaining vessel to other contracts, making claimant’s impossible. Held: Self-induced by defendant’s allocation choice (criticized as potentially too strict). t seems that any act by a party which
contributes to the event will prevent the contract from being frustrated. This shows the narrow
limits within which the doctrine of frustration operates and the advantage of inserting a
force
majeure clause in the contract to avoid liability

25
Self-Induced Frustration: Burden of Proof
Party alleging self-induced frustration by the other bears the burden of proving fault. Authority: Joseph Constantine v Imperial Smelting.
26
Frustration: Leases of Land
Can apply to leases, but rarely (National Carriers Ltd v Panalpina (Northern) Ltd [1981]). Significant disruption alone is insufficient if a substantial portion of the lease term remains.
27
Conclusion: Restrictions on Frustration
Restrictions, especially strict view on self-induced frustration, highlight the narrow scope of the doctrine. Reinforces the practical benefit of using well-drafted force majeure clauses for managing unforeseen events.
28
Effect of frustration: Automatic Discharge
The contract is automatically discharged at the precise moment the frustrating event occurs. This happens by operation of law, without the need for any action by the parties. Consequently, future obligations under the contract cease for both parties from that point onwards.
29
Effect: No Breach Remedies
Because frustration occurs due to an unforeseen event beyond the parties' control, neither party is considered to be in breach of contract regarding the frustrating event itself. Therefore, standard remedies for breach, such as claims for damages, are not available in respect of the non-performance caused by the frustration.
30
Financial Ramifications (Common Law): Total Failure
Fibrosa Spolka Akcyjna v Fairbairn Lawson Combe Barbour Ltd [1943]: Introduced the principle that money paid is recoverable if there has been a total failure of consideration (the performing party has received nothing of what they contracted for).
31
Law Reform (Frustrated Contracts) Act 1943
Legislation enacted to govern the financial consequences of contract discharge by frustration, aiming to provide a fairer outcome than the common law. It allows for the recovery of sums paid before the frustrating event and provides for compensation for expenses incurred.
32
Frustrated Contracts Act 1943: s. 1(2)
Money paid before the frustrating event is recoverable. Money that was due to be paid before the frustrating event ceases to be payable. The court has discretion to allow the party who incurred expenses before the frustrating event to recover a just sum for those expenses from the money paid or payable. **Gamerco SA v ICM/Fair Warning (Agency) Ltd [1995]: Illustrates the court's broad discretion in awarding expenses under this section.
33
Frustrated Contracts Act 1943: s. 1(2) Weaknesses
Recovery of expenses is limited to the amount of money paid or payable before the frustrating event. There is a lack of clear guidelines on how the court should exercise its discretion in awarding expenses, leading to potential unpredictability.
34
Frustrated Contracts Act 1943: s. 1(3)
If one party has conferred a valuable benefit (other than money payment) on the other party before the frustrating event, the court may order the benefiting party to pay a just sum for that benefit. The award cannot exceed the value of the benefit. The court will also consider any expenses incurred by the benefiting party in relation to the benefit. **BP Exploration Co (Libya) Ltd v Hunt [1979]: Outlines a two-stage process: 1) Identify and value the benefit conferred (the end product of the services, not just the work done). 2) Assess a "just sum" to be paid, taking into account the expenses incurred by the benefiting party.
35
Frustrated Contracts Act 1943: s. 1(3) Weaknesses
There is difficulty in predicting the amount the court will award for a valuable benefit. Valuing the "end product" of services, rather than the work done, can sometimes lead to unfair results. These weaknesses further encourage the use of force majeure clauses to provide more certainty.
36
Frustrated Contracts Act 1943: s. 2
Parties can expressly exclude the operation of the Act by including specific clauses in their contract (e.g., comprehensive force majeure clauses). The Act does not apply to certain types of contracts, including some charterparties (contracts for hiring ships) and contracts of insurance. In assessing losses, any sums paid or payable under a contract of insurance are to be disregarded, unless the insurance was specifically required by the frustrated contract. **Gamerco SA v ICM/Fair Warning (Agency) Ltd [1995]: Confirmed that if insurance was not contractually required, insurance payouts received by a party are ignored when calculating recoverable expenses under the Act.