*Utility Relocation Quiz Flashcards
- Master Agreements are normally used on what type of project?
a. Freeway
b. Conventional Highway
c. Expressway
d. Any of the above
d. Any of the above
Answer: 13.04.03.01
- Utility Relocation plans can be designed by
a. utility coordinator
b. project development
c. utility owner
d. both B and C
d. both B and C
Answer: 13.03.04.00
b. project development
c. utility owner
- Utility Coordinator’s responsibilities include all but one of the following:
a. obtain encroachment permits
b. ensure relocation is done by the due date
c. write relocation plans on behalf of the Owner
d. coordinate with Construction for inspection of relocation work
c. write relocation plans on behalf of the Owner
Answer: 13.01.01.01
- When do Utility Agreements have to be amended?
a. only when it is determined necessary by Audits
b. when the Utility Owner notifies the coordinator that their costs are over original estimate.
c. If the final relocation costs exceed 25% of original estimate
d. Never
c. If the final relocation costs exceed 25% of original estimate
Answer: 13.07.05.01
- The primary purpose of the JUA/CCUA is what?
a. perpetuate the State’s rights
b. perpetuate the Owner’s rights
c. determine liability
d. all of the above
b. perpetuate the Owner’s rights
Answer: 13.11.02.00
- A _______ is used when the Owner’s facility will remain on lands used for highway purposes but will be relocated to a position outside, or partly outside, the Owner’s existing right of way where the Owner had prior rights?
a. CCUA(Consent to Common Use Agreement)
b. MOS (Memorandum of Settlement)
c. JUA (Joint Use Agreement)
d. Permit to Enter
c. JUA (Joint Use Agreement)
Answer: 13.11.02.01
- When is the Utility work performed on a project (timing)?
a. Before Construction
b. After Construction
c. During Construction
d. A and C
e. all of the above
e. all of the above
Answer:
- State owned facilities are always considered exempt?
TRUE FALSE
FALSE
Answer:
- State does not pay for _______ of facility, unless such an increase was a project ______ forced on the owner.
a. enlarging
b. improving
c. betterment
d. functional
c. betterment
Answer: 13.04.05.06
- If a Utility Owner has to relocate their facilities with-in _____, the State is liable for these relocation costs.
a. 7 years
b. 15 years
c. 10 years
d. Never
c. 10 years
Answer:
- When does Caltrans allow utility functions to remain longitudinally within the state right of way without the approval of the Chief, Encroachment Exceptions, Division of Design?
a. only on freeways (access restricted)
b. conventional roads
c. on both conventional roads and freeways
b. conventional roads
Answer: 13.03.04.01
- The ______ is utilized by the R/W Agent to order a utility company to remove, adjust, relocate or abandon its facilities with the State’s proposed highway construction area by a specified date to accommodate a project.
a. Utility Agreement
b. Encroachment permit
c. Notice to Owner
d. Right of entry
c. Notice to Owner
Answer: 13.06.01.00
- Master Agreements are an important factor in determining Prior and Superior Rights?
TRUE FALSE
FALSE
Answer: 13.04.01.01
- An Encroachment is a non highway structure or object which is placed in, under or over any portion of the highway.
TRUE FALSE
TRUE
Answer:
- The current Freeway Master Contract totally replace statues in determining cost liability on utility relocation for freeway projects?
TRUE FALSE
TRUE
Answer: Table 13.04-1
- Toxic or flammable gases are considered to be high risk.
TRUE FALSE
TRUE
Answer:
- The Utility Agreement addresses the following credits:
a. salvage, betterments and master agreement
b. depreciation, salvage and betterments
c. pole counts and master agreements
d. appreciation, salvage and betterments
b. depreciation, salvage and betterments
Answer: IV-8
- Four Criteria that are considered when determining property rights liability are Superior Rights, Special State Laws, Master Contracts and Pole Count Method?
TRUE FALSE
TRUE
Answer:
- Which statement is true regarding the Pole Count Method?
a. The Pole Count method is always a factor in determining liability.
b. Poles in the before condition are used to determine percentages.
c. Poles in the after condition are used to determine percentages
d. The pole count method can be used in conjunction with a Master Agreement to determine utility liability.
b. Poles in the before condition are used to determine percentages.
Answer:
- Utility Activities can be considered another form of property right acquisition?
TRUE FALSE
TRUE
Answer: Table 13.03-3
- The Project Engineer’s Certification of Utilities must be submitted to the Office of the Office Engineer of the Engineering Service Center prior to which stage of the project:
a. 65% PSandE
b. Right of Way Certification 3
c. PA and ED
d. Ready To List (RTL) date
e. Project Report Approval
b. Right of Way Certification 3
Answer: Project Development Procedures Manual (PDPM)
- A pole belonging to ATandT located within the right of way of an existing conventional highway in a rural area must be relocated for a SHOPP sponsored project. The pole is currently within the right of way as an encroachment and the planned relocation outside the right of way will be permanent. What should the RW coordinator do?
a. To issue a new encroachment to ATandT for a different portion of the highway to mitigate ATandT’s loss of service at its current location
b. To pay 50% of the cost to relocate the pole outside the right of way, where ATandT will then be responsible for obtaining new encroachment rights
c. To issue a Notice to Owner to ATandT to relocate
d. The Project Engineer must verify ATandT’s facility and advise ATandT how to relocate the pole so that it will continue to function with other poles still within the right of way but outside the project area
c. To issue a Notice to Owner to ATandT to relocate
Answer: 13.06.00.00
- TRUE or FALSE: If the State’s project design changes within 6 months of the relocation, and a subsequent relocation is necessary, ATandT must pay 100% of the cost for the second relocation since the pole is entirely outside the right of way.
FALSE
Answer:
- A project to install new traffic signals and minimal widening is taking place along a conventional highway, which also serves as a city street in an urban area and is going to require excavation. Part of the project will require old sewer lines that were installed in the city street before it was adopted as part of the State Highway System are not up to building code and will need to be replaced. New sewer lines will need to be installed for the private owners affected by the State’s project. What is the State’s obligation to the private property owner?
a. The State has no obligation since the City allowed the property owners to maintain substandard sewer lines after the route was adopted
b. The State and City must provide 50% of the cost to replace the sewer lines as the owner is not responsible for the State’s project
c. The State provides 100% reimbursement to the property owner for the original damages but the property owner must pay for the amount it will cost to bring the sewer lines up to code
d. The State’s construction contractor will replace the sewer lines up to codes as part of the construction contract
d. The State’s construction contractor will replace the sewer lines up to codes as part of the construction contract
Answer: Streets and Highway Code 703 (S and H 703)