Week 12: Engineering surveying II Flashcards
(54 cards)
The various lines in roading alignments
- Centre line
- Shoulder road, kerb, boundary, etc
- Edge of earthworks (top of cut, toe (bottom) of fill
Traditional method of roading alignments
Work off centreline or specific position
How to obtain coordinates in roading alignments
- Engineering software pre-calcs coords
- Set out by TS from random setup point
- GNSS
Machine control in roading alignments
No stakes at all - checks very important plus site control
Batter staking (AKA slope staking) involves
Marking edge and slope of cuts and fills, which is used for roads and building platforms
Examples of batter staking methods
Slope rails, sight rails, slope stakes, batter boards
Cuts usually define
The actual line of the slope
Fills usually used with
A boning (traveller) road or laser line
Anywhere that there is either dirt/rock being removed or brought in requires
Batter stakes
Types of cross section areas
Cut, Fill, Cut and fill
Batter staking: Basic slope staking process (for a roadway) Steps 1-8
- Get a first guestimate of position of catch point from X-section or from plan (i.e distance from CL or eye. This position is temporary
- Measure to this first temporary position (Tape, TS, GPS)
- Tie this position - determine RL and measure offset from CL (or feature if not for a road (e.g corner of building))
- Calculate the ‘calculated’ offset at this particular RL
- Try a new temporary position and determine new RL and offset
- Repeat until you find the correct catch point
- When catch point is found set a small marker stake at the catch point and label with c/f details
- Offset the catch point with sight rails - note these offset stakes are actually more important than catch point stakes. Catch point stakes will likely get destroyed during earthworks.
Batter staking is iterative, meaning
Will have to move to correct position, e.g if the position measured is at 22m and the RL calcs it to be 24m then move back 2m if ground was flat
Process for placing sight rails (offset stakes)
- Set out two stakes approx. 1 and 2m back from peg at catch point
- Tie to the top of the stakes
- Calculate the distance from the top of the stake to the design level
When setting out two stakes for sight rails what three things need to be done
- Need to know distance to be able to calculate RL
- These stakes are put in perpendicular to the centreline alignment (radially in curves)
- Allow room for earthmoving machinery
When tying to the top of the stakes, what three things need to be done
- Determine the offsets from the centreline
- At these offsets, calc the deisgn level of batter as if it passed through these stakes
- Allow for the boning rod length to be used (in fill section)
When calculating the distance from the top of the stake to the design level, what three things should be done
- Measure down from the tops of the stakes - aka the dip
- Mark these levels on both stakes
- Nail the sight rail so that its upper edge is on this design c/f line (on cut exactly, 1m above fill line)
Reasons for marking the batter stakes consistently
- To show CL offset and distance to catch point
- Very important to note whether the cut/fill is to finish grade or subgrade
Batter stake marking should show important information such as
- Offset distance to catch point
- C/F to toe/top from catch
- Offset distance to CL slope batter
You/contractor can mark the actual cut/fill line with
Spray paint (i.e top of cut or toe of fill on the ground)
Make sure the contractor knows how to
Interpret the batter stakes to avoid any confusion
Batter staking fieldnotes will show
- Catch point - distance from CL (L or R) and RL
- Slope rail stakes - offset and RL of front stake
- Dip down from top of stake to design line
- Offset from front stake to catch point (top of cut or toe of fill)
Batter staking summary for a job, e.g stake cut batter for a building platform
- Set out corners of building
- Building platform RL from plan and distance offset to toe of slope
- Horizontal position of top of cut determined from plot or ‘guestimate’
- Go to this position. Determine RL of peg and then calc total distance along slope and offset from building. The calc distance and measured position distance need to be identical
- If not found, repeat and try again
- When you find catch point set out catch point stakes and offset batter stakes
- Calculate height of design surface at the slope stakes and place sight rail to match batter slope
Uses for GNSS in batter staking
Know whats happening on site, what are you marking out or feeding as a file into earthwork machinery
Be careful of small/low marks because
They could be stripped out with topsoil at some point. Consider batter staking with GNSS even if perhaps less intuitive.