Week 12: Engineering surveying II Flashcards

(54 cards)

1
Q

The various lines in roading alignments

A
  1. Centre line
  2. Shoulder road, kerb, boundary, etc
  3. Edge of earthworks (top of cut, toe (bottom) of fill
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Traditional method of roading alignments

A

Work off centreline or specific position

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How to obtain coordinates in roading alignments

A
  1. Engineering software pre-calcs coords
  2. Set out by TS from random setup point
  3. GNSS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Machine control in roading alignments

A

No stakes at all - checks very important plus site control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Batter staking (AKA slope staking) involves

A

Marking edge and slope of cuts and fills, which is used for roads and building platforms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Examples of batter staking methods

A

Slope rails, sight rails, slope stakes, batter boards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cuts usually define

A

The actual line of the slope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Fills usually used with

A

A boning (traveller) road or laser line

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Anywhere that there is either dirt/rock being removed or brought in requires

A

Batter stakes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Types of cross section areas

A

Cut, Fill, Cut and fill

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Batter staking: Basic slope staking process (for a roadway) Steps 1-8

A
  1. Get a first guestimate of position of catch point from X-section or from plan (i.e distance from CL or eye. This position is temporary
  2. Measure to this first temporary position (Tape, TS, GPS)
  3. Tie this position - determine RL and measure offset from CL (or feature if not for a road (e.g corner of building))
  4. Calculate the ‘calculated’ offset at this particular RL
  5. Try a new temporary position and determine new RL and offset
  6. Repeat until you find the correct catch point
  7. When catch point is found set a small marker stake at the catch point and label with c/f details
  8. Offset the catch point with sight rails - note these offset stakes are actually more important than catch point stakes. Catch point stakes will likely get destroyed during earthworks.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Batter staking is iterative, meaning

A

Will have to move to correct position, e.g if the position measured is at 22m and the RL calcs it to be 24m then move back 2m if ground was flat

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Process for placing sight rails (offset stakes)

A
  1. Set out two stakes approx. 1 and 2m back from peg at catch point
  2. Tie to the top of the stakes
  3. Calculate the distance from the top of the stake to the design level
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When setting out two stakes for sight rails what three things need to be done

A
  1. Need to know distance to be able to calculate RL
  2. These stakes are put in perpendicular to the centreline alignment (radially in curves)
  3. Allow room for earthmoving machinery
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When tying to the top of the stakes, what three things need to be done

A
  1. Determine the offsets from the centreline
  2. At these offsets, calc the deisgn level of batter as if it passed through these stakes
  3. Allow for the boning rod length to be used (in fill section)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When calculating the distance from the top of the stake to the design level, what three things should be done

A
  1. Measure down from the tops of the stakes - aka the dip
  2. Mark these levels on both stakes
  3. Nail the sight rail so that its upper edge is on this design c/f line (on cut exactly, 1m above fill line)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Reasons for marking the batter stakes consistently

A
  1. To show CL offset and distance to catch point
  2. Very important to note whether the cut/fill is to finish grade or subgrade
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Batter stake marking should show important information such as

A
  1. Offset distance to catch point
  2. C/F to toe/top from catch
  3. Offset distance to CL slope batter
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

You/contractor can mark the actual cut/fill line with

A

Spray paint (i.e top of cut or toe of fill on the ground)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Make sure the contractor knows how to

A

Interpret the batter stakes to avoid any confusion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Batter staking fieldnotes will show

A
  1. Catch point - distance from CL (L or R) and RL
  2. Slope rail stakes - offset and RL of front stake
  3. Dip down from top of stake to design line
  4. Offset from front stake to catch point (top of cut or toe of fill)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Batter staking summary for a job, e.g stake cut batter for a building platform

A
  1. Set out corners of building
  2. Building platform RL from plan and distance offset to toe of slope
  3. Horizontal position of top of cut determined from plot or ‘guestimate’
  4. Go to this position. Determine RL of peg and then calc total distance along slope and offset from building. The calc distance and measured position distance need to be identical
  5. If not found, repeat and try again
  6. When you find catch point set out catch point stakes and offset batter stakes
  7. Calculate height of design surface at the slope stakes and place sight rail to match batter slope
23
Q

Uses for GNSS in batter staking

A

Know whats happening on site, what are you marking out or feeding as a file into earthwork machinery

24
Q

Be careful of small/low marks because

A

They could be stripped out with topsoil at some point. Consider batter staking with GNSS even if perhaps less intuitive.

25
What principle a surveyor should think of while batter staking
Does the plan or set out make sense 1. Look at computer plan/plan for machine guidance, check, check, check 2. Look back at marks in the field to ensure they make sense
26
Uses of profile boards
1. Set out to mark building lines 2. Foundation lines, column lines 3. String lines between nails 4. Place outside the construction area 5. They are considered semi-permanent
27
Profile boards are typically what sized wooden boards
150mm x 25mm (6"x1")
28
Problems created from use of profile boards
1. Offset from corner not known 2. Can't (and don't want to) set out boards at a predetermined position
29
Do the offset boards need to be at a pre calcd position
No
30
Profile boards should be installed with
Nails into boards, and string between (check diagonals to confirm)
31
Profile boards can be used for what control of the building
Horizontal and vertical control
32
Always work with a ____ to give them exaclty what they need and want
Contractor
33
Ten steps to profile boards setout (iterative)
1. Set out approx corner of building by coordinates, body offsets, etc 2. Build profile boards at appropriate position 3. Mark approx line of building on board (within 300mm) 4. Use instrument (orientated) then survey fix (i.e survey to) this position 5. Calc position of true line wrt this point 6. Calc small shift required 7. Mark final position on board (pencil) 8. Plaxe nail at this point 9. Survey fix this nail to check position 10. Record final position (not iterations)
34
Two profile board checks on the ground (quick and simple)
1. String the profile boards (same as builder) and check the plan building measurements 2. Measure the diagonals
35
Profile board check by calculation
Tie to the profile nails, compute intersections from these to determine corners of buildings. Then take a join between building corners, check distances are correct against plan dimensions, and bearings are 90 degrees different.
36
In high rise buildings, three things are important to set out for and be vigilant about
1. Establishment and upkeep of control grid lines 2. Verticality of columns 3. Establishment and maintenance of RLs 4. Precise linework is very important
37
Four methods for controlling verticality
1. Plumb bob 2. Theodolite 3. Specialized plummet 4. Total station
38
Plumb bob verticality method
1. Heavy plumb bob (2 kg) is suspended from piano wire over a known location 2. Knock out or leave out holes (500mm^2) are left in a corner (s) of the building floors for observing and measuring from (4 ideal) 3. Plumb bob immersed in water or oil to dampen the movement caused by wind 4. Plumb bob line marks a baseline from which measurements are made
39
Plumb bobs are used for lower height buildings of how many stories
3-4
40
Theodolite verticality method
1. Set up on peg P4 and sight to peg P3 on LF 2. Transit up the building and mark on column, repeat process on RF. 3. Take mean position if the theodolite is out of adjustment 4. Set up on P2, sight P1 and repeat procedure and mark column 5. Mark the centreline intersections of the rest of the building 6. Once the CL is established, measurements are made from that to establish any position within the building
41
The special theodolite attachment used to establish a vertical line and extend lines
Pentraprism and counterweight (balance) attached to wild T2 instrument
42
The pentraprism (on eyepiece) accurately transfers line
Both up and down
43
Accuracy of pentraprism
1 : 50,000 RF
44
Specialized plummet is a specialist instrument that sets out
Vertical lines
45
A specialized plummet can be either
Optical or Laser
46
Optical plummet sights ____, while high power telescope looks ____
Sights downwards (nadir), looks upward (zenith)
47
For specialized plummet, what is required as with any optical plummet
1. Holes in each floor 2. Adjustments need to be made
48
For specialized plummet, forced centring requires
Removing plummet from tribrach and insert TS for more work
49
Accuracy of specialized plummet
RF 1 : 30,000 +
50
Issues with specialized plummets
1. Floor holes need to be kept open 2. Watch for refraction - more serious next to the instrument rather than the target, e.g too close to concrete holes 3. Watch for divergence of laser beam
51
How to control verticality using a total station
Use of a free station
52
Five reasons for usage of a free station for verticality
1. Need lots of reduncancy 2. Ten stations if possible 3. High and low targets 4. Need targets on other buildings 5. Need constant checks
53
Issues of a free station
1. Buildings move with heat/cold 2. Concrete and steel moves 3. Control target safety
54
Methods of controlling high rise buildings
1. Static and RTK GPS 2. Dual axis precise clinometers - measure +_ 0.2" of arc 3. Robotic total stations 4. Everything connected to computer for constant, dynamic modeling of structure as it is being built