Week 4, chap 7,8,9,10,13,14 Flashcards

(58 cards)

1
Q

What is the difference between a plan and a strategy?

A

Strategy: states the overall decisions on how to achieve the desired impact

Plan: describes the steps required to reach the goal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name 8 elements included in a project plan.

A
  1. Purpose and goals
  2. Scope and delimitations
  3. Requirements specification
  4. Delivery and implementation
  5. Situational analysis and stakeholders
  6. Organization and staffing
  7. Communication
  8. Milestones
  9. Activities
  10. Schedule
  11. Budget and benefit assesment
  12. Risk analysis
  13. Routines for change management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Describe a Sequential development planning model/Waterfall planning modell.

A

One activity has to be completed and approved before next one starts. Takes usually to long time to work in the real world. Low risk!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Describe a concurrent engineering planning model.

A

Develop different parts of a project simultaneously. Quicker method but risk that the different parts doesn’t fit together.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Describe a rolling wave planning model.

A

Only the closest time period is planned in detail, activities happening later on are only planned at a general level to be planned for later. Good when operating in a changing environment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Describe an agile sprint planning model.

A

You plan for one sprint at a time, 2 - 4 weeks. Suitable when you don’t know what the solution will be, you develop the plan as you go.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the 8 steps in the planning chain?

A
  1. Determine the purpose and goal
  2. Define the scope of the project
  3. Compare with requirements
  4. Create a logical network
  5. Plan activities
  6. Draw up a schedule
  7. Map out resource needs
  8. Estimate costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 5 resources usually needed in projects?

A
  1. Project members
  2. Equipment
  3. Materials
  4. Time
  5. Money
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does a Gantt chart illustrate and how is it used?

A

It is an activity plan with a timeline. Activities are specified with duration, start and finish times. Activities are illustrated as bars, milestones as markers and dependencies as arrows.

It is used for achieving good prerequisites for producing a realistic schedule and help to plan for resources needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does a logical network illustrate and why is it used?

A

It shows how and which activities depend on each other. Work packages that have logical dependencies are placed in the same network, otherwise they are in parallel networks. Help to know in what order things need to be executed in the activity list.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does a resource histogram illustrate and why is it used?

A

Shows the resource usage over time. Helps you to see if there is an uneven use of resources over time in the projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does a Work Breakdown Structure illustrate and why is it used?

A

The project goals are broken down into smaller parts, which is illustrated in a hierarchical structure. Facilitates the work of identifying activities and milestones.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Name two strategies to estimate uncertainties. Explain.

A

Lischtenberg and PERT. Used when time is an uncertainty. Estimate maximum, minimum and likely value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why is it risky to have the project manager select the project group?

A

He or she might only choose people they have worked with before. Not be objective enough.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In a well-functioning matrix organization, how should the process of staffing the project group take place?

A

The PM decides and inform how many and what kind of resources he needs. Then the line manager (resource owners) choose and allocate the asked employees.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a procurement process?

A

Its a process for acquire resources/material/equipment externally. Usually begins with a request for proposal to the supplier assessed and end with a signed contract with the best supplier.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the 5 questions that should be answered ahead of procurement?

A
  1. Is procurement required?
  2. What is to be procured?
  3. How will procurement be performed?
  4. When will procurement be performed?
  5. Who is the supplier?
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are the different basic phases of a negotiation process?

A
  1. Planning
  2. Exchange of information (ask questions, communicate)
  3. Bargaining (If.. then)
  4. Closure (be detailed)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the difference between project costs and product costs?

A

Project costs = resources in the project

Product costs = materials needed to produce the project (the result of the project)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is “the lifecycle cost”?

A

All costs arising during all phases of a product’s lifecycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the two strategies to estimate costs during the planning phase of a project?

A

Top-down (base estimate on costs on other similar projects already executed)

Bottom-up (base estimate on a detailed analysis of each activity in the project)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the difference between direct and indirect costs?

A

Direct costs: can be assigned to a specific activity

Indirect costs: overhead costs, shared bu several activities or cost bearers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is a self-costing estimate?

A

The project should bear all of its own costs - both direct costs and a fair share of the company’s overhead

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Why does the project triangle play a big role when planning costs?

A

To know which requirements should be prioritized. The budget probably can’t cover all requirements asked for.

25
What is a contribution estimate and why is it useful?
The project is being responsible only for the specific costs (costs that arise only if the project is executed). Useful when trying to choose and prioritize between different projects.
26
What is a specific revenue?
The revenue that arises through the execution of the project
27
What is a specific cost?
Costs that arises only if the project is executed
28
How is the contribution margin calculated?
Specific revenue - Specific cost = contribution margin
29
How is the financial result calculated?
Revenue - Cost = financial result
30
Why is the activity plan useful when estimating costs?
You can put a price in the planned resources and multiply it by the time the resources are needed -> easier to keep track on costs if an activity changes.
31
How is the cost for a Scrum team calculated?
Sprint duration * No of developers in the team * Cost/day/developer
32
How is the cost for an agile project calculated?
No of sprints + Cost for time of project owner
33
What is a resource histogram and how can it be used during planning?
Shows an overview of the distribution of resources over time. Give us an estimate of project costs over time.
34
How can a resource histogram be used during execution?
It is used as information source in order to enable accrual-basis accounting.
35
How do you calculate the estimated average value according to Lichtenberg's method?
(Texpected) = (Tmax + 3 Tlikely + Tmin)/5
36
What are the values in Lichtenberg's method based on?
Experience from other projects or estimates from groups with members having different ideas of the final costs
37
What is the pay-off method and how can it be used?
You estimate the time that passes before a project has earned back the capital invested. Can be used when ranking different projects against each other.
38
What is the net present value method and how can it be used?
A method for estimating investments, taking into account payments and expenditures that occur in the future/at different time points. Recalculate the value of all expected payments and expenditures of the investment at a certain time.
39
What is the internal rate of return and how can it be used?
Determine the interest rate at which the net present value is zero. It reveals the annual ROI on the project.
40
Explain the difference between risk and uncertainty.
Risk = an uncertain event that it is unsure if it's going to occur or not, uncertain consequense Uncertainty = a known event that will have different outcomes depending on external or internal factors
41
Explain the process of risk identification.
Through risk identification, possible risk events are found. It is an iterative process that begins in the idea stage. It is best to use as many sources as possible to identify risks.
42
What are the four examples of risk categories in Tonnquist?
1. Risks related to technology, quality and execution 2. Risks related to project management 3. Organizational risks 4. External risks
43
Explain the difference between mini risk method and maxi risk method.
Mini: multiply the likelihood of a risk event happening with the value of the consequence. Focus on the risk events with the higher sum. Maxi: The consequense of each risk event is valued in 3 dimensions: Q, T, R.
44
Once risks have been identified, what is the next step to be done in the planning?
You need to find the probability of the risk event actually happening and the consequences they bring if they do. This is done through a qualitative and quantitative risk analysis.
45
What is risk response planning?
An action plan with strategies for realizing possibilities and handling risks.
46
What strategy should be used to prioritize risks?
Calculate the one with highest probability to happen together with highest value of consequence for the project.
47
Give four examples of risk response strategies.
1. Avoid risk - change the project plan. remove risk. 2. Transfer risk - shift to third party, ex insurance 3. Reduce risk - decrease the likelihood or consequence 4. Accept risk - no changes
48
What is Japanese quality philosophy?
Teach your customers to always ask for better service/goods. Forces companies to stay good.
49
Which three aspects do Quality management consists of?
1. Quality planning (triangle, level, ambition) 2. Quality assurance 3. Quality audit (Pareto chart) Purpose is to increase the quality in project work.
50
Which activities should be performed during execution?
1. Communicating and reporting 2. Following up and comparing results with schedules 3. Following up and comparing resources and costs with budget 4. Analysing consequences 5. Handling changes 6. Following up contracts and resources
51
What does RACI stands for?
A matrix where you define roles and who do what Responsible - the person in charge of execution Accountable - the person with mandate to approve and make decisions Consulted - the person who provides support as a resource Informed - the person who needs info on status and decisions
52
Name two of the methods for status reports.
Milestone chart - compare planned milestones with when they were completed in reality. Percentage work performed - assess how much of each activity that remains
53
Which are the 6 steps for keeping project costs under control?
1. Reporting and following up on actual costs as compared with the plan 2. Identifying deviations as compared with the plan 3. Identifying causes of deviations 4. Creating and implementing relevant measures 5. Follow up to see if the measures have fixed the problem 6. Creating further measures if necessary
54
What does implementation entail?
Placing the product in the environment it is created for
55
What are the three stages of an individual's attitude to change?
1. Excitement 2. Hangover 3. Positive attitude
56
What can be done to facilitate the process of an individuals resistance to change?
Get the organizations support - include informal leaders, use reference groups from different parts of the organization. Make sure the employees understand the purpose of the change and give them time to accept it.
57
Which activities can facilitate a successful hand-over?
1. A working change management 2. Established routines ensuring that goals and requirements have been met 3. Constantly keeping the stakeholders informed
58
What is the primarily goal of an administration and management model?
To manage and describe how administration work is to be performed. Use to control work and plan activities that are necessary for administration of the product.