Week 5 (Part 2) Flashcards
(5 cards)
1
Q
it is a major concern of the client
A
Probable Total Cost
2
Q
What are the probable total capital cost made up of
A
- professional engineering costs
- construction cost
- legal and land costs
- owner’s costs
- contingency allowance for unknowns
3
Q
it is the estimated total cost of constructing the facility to be covered by the proposed detailed design or supervision services
A
Construction Cost
4
Q
include audits, the cost of issuing bonds, land costs, and interest for borrowed money during construction
A
Legal, Land, Administration, Staffing and Financial Costs
5
Q
Add 20% or more to the estimated probable total project cost at the completion of the study and report phase.
Reduce to 10% at the completion of final design and perhaps 5% when the construction bids become known.
A
Contingency Allowance