Week 5 - Project Management 2 Flashcards
(83 cards)
What questions should be considered in risk management?
What is likely to happen?
What can minimise the probability or impact of these events?
What cues will signal the need for action?
What is risk management defined as?
The art of identifying, analysing and responding to risk factors throughout the life of a project and in the best interest of its objectives
What is project risk defined as?
An uncertain event or condition that if occurs may have a positive or negative effect on project objectives
What are common types of project risk?
Absenteeism Resignation Staff pulling away Time overruns Unavailable skills or poor training Incomplete specs Change of orders
What is a risk impact matrix?
It is a way of measuring risk, measuring the consequences and likelihood
What are some risk mitigation strategies?
Accept, minimise, share, transfer, contingency reserves, insurance, workaround, mentoring, cross training
What does control and documentation do?
Helps managers classify and codify risks, responses and outcomes
What are some common sources of project cost?
Labour, materials, subcontractors, equipment and facilities, travel
What are some problems with cost estimation?
Low estimates, unexpected difficulties, lack of definition, spec changes, external factors
What is contingency funding?
It is where funds are set aside for future unknowns, in case something unexpected happens
What are the benefits of contingency funding?
Recognises future unknowns, adds provision for plans for an increase in project cost, acts as warning signal to overdrawn budget
What does project scheduling require you to do?
Follow some laid-out steps in order to allow a schedule to take shape
What is project planning defined as?
The identification of the project objectives and the ordered activity necessary to complete the project
What is a project network diagram?
Any schematic display of the logical relationships of project activities
What is an early start date in project scheduling?
The earliest possible date an uncompleted activity can start
What is a late start date in project scheduling?
The latest possible date that an activity may begin without delaying a milestone
What is calculated in the forward pass of a project scheduling diagram?
Earliest start / earliest finish of an activity
What is calculated in the backward pass of a project scheduling diagram?
The late start / late finish data for a task in the network
What is the float in a Project Network Diagram?
The amount of time an activity may be delayed from its early start without delaying the finish of the project
What is the critical path in a project network diagram?
The path through the project network with the longest duration
What is the critical path method?
A network analysis technique used to determine the amount of schedule flexibility used to determine the minimum project duration
What does m, b and a stand for in beta distribution?
most likely (m) most pessimistic (b) most optimistic (a)
What is the formula for activity duration?
(a + 4m + b) / 6
where a is most optimistic, b is most pessimistic and m is most likely
What is the formula for calculating activity variance?
((b - a) / 6) ^ 2
where a is most optimistic, b is most pessimistic