Payment Flashcards

1
Q

Fundamental elements of payment

A

The Prices (how much are the works supposed to cost)

Defined cost (how much the works are currently projected to cost)

PWDD (what the contractor should be paid for the works in their partially complete state)

Disallowed cost (what the contractor requested but the PM has decided he are not entitled to receive)

Schedule of cost components (a way to recalculate the costs when things change) - not applicable to main option F as contractor is reimbursed for all payments to SC’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How does an activity schedule differ from a BOQ

A

Activity schedules have lump sums for items

BOQ’s have quantity, unit and rate info for items (more detailed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How do the prices, defined cost and the fee interact

A

The prices = defined cost + the fee

This does not apply to priced contracts (main options A and B)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Basis for cost dependent on main option

A

A & B - the Prices

C - F - defined cost + fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the fee

A

Single % given in CD part 2

Covers overheads, profit, tax, insurance etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the schedule of cost components

A

Submitted by contractor in CD part 2

Used to calculate the cost parts of works changed from the original intent in all main options excluding main option F

Example content:
People, equipment, plant and materials, design, insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is defined cost

A

The original intended costs (the Prices) and those incurred through CE’s

The contractor’s actual incurred cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is PWDD

A

Represents expenditure on the partially complete structure, determined differently dependent on the basis of payment (the Prices or defined cost + fee)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is disallowed cost

A

Costs that the contractor has asked to be paid, but the PM believes are unsupported by the contract

Deductions from contractor’s application for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Key payment term in Construction Act (payment cycle)

A

Part II payment cycle

Payment due within 7 days of relevant period

Payment notice within 5 days (becomes notified sum)

Payless notice no later than 7 days before final date for payment

Final date for payment is 17 days after due date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

NEC4 payment process

A

Contractor submits payment application before each assessment date detailing amount due and basis for calculation

PM certifies payment within 1 week of application

Client pays contractor within 3 weeks of certification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What if payment requires correction in later period

A

PWDD is altered accordingly in subsequent payment period

Interest is to be paid to the underpaid party

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How does NEC4 address client non-payment

A

Contractor has right to terminate

If they do not, they must continue as their obligations remain

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When is the first payment assessment

A

Within one assessment interval after the starting date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do final assessment intervals differ

A

Within 4 weeks of issuance of defects certificate from supervisor

Within 13 weeks of issuance of termination certificate from PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is amount due calculated

A

PWDD + any other amounts due to contractor - amounts to be paid by or retained from the contractor (50.3)

17
Q

How do priced contracts differ in their PWDD calculation

A

Priced contracts - Prices spent so far

Others - forecast of defined cost to be spent by next assessment date + the fee

18
Q

Failure to submit application

A

Amount due becomes lesser of:

PM assessment

Amount due at previous assessment date

19
Q

Amount due if client terminates contractor

A

Amount due includes “a deduction of the forecast of the additional cost to the client of completing the whole of the works” (93.2)