3.7 Contract Admin Flashcards

(16 cards)

1
Q

What is the JCT structure?

A

1- articles of agreement
2- particulars (filling in project specific)
3- Conditions
4- Schedules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the changes in the latest JCT?

A
  • Collaborative working
  • Gender neutral language
  • Target cost contracts
  • Electronic communications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who administers the JCT and NEC?

A

NEC is PM
JCT is Employer’s Agent or Contract Administrator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the NEC structure?

A
  • Core + W
  • Secondary + Y
  • Contract data 1 - client
  • Contract data 2 - contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the FIDIC structure?

A

Red book - construction
Yellow book - design & build
Silver book - engineering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Differences between the NEC3 and NEC4?

A
  • Allow emails as as formal communication
  • Final certificate
    Dispute avoidance board
    ECI
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the NEC main options?

A

A - Priced contract with activity schedule
B- Priced contract with BoQ
C - Target contract with activity schedule
D - Target contract with BoQ
E - Cost reimbursable
F - Management contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is change management under NEC?

A

Compensation even section 6
Clause 60 - 64

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How are risk managed under NEC?

A

Early warnings
Clause 15

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How is quality managed under NEC?

A

Defects - Clause 40

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the Y(UK) clauses?

A

Country Specific
1 - project bank account
2 - HGCR Act
3 - third party rights

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the rules under Construction Act?

A
  • Contracts don’t need to be written.
  • Pay-When-Certified axed.
  • Payment notice issued within 5 days of due date.
  • Payment notice calc shown even when it’s Nil.
  • Right to suspend work.
    -Default notices.
    -Pay less notice.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is an Early warning?

A

Clause 15
- increase in costs
- delay completion
- delay key date
- impair performance…

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is completion and planned completion?

A
  • Completion: done all the work and corrected notified defects
  • Planned completion: when the contractor plans to complete
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is loss and expense?

A

Direct Loss or expenses incurred due breach by others. NEC is the CE process. JCT is generally relevant matters and can include the following:
- Prolongation cost
- Disruption
- Finance charges
- Loss of profits
- Demonstratable overheads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the difference between relevant matters and relevant events?

A
  • RE - time only (possession of site)
  • RM - loss and expense (client disruption)