3.8 Risk Management Flashcards

(9 cards)

1
Q

What is a risk?

A

Probability or threat of liability, loss or any other negative occurrence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Example of risks?

A

Contractor - Materials/weather
Client - Funding fo the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Example of oportunity?

A

Coventry AQP - overlap with other delopment saving time in site clearance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the risk management routes?

A

Avoidance
Reduction
Transfer
Sharing
Retention

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is qualitative and quantitative risk management?

A

Used to analyse the significance of risks.
Qualitative - not including costing i.e. (Very High, High, Medium…)
Quantitative - costing up the risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are risk quanitification techniques?

A
  • Probability trees - used for dependant risks (linked)
  • Monte Carlo - computer generated simulation
  • Percentage addition - percentage of cost plan
  • Simple Method - a likely cost x probability
  • Probabilistic method - similar to simple x3 for best, likely and worst cases added up
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who is responsible for updating the Early Warning register?

A

PM and Contractor add to the register
PM revises the EW Register to incorporate the EW meeting notes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are Early Warning Notices?

A

Clause 15 notify the other ASAP of :
-increase in the total of the Prices
-delay to key dates
-delay to completion
-impair the perfomance of works in use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is time risk allowance?

A

Time a contractor adds to an activity duration to account for potential delays and risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly