3.8 Risk Management Flashcards
(9 cards)
What is a risk?
Probability or threat of liability, loss or any other negative occurrence
Example of risks?
Contractor - Materials/weather
Client - Funding fo the project
Example of oportunity?
Coventry AQP - overlap with other delopment saving time in site clearance
What are the risk management routes?
Avoidance
Reduction
Transfer
Sharing
Retention
What is qualitative and quantitative risk management?
Used to analyse the significance of risks.
Qualitative - not including costing i.e. (Very High, High, Medium…)
Quantitative - costing up the risk
What are risk quanitification techniques?
- Probability trees - used for dependant risks (linked)
- Monte Carlo - computer generated simulation
- Percentage addition - percentage of cost plan
- Simple Method - a likely cost x probability
- Probabilistic method - similar to simple x3 for best, likely and worst cases added up
Who is responsible for updating the Early Warning register?
PM and Contractor add to the register
PM revises the EW Register to incorporate the EW meeting notes.
What are Early Warning Notices?
Clause 15 notify the other ASAP of :
-increase in the total of the Prices
-delay to key dates
-delay to completion
-impair the perfomance of works in use
What is time risk allowance?
Time a contractor adds to an activity duration to account for potential delays and risks