NCIDQ Codes Systems Standards Contracts Flashcards

1
Q

Calcium Chloride test

A

common and inexpensive test method of determining concrete moisture, conducted by placing a standard mass of the referenced material underneath a plastic cover and sealing it to the concrete floor, then measuring the weight of the standard mass after a 72-hr period, also called the ‘moisture dome test’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Hygrometer test

A

also know as the relative humidity test; moisture of the concrete is assessed by measuring the relative humidity of the air directly adjacent to it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

polyethylene sheet test

A

a 1.5 foot square of plastic is laid atop the concrete for a period of atleast 16 hours. If condensation forms on the underside of the plastic, it is considered to be unacceptable for resilient flooring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In a commercial construction projects, wallboards are typically composed of

A

metal studs with 5/8”, 2 1/2 “, 3 5/8”, 4”, and 6”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Fire rated gypsum wallboard is often referred to as

A

Type X

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Electrical Impedance test

A

Determines the conductance and capacitance of concrete as a means of determining its moisture content.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

PH Test

A

Performed to gauge the alkalinity of the concrete, which normally has a PH level from 12-13.3. A Special paper strip is applied to the surface of the concrete; in order for resilient flooring to be applied, concrete needs to have a PH no higher than 9.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Granite

A

An igneous rock with visible grains; common colors include gray, beige, white, red, blue, green, and black. Five common finishes include: polished, honed, fine-rubbed, rubbed and thermal.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Marble

A

A metamorphic rock created when ancient shells are melted and mashed into a calcite or dolomite crystalline substance. 4 common finishes: Polished, hined, abrasive and wet-sand.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Limestone

A

More popular for exterior use. It is especially porous stone, it is often filled with resin when it is used as flooring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

slate

A

A fine-grained rock which can be divided easily into long thin slabs suitable for flooring. 3 common finishes: sand-rubbed, honed and natural cleft.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Sandstone

A

A sedimentary rock composed partly of sand. Is easy to cut into flat thin surfaces suitable for flooring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Hydrophobic fabric Wallcovering

A

do not absorb or retain moisture.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Sound transmission Class (STC)

A

the single-number rating of the ability of an object to dampen the transmission of sound.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Noise reduction Coefficient (NRC)

A

the single-number average of the coefficients absorption of a given material at 250HZ, 500HZ, 1000HZ and 2000HZ. This average is rounded to the nearest 0.05

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Reverberation Time

A

the interval required for the sound level in a space to drop by 60 db after the sound source has stopped production.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Articulation Class

A

indicates how well a ceiling absorbs sound coming over a wall.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Ceiling attenuation Class

A

is the single-number measure of the transmission loss through ceiling tiles between 2 closed rooms if the is no barrier above the suspended ceiling.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Freight bill

A

the invoice sent by a shipping company

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Bill of lading

A

indicates the contents of a shipment made by a manufacturer or vendor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Conforming goods

A

are the delivered goods as they are described in the sales agrement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Gravity Loads

A

(live loads, dead loads) all of the weight that depends on the structure of a building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Live Load

A

is calculated as the total combined weight of people, furniture & moveable equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Dead Load

A

is calculated as the total weight of the building components and immovable equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Lateral Loads

A

wind and seismic forces exerted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Dynamic Loads

A

A force that is applied rapidly or that fluctuates a great deal; Example - Cars moving around in a parking garage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Relief Joint

A

typically placed either at a mullion or perpendicular to a structural wall or column

28
Q

Slip joint

A

are placed at the top of a partition in order to compensate for deflection on the floors above.

29
Q

Connection

A

consideration of the manner in which the detail connected to the substrate; as well as the manner in which the various parts of the detail are connected.

30
Q

Structure

A

The ability of the detail to withstand the various forces that are likely to be applied to it during its lifecycle

31
Q

Movement

A

The ability of the detail to maintain its integrity despite movement due to settling, temperature, or humidity.

32
Q

Tolerances

A

The ability of a material used in detailing to vary from a given line indicated in the design documents.

33
Q

Clearances

A

The amount of space that has been left to accommodate the placement if a detail.in order for installation to be possible, a design needs to allow enough room for each subsequent element of construction to be added.

34
Q

Construction trade sequence

A

The order in which the construction task will be accomplished

35
Q

Designer Liability

A

The degree to which the designer is responsible for any errors made during detailing.

36
Q

Beam-and-Girder

A

concrete slab rests atop intermediate beams, which in turn are placed atop larger girders.

37
Q

Concrete Joist system

A

Concrete girders are framed into larger beams; the concrete girders are usually between 24 and 36 inches apart.

38
Q

Flat Plate construction

A

a concrete slab is placed atop the columns; in situations where floor to floor heights must be kept as small as possible, this type of construction is appropriate

39
Q

Flat Slab Construction

A

A concrete slab is placed atop the columns, a drop panel is placed near the column to improve strength.

40
Q

Waffle Slab Construction

A

waffle-like concrete slab resting atop columns; sometimes lighting systems are placed directly into the holes.

41
Q

Drop ship Order

A

this is completed when the company placing the order wants to have goods shipped to an address other than their own.

42
Q

Part I of the technical Specifications

A

General requirements for the section, scope of this section, submittals required, warranties, project conditions, the delivery specification and a protocal for storing and handling materials.

43
Q

Part II of the technical Specifications

A

Specifications for the materials and products (including approved manuf.), as well as the standards and test methods to which materials must conform and how they must be fabricated.

44
Q

Part III of the Technical specifications

A

describes how the products and materials are supposed to be installed or applied. Also includes the examination and preparation required before installation, the quality control protocols and the requirements for maintaining finished work.

45
Q

Division 4

A

Masonry, consideration of brick, stone, terra cotta, glass block and concrete block; including restoration and cleaning

46
Q

Division 5

A

Metals, consideration of all structured metals, ornamental metals and metal fabrications

47
Q

Division 6

A

Wood, Plastics and Composites, issuses related to framing, carpentry, woodwork, restoration and cleaning

48
Q

Division 7

A

thermal an moisture protection, consideration of moisture resistance, air barriers, fire and smoke protection and roofing supplies that influence heat and water retention.

49
Q

Division 12

A

Furnishings, Includes furniture, systems furniture, window treatments, accessories and indoor plants

50
Q

Division 13

A

Special Construction, Includes seismic control apparatus, rooms supported by air, lightning protection, hot tubs, kennels and planetariums

51
Q

Division 14

A

Conveying Equipment, elevators, escalator, lifts, and dumbwaiters

52
Q

Division 21

A

Fire Suppression, Fire detection devices, alarms and all sorts of fire-extinguishing systems

53
Q

Division 22

A

plumbing, includes all plumbing topics except those related to processing piping, which are covered in the process equptment subgroup.

54
Q

Division 00

A

procurement and contracting requirements; issues related to bidding and contracting

55
Q

Division 01

A

General requirements; all of the topics which apply to all of the subsequent individual sections; as well as general topics which apply to an interior design project

56
Q

Division 2

A

Existing Conditions; issues related to site decontamination, remediation, investigation and demolition.

57
Q

Division 3

A

Concrete; forms, reinforcement, precast concrete, cast-in-place concrete, grout, concrete restoration and concrete cleaning.

58
Q

Division 8

A

Openings; doors, windows, skylights, storefronts, curtains and glazing.

59
Q

Division 9

A

Finishes;plaster, gypsum, wallboard, floor tile, wall tile, terrazzo, acoustical ceilings and any other kind of decorative ceiling or wall covering

60
Q

Division 10

A

Specialties; interior Signage, grilles, toilet compartments, lockers, awnings and flagpoles

61
Q

Division 11

A

Equipment; vaults, vending machines, audio-visual, library resources, musical instruments, medical equipment, etc.

62
Q

Division 23

A

Heating, ventilation and air conditioning

63
Q

Division 25

A

Integrated Automation; energy control, lighting

64
Q

Division 26

A

Electrical

65
Q

Division 27

A

Communications; cable, telephone, internet and speaker systems

66
Q

Division 28

A

Electronic Safety and Security; consideration of intrusion detection systems and video surveillance systems.