6 Project Schedule Management Flashcards

(47 cards)

1
Q

The primary output of breaking down the

WBS work packages.

A

Activity list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The identification of more than one
solution. Consider roles, materials, tools,
and approaches to the project work.

A

Alternative analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A somewhat unreliable estimating approach that relies on historical information to predict what current activity
durations should be. It’s more reliable, however, than
team member recollections. It’s also known as top-down
estimating and is a form of expert judgment.

A

Analogous estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
The most accurate time-and-cost
estimating approach a project manager
can use. This estimating approach starts
considering every activity, its predecessor
and successor activities, and the exact
amount of resources needed to complete
each activity.
A

Bottom-up estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
A WBS entry that considers the time,
cost, and scope measurements for that
deliverable within the WBS. The
estimated performance is compared
against the actual performance to
measure overall performance for the
deliverables within .
A

Control account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A predetermined range of acceptable
variances, such as +/–10 percent off
schedule. If the variance exceed, then project
control processes and corrected actions will be
enacted.

A

Control threshold

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A schedule compression approach that
adds more resources to activities on the
critical path to complete the project
earlier. Costs are added because the associated
labor and other resources cause costs to increase.

A

Crashing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
The path in the project network diagram
that cannot be delayed, otherwise the
project completion date will be late. There
can be more than one.
Activities have no float.
A

Critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
These dependencies are the preferred
order of activities. Project managers
should use these relationships at their
discretion and should document the logic
behind the decision. Allow activities to happen
in a preferred order because of best
practices, conditions unique to the project
work, or external events.
A

Discretionary dependencies / Soft Logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The earliest a project activity can finish.
Used in the forward pass procedure to
discover the critical path and the project
float.

A

Early finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The earliest a project activity can begin.
Used in the forward pass procedure to
discover the critical path and the project
float.

A

Early start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
As the name implies, these are
dependencies outside of the project’s
control. Examples include the delivery of
equipment from a vendor, the deliverable
of another project, or the decision of a
committee, lawsuit, or expected new law.
A

External dependencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A schedule compression method that
changes the relationship of activities.
Activities that would normally be done in
sequence are allowed to be done in parallel or
with some overlap. It can be
accomplished by changing the relation of
activities from FS to SS or even FF or by
adding lead time to downstream
activities. However, it does
add risk to the project.

A

Fast tracking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

An activity relationship type that requires
the current activity to be finished before
its successor can finish.

A

Finish-to-finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

An activity relationship type that requires
the current activity to be finished before
its successor can start.

A

Finish-to-start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
A representation of a project network
diagram that is often used for outsourced
portions of a project, repetitive work
within a project, or a subproject. Also
called a subnet.
A

Fragnet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

This is the total time a single activity can
be delayed without affecting the early
start of its immediately following
successor activities.

A

Free float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
Logic that describes activities that must
happen in a particular order. For
example, the dirt must be excavated
before the foundation can be built. The
foundation must be in place before the
framing can begin.
A

Mandatory dependency / Hard logic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Internal relationships to the project or the
organization. For example, the project
team must create the software as part of
the project’s deliverable before the
software can be tested for quality control.

A

Internal dependencies

20
Q

Positive time that moves two or more

activities further apart.

21
Q

The latest a project activity can finish.
Used in the backward pass procedure to
discover the critical path and the project
float.

22
Q

The latest a project activity can begin.
Used in the backward pass procedure to
discover the critical path and the project
float.

23
Q

Negative time that allows two or more
activities to overlap where ordinarily
these activities would be sequential.

24
Q

A percentage of the project duration to
combat Parkinson’s Law. When project
activities become late, their lateness is
subtracted from the:

A

Management reserve

25
These dependencies are the natural order of activities. For example, you can’t begin building your house until your foundation is in place.
Mandatory dependencies / Hard Logic
26
A project simulation approach, predicts how scenarios may work out, given any number of variables. The process doesn’t actually churn out a specific answer, but a range of possible answers. It can examine, for example, the optimistic completion date, the pessimistic completion date, and the most likely completion date for each activity in the project and then predict a mean for the project schedule.
Monte Carlo analysis
27
``` A quantitatively based duration estimate that uses mathematical formulas to predict how long an activity will take based on the quantities of work to be completed. ```
Parametric estimate
28
``` A theory that states: “Work expands so as to fill the time available for its completion.” It is considered with time estimating, because bloated or padded activity estimates will fill the amount of time allotted to the activity. ```
Parkinson’s Law
29
A WBS entry located below a control account and above the work packages. Signifies that there is more planning that needs to be completed for this specific deliverable.
Planning package
30
``` A network diagram that shows activities in nodes and the relationship between each activity. Predecessors come before the current activity, and successors come after the current activity. ```
Precedence diagramming method
31
Calendars that identify when the project | work will occur.
Project calendars
32
This is the total time the project can be | delayed without passing the customer expected completion date.
Project float
33
A diagram that visualizes the flow of the project activities and their relationships to other project activities.
Project network diagram
34
An update to the work breakdown | structure.
Refinement
35
``` This is a hierarchical breakdown of the project resources by category and resource type. For example, you could have a category of equipment, a category of human resources, and a category of materials. Within each category, you could identify the types of equipment your project will use, the types of human resources, and the types of materials. ```
Resource breakdown structure (RBS)
36
Calendars that identify when project resources are available for the project work.
Resource calendars
37
``` A method to flatten the schedule when resources are overallocated. It can be applied using different methods to accomplish different goals. One of the most common methods is to ensure that workers are not overextended on activities. ```
Resource-leveling heuristic
38
The imminent work is planned in detail, while the work in the future is planned at a high level. This is a form of progressive elaboration.
Rolling wave planning
39
A subsidiary plan in the project management plan. It defines how the project schedule will be created, estimated, controlled, and managed.
Schedule management plan
40
The activities don’t necessarily have to happen in a specific order. For example, you could install the light fixtures first, then the carpet, and then paint the room. The project manager could use it to change the order of the activities if so desired.
Soft logic / Discretionary Dependencies
41
An activity relationship that requires an activity to start so that its successor can finish. This is the most unusual of all the activity relationship types.
Start-to-finish
42
An activity relationship type that requires the current activity to start before its successor can start.
Start-to-start
43
A representation of a project network diagram that is often used for outsourced portions of projects, repetitive work within a project, or a subproject.
Subnet / Fragnet
44
A previous project that can be adapted for the current project and forms that are pre-populated with organizational-specific information.
Template
45
An estimating technique for each activity that requires optimistic, most likely, and pessimistic estimates to be created. Based on these three estimates, an average can be created to predict how long the activity should take.
Three-point estimate
46
This is the total time an activity can be delayed without delaying project completion.
Total float
47
The smallest item in the work breakdown | structure.
Work package