PPI Practice Questions Flashcards
ASTM is:
A) a model code group
B) an industry standard-writing organization
C) a testing lab
D) a federal code writing agency
B) an industry standard-writing organization
In order to specify an acceptable type of wall covering, which of the following tests should the designer require that the wall covering pass?
A) methenamine pill test
B) smoke density chamber test
C) Steiner tunnel test
D) vertical ignition test
C) Steiner tunnel test
this the test most often required in the building code
Smoke density test doesn’t measure flame spread
Which test is MOST frequently used to evaluate carpet in the US?
A) flooring radiant
B) Steiner tunnel test
C) methenamine pill test
D) methods of fire tests of building construction and materials
C) methanamine pill test
Which of the following are the two main factors used to determine whether a space must have more than one exit?
A) travel distance and exit width
B) occupant load and occupancy
C) travel distance and occupant load
D) exit width and occupancy
B) occupant load and occupancy
Which of the following is an INCORRECT statement about corridors?
A) corridor construction must be fire rated
B) corridors are part of the exit access
C) corridors must be used exclusively for egress
D) corridors are included in calculating travel distance
A) corridor construction must be fire rated
Corridors are part of the exit access. This means they are used for calculating travel distance but they do not necessarily have to be fire-rated (although they usually are). Also, by definition they must be used exclusively for egress.
When doing design work for remodeling toilet rooms to make them accessible, the designer finds that it is impossible to provide adequate clearance on one side of a door. Best course of action?
A) Propose to the client that walls be demolished and replanned to provide the necessary clearances
B) Apply to the building department for a variance because of the remodeling problem
C) Specify a power-assisted door opener that meets accessibility standards and incorporate this into the design
D) Suggest that a unisex toilet be built nearby that complies with all accessibility requirements.
C) Specify a power-assisted door opener that meets accessibility standards and incorporate this into the design
least expensive option and most sensitive to accessibility requirements
In developing a signage system for a health care clinic, the designer decides that the room identification signs should be mounted perpendicular to the wall near the door to each room. What would be of LEAST concern in the design work?
A) the color of its lettering and its background
B) that the amount the Braille lettering is raised above the surface
C) whether or not the width of the accessible route was reduced
D) the mounting height to the center of the sign
A) the color of its lettering and its background
FYI- tactile signs must have a 1/32” raised surface
What type of locking device is most appropriate for an office building?
A) cylindrical lock
B) unit lock
C) card reader lock
D) mortise lock
D) mortise lock
heavy duty, most durable, and most secure. harder to install.
cylindrical lock is more appropriate for hotel bathrooms or interior private offices (one piece construction). easier to install. less expensive than mortise lock.
What type of system would be MOST appropriate in a large commercial remodeling project where a decorative acoustical ceiling and plenum access are required?
A) integrated
B) linear metal strip
C) gypsum wallboard
D) concealed spline
D) concealed spline
cost of integrated ceilings and linear metal strip ceilings are not warranted in a large commercial project
To detail a doorframe for a conference room where privacy is critical, which of the following is LEAST likely to be required?
A) automatic door bottom
B) a heavy-duty silent closer
C) neoprene gasketing
D) a solid-core door
B) a heavy-duty silent closer
the noise created by a closer might be objectionable for the short time the door was closing, but it would have no effect on privacy once the door was closed
The structure above a small opening cut in a masonry load bearing wall would be supported with a:
A) beam
B) header
C) lintel
D) trimmer
C) lintel
- beam is used for structural framing or to span large openings
- a header refers to a lintel in wood frame construction
- a trimmer is a double thickness of wood around an opening running parallel to the direction of the joists
With whom should the interior designer consult to determine where to locate free-standing stacks in a library?
A) mechanical engineer
B) library planner
C) structural engineer
D) fire protection designer
C) structural engineer
all of these people may need to be consulted but the structural engineer needs to be contacted first in early planning.
According to the IBC, the LEAST number of continuous treads to constitute a flight in a non residential building is
A) 1 continuous tread
B) 2 continuous treads
C) 3 continuous treads
D) 12 continuous treads
According to the IBC, a continuous run of rectangular treads, winders or a combination thereof, from one landing to another is a flight. Therefore, even one tread between two landings would be considered a flight.
In designing a new space, the interior designer can influence life safety the MOST by coordinating with consultants concerning
A) compartmentation
B) fire detection
C) smoke control
D) sprinklers
D) sprinklers
compartmentation and smoke control have already been designed by the architect and the mechanical engineer and the designer would have little influence over these.
smoke detection is governed by the type of the building and occupancy
interior designer would likely be able to influence the design of sprinklers (location and quantity)
Which of the following information about gypsum wallboard partitions should be part of a project’s specifications, not its drawings?
A) edge treatment
B) fastener spacing
C) stud depth
D) wallboard thickness
B) fastener spacing
Who is responsible for ordering and placing the stone?
A) architect
B) interior designer
C) stone fabricator
D) woodwork fabricator
D) woodwork fabricator
the woodwork fabricator orders minor accessory materials such as stone, metal, and glass from other suppliers and then incorporates them into the woodwork
Which of the following plans would show a property’s buildings, walks, driveways, drainage paths, and utility locations?
A) architectural plan
B) city engineer’s plan
C) civil engineering plan
D) site plan
D) site plan
A project’s interior designer is developing the interior construction drawings for a laboratory. After the interior construction is complete, extensive built-in equipment will be placed within the laboratory’s work counters. Where should the interior designer document the equipment’s specifications?
A) on an equipment schedule
B) on an enlarged floor plan
C) on descriptive floor plan keynotes
D) on a large-scale elevation
B) on an enlarged floor plan
most floor plans are 1/8” or 1/4” which is too small to for something so complicated.
If a client wanted to obtain the most competitive bid price while still being assured that the product was acceptable, what type of specification should be written?
A) open
B) reference
C) performance
D) base bid with approved equal
D) base bid with approved equal
a performance or reference spec would likely result with an acceptable final product, the base bid would ensure it
Which of the following is the most legally binding?
A) drawings
B) specifications
C) schedules
D) plans
B) specifications
Which of the following is a relatively inexpensive instrument that may be used by one person to take quick and accurate field measurements of a large site?
A) 100 ft tape measure
B) sonic distance measuring device
C) reflector less electronic distance measuring device
D) laser scanner
C) reflector less electronic distance measuring device
accurate enough and less expensive than a laser scanner
tape measures are awkward for one person to use and slow
sonic distance measuring device is less accurate for small spaces
To determine the necessary floor area for a project, the interior designer must know all of the following EXCEPT
A) net assignable
B) efficiency factor
C) rentable-usable ratio
D) number of employees
D) number of employees
Who would be the least involved in the selection of an underfloor raceway system?
A) electrical consultant
B) structural consultant
C) architect
D) mechanical consultant
D) mechanical consultant
an underfloor raceway system uses metal enclosures buried in the concrete floor slab (needs mechanical)
obi needs architect and electrical consultant
All of the following are part of a drawing’s title block EXCEPT
A) north arrow
B) project title
C) copyright notice
D) list of notes or key notes
A) north arrow
title block must have : project title, copyright notice, and a list of notes or key notes
A client requires a 100,000 square foot project be completed as quickly as possible. Therefore, which the project delivery method should the designer suggest to the client?
A) construction manager method
B) design-bid-build
C) design-build method
D) multiple contracts method
A) construction manager method
construction managers cost extra but they can put the project on a fast track schedule
design-bid-build=lower cost. slower than construction manager
design-build= fixed price. not the quickest construction completion time
multiple contracts= increased construction time
During a routine site visit, the interior designer notices a lack of barricades around a floor openings while interior construction is taking place. What should the designer do?
A) point out the situation to the contract and write a letter to the client stating what was observed
B) tell the contractor to correct the situation
C) write a letter to the contractor stating the concerns, and copy the owner on the letter
D) have the contractor stop the work until the problem is corrected
A) point out the situation to the contract and write a letter to the client stating what was observed
The risk for furniture being damaged during shipment is assigned by the:
A) FF&E General Conditions
B) Owner-Designer Agreement
C) Owner-Vendor Agreement
D) Uniform Commercial Code
D) Uniform Commercial Code
The UCC assigns risks by allowing the factory and vendor to use “FOB” Factory or “FOB destination” to determine at what point title is transferred and who is at risk for shipping damage
If during construction, the contractor notices that a handrail does not meet the local building codes, what action could the designer reasonably expect the contractor to take?
A) the contractor should notify the designer of the discrepancy in writing
B) the contractor should correct the situation and submit a change order for the extra work
C) the contractor should building the handrail according to the contract documents because conformance to building codes is the designer’s responsibility
D) the contractor should notify the designer of the problem and suggest a remedy
A) the contractor should notify the designer of the discrepancy in writing
this is stated in the AIA General Conditions for the Contract for FFE