Topic Four, Part 12 - Critical Path Analysis (Floats and Analysis/Requires Further Revision) Flashcards

1
Q

What is a float?

A

Shows how delayed an activity can be before effecting the next activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a total float?

A

How long an activity can be delayed before affecting the projects end time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a Free float?

A

Amount of spare time available for an activity without delaying the whole project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a critical path?

A

Dotted line on the diagram to show a journey of activities with no float time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a dummy activity?

A

A activity created to purely illustrate dependency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Advantages of critical path analysis?

A
  • Materials can be ordered to arrive when needed

- Informed decisions can be made

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Disadvantages of critical path analysis?

A
  • Diagrams can be unmanageable

- Timescales need to be realistic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly