CDS Flashcards

(73 cards)

0
Q

Allows the CM to charge the owner the actual construction cost of the project plus a negotiated fee that is agreed to before construction begins

A

Cost-plus structure

Actual costs are typically determined by the lowest bid received from the managers subcontractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Allows manager to establish a guaranteed cost of construction (including managers services) before design is fully documented

A

Fixed-price structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The highest probable cost limitation for the construction of the project guaranteed by the construction manager

A

Guaranteed maximum price structure

Any cost savings from a positive bid climate go to the owner not the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Buildings designed after the original building that are either substantially similar to or modifications of the original buildings

A

Derivative works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A civil wrong that causes injury to another person

A

Tort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

requirements for bidding and contracting including bid solicitation, instruction to bidders, bid forms, bonds and certificates, general condition of contract

A

Division 00

procurement and contracting requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

requirements that are applicable to entire project, summary of work, alternates, unit prices, submittal procedure, pricing and payment

A

Division 01

General requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

site remediation, site decontamination, subsurface investigation, surveying, selective demolition

A

Division 02

Existing conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

forms, reinforcement, cementitious deck and underlayment, grouts, restoration and cleaning

A

Division 03

Concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

brick, concrete block, stone, terra cotta, glass block

A

Division 04

Masonry

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

structural steel, metal fabrication, ornamental ironwork, handrails, expansion joint covers

A

Division 05

Metals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

structural wood framing, rough carpentry, finish carpentry, structural plastics

A

Division 06

Wood, plastics, and composites

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

dampproofing and waterproofing, insulation, vapor retarders, air barriers, shingles, roof tiles, siding, flashing, joint sealers, fire and smoke protection, roofing specialties

A

Division 07

Thermal and moisture protection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

metal doors and frames, wood doors and frames, specialty doors, storefronts, windows, skylights, hardware, curtain walls

A

Division 08

Openings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

plaster, gypsum wallboard, floor and wall tile, flooring materials, acoustical ceilings, light-gage metal framing paritions

A

Division 09

Finishes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

toilet compartments, visual display boards, louvers, grilles, flagpoles, lockers, awning, toilet and bath accessories

A

Division 10

Specialties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

vaults and security items, church related equip, library equip, theater and stage equip, musical equip, audio-visual equip, loading dock equip

A

Division 11

Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

furniture, system furniture, art, window treatments

A

Division 12

Furnishings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

special-purpose rooms (clean room / saunas), radiation protection, lightning protection, pre-engineered structures

A

Division 13

Special construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

elevators, escalators, dumbwaiters, moving walks, lifts

A

Division 14

Conveying equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

fire suppression systems, wet-pipe, dry-pipe, standpipes and hoses

A

Division 21

Fire Suppression

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

plumbing for buildings

A

Division 22

Plumbing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

HVAC

A

Division 23

Heating, Ventilating, and Air Conditioning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

energy monitoring and control, environmental control, lighting control

A

Division 25

Integrated Automation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
electrical
Division 26 | Electrical
25
communication, sound, video
Division 27 | Communication
26
intrusion detection, security access, video surveillance
Division 28 | Electronic safety and security
27
excavation and fill, grading, soil stabilization, erosion control, foundation walls, caissons, piles
Division 31 | Earthwork
28
above grade items like paving, fences and gates, site furnishings
Division 32 | Exterior improvements
29
water distribution, sanitary piping, septic tanks, subdrainage, storm drainage
Division 33 | Utilities
30
Standard form of agreement between Owner and Contractor
A101
31
General conditions of the contract for construction
A201
32
Standard form of agreement between contractor and subcontractor
A401
33
Guide for supplementary conditions
A503
34
Instructions to bidders
A701
35
Standard form of agreement between owner and architect
B101
36
Standard form of architect's services: design and construction administration
B201
37
Standard for of architect's services: programming
B202
38
Joint venture agreement for Professional services
C101
39
Standard form of agreement between architect and consultant
C401
40
Standard form of agreement between owner and contractor: construction manager as Advisor
A132
41
standard form of agreement btw owner and construction manager as constructor where the basis of payment is the cost of work plus a fee with a guaranteed maximum price without a guaranteed maximum price
A133 | A134
42
Agreement between owner and design-builder
A141
43
Standard form of agreement between design-builder and architect
B143
44
standard form of agreement between owner and contractor for integrated project delievery
A195
45
standard form of agreement between owner and architect for integrated project delivery
B195
46
in all windowsill details, the glass is placed on two or more _______ to support the weight of the glass and cushion it from the frame
setting blocks
47
used in window jamb frames to prevent the glass from touching the jambs
anti-walk blocks
48
a material used to cushion and seal the glass against the stop and the frame
glazing bead
49
a removable piece used to hold the glass in place after it has been installed in the frame, which makes it possible to replace the glass when necessary
stop
50
requires a project architect or designated quality control reviewer to check the work immediately before it is distributed to the user
Quality control
51
requires periodic checks of the work while it is being developed. periodic check sets generated for the reviewer when the project is 25%, 50% and 90% complete
quality assurance
52
goes beyond quality control and quality assurance
total quality management
53
not part of the contract documents, but may be included in the project manual and be designated "for information only"
subsurface soil conditions report
54
procedures for submittals are found in which masterformat division
01 | general requirements
55
requirements for testing of materials and equipment are in which part of each technical section of the masterformat system
Part 3
56
type of specification that requires a material or product to comply with the requirements of an independent testing laboratory or authority
reference specification
57
Coverage insures the owner in the event that use of the property is lost Not required by A201
Loss of use insurance
58
Permits authorized by the code official in the project jurisdiction
Occupancy permit Architects do not issue occupant permits
59
Type of construction: non combustible materials
Types I and II
60
Type of construction: exterior walls non combustible, interior elements are any materials complying with code
Type III
61
Type of construction: heavy timber construction
Type IV
62
Type of construction: exterior and interior elements are of any materials complying with the code
Type V
63
Allow the architect to confirm that the design intent and requirements of the construction documents will be met by the products that the contractor proposes to include
Submittals
64
Where there are more than 6 separate-sex water closets how many must be accessible
Half of those provided (at least one)
65
A small area subsidiary to the primary occupancy of the building in which it is located
Accessory occupancy
66
Who should prepare the owner-contractor agreement, including the general conditions
Owner's attorney Architects are not permitted to prepare contracts to which they are not a party
67
What do the contract documents consist of
Agreement between owner and contractor, conditions of the contract (general and supplementary conditions), drawings, specifications, addenda
68
Bid amounts must be expressed in which ways? Which one prevails?
Bid amounts must be expressed in the bid form in both words and numerical form. If there is s discrepancy between the two, the words prevail
69
Sheet type designators (0-9)
``` 0 schedules, keynote legend, general notes 1 plans 2 elevations 3 sections 4 large scale views 5 details 6 schedules and diagrams 7 user defined 8 user defined 9 3D representations ```
70
Quasi-judicial
An architects interpretations of the contract documents are performed in a quasi judicial capacity Will not show partiality to either the owner or contractor
71
A305
Contractors qualification statement
72
Labor and material payment bond
Guarantee payment for labor and materials | Protects the owner against possible liens against the property