Chapter 12 - Procurement Flashcards
(23 cards)
When do bidder conferences occur?
Used to ensure that all prospective sellers have clear understanding of procurement requirements. Before that they get submitted.
What are the 3 types of contracts?
Fixed price
Time and Materials
Cost Reimbursement
Main element of Time and Materials contract?
Who wins?
Buyer pays per hour or per item.
Small $, short time.
Seller wins.
Buyer has medium cost risk.
What situation is Time and Materials contract used?
Services when level of effort cannot be defined when contract is awarded
What situation is Cost Reimbursable used?
Exact scope is uncertain , therefore costs cannot be estimated accurately enough to effectively use a fixed price contract
Why are incentives needed?
Seller focused on profits
Buyer focused on total cost, performance, schedule.
Motivate seller to do the right thing.
Name the top 4 fixed-price contract advantages
- Less work for buyer to manage
- Seller wants to control costs
- Companies have experience
- Buyer knows total price before work begins
Name the top 4 disadvantages of fixed-price contract
- Seller charge more for change orders because underpriced the work originally.
- Seller may not complete because they run out of money
- more work for buyer to write PSC
- More expensive if PSC is incomplete and seller needs to add to the price for increased risk.
What are the top three advantages of time and material contract?
- Contract prep quick because SOW less detailed.
- Short duration.
- Used to add contract bodies
What are the three disadvantages of time and material?
- Profit for seller in every hour billed.
- Seller has no incentive to control costs
- Small efforts
- Day to day oversight from buyer
What are the top three advantages of cost reimbursable contract?
- Contract prepared very quick because simple SOW
- less work to define scope than fixed price.
- Less cost than fixed price because seller does not have to add much for risks
What are the 4 disadvantage for Cost Reimburse contracts?
- Must audit seller’s invoices or recharge.
- More work for buyer to manage because SOW is not well defined
- Seller only has moderate incentives to control costs
- Total price unknown
Select the correct contract type:
You need to begin work right away
T and M
Select the correct contract type:
You want to buy expertise in determining what needs to be done
CR
Select the correct contract type:
You know exactly what needs to be done
FP
Select the correct contract type:
You are buying a programmer services to augment your stuff for a short.
TM
Select the correct contract type: you need work done but you don’t have time to audit invoices on this work
FP
Select the correct contract type:
You need to rebuild a bridge as soon as possible after storm
FPIF
Select the correct contract type:
The project requires a high level of expertise to complete and you want to have the best performance possible in the finished product
CPIF
Select the correct contract type:
You need to hire a contractor to perform research and development.
CR
Select the correct contract type:
The scope of work is complete but the economy is unpredictable
FPEPA
Select the correct contract type:
You’re buying standard commodities
PO
What does point of total assumption mean?
Fixed-price incentive fee contracts only.
Refers to the amount above which the seller bears all the loss of a cost overrun.
PTA = ceiling-target/buyer share ratio +target