Chapter 7 - Cost Flashcards

(18 cards)

1
Q

What is parametric estimating?

A

An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is bottom-up estimating?

A

A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which is the correct order for accuracy of estimates? Least accurate to most accurate.

ROM, budget estimates, definitive estimates

Budget estimate, ROM, definitive estimates

Definitive estimates, budget estimates, ROM

A

ROM, budget estimates, definitive estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When is a ROM created? What phase?

Initiating, planning, executing, monitor and control or close?

A

Initiating

-25% to +75% from actual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When is budget estimates created?

Initiating, planning, executing, monitor and control or close?

A

Planning

-10% to +25% from actual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When is the definitive estimates created?

Initiating, planning, executing, monitor and control or close?

A

Later in the project the estimate will become more refined.

-5% to +10% from actual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is analogous estimating?

A

A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is earned value?

A

The measure of work performed expressed in terms of the budget authorized for that work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the definition of schedule variance?

A

A measure of schedule performance expressed as the difference between earned value and plan value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the formula for schedule variance?

A

EV-PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the formula for cost variance?

A

EV-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the formula for schedule performance index?

A

EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the formula for cost performance index?

A

EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

If the performance index is = 1.

On plan?
Ahead of plan?
Behind?

A

Performance index is on plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If the performance index is > 1

On plan?
Ahead of plan?
Behind?

A

Performance index is ahead of schedule
Or
Performance is under planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If the performance index is less than 1

A

Project is behind schedule or

Project is over budget

17
Q

What is internal rate of return (IRR)?

A

The rate of return where in PV equals zero

18
Q

Formula for EAC?

A

EAC = BAC/CPI

EAC = AC+BAC-EV