Chapter 3 Flashcards

(39 cards)

1
Q

Assumption

A

Something that is believed to be true or false but has not yet been proven to be true or false. Assumptions that prove wrong can become risks for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Benefits Management Plan

A

A component of the project management plan that defines how the project will create, maximize, deliver, and sustain the benefits provided by a project or program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Business Case

A

A document that examines the objectives, cost, benefits, strategic goals, constraints, and assumptions of a project and provides justification for an organization to approve the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Constraint

A

A restriction or limitation that affects the project’s ability to meet its objectives and deliver the desired results. Constraints can be internal or external and can impact the project’s scope, schedule, budget, quality, or resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Baseline

A

A “time-lapse exposure” of when the project monies are to be spent in relation to cumulative values of the work completed in the project. The cost baseline shows the aggregated costs of all the work packages within the work breakdown structure (WBS).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Duration

A

The amount of time required to complete a project task or activity. It is an estimate of the elapsed time between the start and end of an activity, excluding non-working time such as weekends, holidays, and planned downtime.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Epic

A

In agile, a large body of work that can be broken down into smaller, more manageable tasks, or user stories. Epics are often used to represent a complex feature or functionality that spans multiple teams or sprints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Feasibility Study

A

An assessment of the practicality of a project or system to uncover the strengths and weaknesses of an existing business or proposed venture objectively and rationally. This is done by analyzing technical, economic, legal, operational and time feasibility factors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Incremental Approach

A

A software development methodology that breaks down the project into smaller, more manageable increments. Each increment is developed and delivered to the customer as a working product. This allows the customer to get feedback early and often, and to make changes as needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Issue

A

An event that has happened, that reoccurs, or that is going to happen that will likely disrupt the project; considered negative; recoverable or can be mitigated in some way.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Kaizen

A

An organizational approach for managing resources. Kaizen posits that small changes in processes are easier to accept and incorporate than large, sweeping changes for the organization or project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Milestone

A

A significant point or event in the project’s progress that represents an accomplishment in the project. Projects usually create milestones as the result of completing phases within the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Milestone List

A

A list that details the schedule milestones and their attributes. It is used for several areas of project planning but also helps determine how quickly the project may be achieving its objectives. The milestone list is in the WBS dictionary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Operations

A

The processes and activities required to maintain and support the project’s products or services after the project has been completed. Ongoing operations are the means by which the benefits of the project are sustained over time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Portfolio

A

Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Product Scope

A

The characteristics and functions of a product or service. It is a high-level description of what the product will do and how it will work. The product scope is typically defined by the product owner, who is responsible for ensuring that the product meets the needs of the customer.

17
Q

Program

A

Related projects, subsidiary programs, and program activities that are managed in a coordinated manner to obtain benefits not available from managing them individually.

18
Q

Progressive Elaboration

A

A process of iteratively defining and planning work to be done on a project. The project manager and the project team start very broadly—typically with a project’s concepts—and then refine the concepts with details, studies, and discussion until a project scope statement is formed.

19
Q

Project

A

A temporary endeavor undertaken to create a unique product, service, or result. The temporary nature of projects indicates a beginning and an end to the project work or a phase of the project work. Projects can stand alone or be part of a program or portfolio.

20
Q

Project Initiation

A

The process of defining the purpose, scope, and objectives of a new project and getting it off the ground. It involves defining the problem or opportunity, conducting a feasibility study, identifying stakeholders, defining the project scope, developing a project charter, and obtaining approval to proceed.

21
Q

Project Life Cycle

A

The series of stages that a project passes through from its initiation to its closure. The project life cycle provides a framework for managing a project, including the definition of the project, the planning and execution of project activities, and the monitoring and control of project performance.

22
Q

RACI Chart

A

A type of responsibility assignment matrix (RAM) that identifies team members and activities to be completed, and defines whether the team members are responsible, accountable, consulted, or informed. There can be no more than one “A” in each row.

23
Q

Requirements Traceability Matrix (RTM)

A

A table that links the origins of individual product requirements to the expected deliverable that meets those requirements so that the project manager can track requirements throughout the project life cycle. An RTM can trace forward and backward traceability and can be used for scope management.

24
Q

Risk Register

A

The central repository for all project risk information. It includes the identified risks, the potential responses, the root causes of risks, and any identified categories of risk. It’s updated throughout the project as risk management activities are conducted to reflect the status, progress, and nature of the project risks.

25
Schedule Baseline
An “approved” version of the project schedule that never changes, but new baselines can be set and created. The schedule baseline is the “plan.” A new schedule baseline is created only through the process of an approved change request.
26
Scope Baseline
Includes the project scope statement, the work breakdown structure (WBS), and the WBS dictionary. It defines the scope of the project, the deliverables, and the project objectives. Any changes to the scope must be approved through the project’s change control process.
27
Sprint Planning Meeting
A scrum meeting attended by the product owner, development team, and the scrum master to determine the amount of work that can be accomplished in the sprint based on the prioritized items in the backlog, the duration of the sprint, the complexity of the work, and the size of prioritized requirements. This determination is based on estimates of the items in the product backlog and past sprints. The selected items from the product backlog become the sprint backlog and the goal of the sprint.
28
Sprint Planning Meeting Duration
The sprint planning meeting, at the start of each sprint, should last up to eight hours for a four-week sprint. Shorter sprints will have shorter planning sessions
29
Stakeholder Register
A register of all project stakeholders and information about their interest in the project, the power they have to influence the project, their expectations, and how their expectations will be managed. You can divide the stakeholder register information into four categories: Identification, Assessment, Classification, and Management Strategy.
30
Story Points
In Agile project tracking, story points are used as a relative estimation tool rather than an absolute measurement of time or effort. This allows for greater flexibility and adaptability in the project management process. User story points are assigned to user stories in relation to the size of the user stories. Story points are a subjective measure that considers the complexity, effort, and uncertainty of a task. Story points are a way to estimate the complexity and effort required for individual stories.
31
Triple Constraints of Project Management
See Iron Triangle of Project Management
32
User Story
Used in Scrum, a story of a role utilizing some functionality to get value from the functionality. User stories follow a formula: “As a , I want , so I can realize .” User stories are written from the customer’s perspective and describe a feature of the product you’re creating. User stories are the items kept in the product backlog, are a small chunk of functionality, and generally take up to 40 hours to create. User stories are prioritized by the product owner.
33
Peer Review
A review of a project performed periodically by peers (with similar experience to project personnel), who are independent from the project, to evaluate technical, managerial, cost and scope, and other aspects of the project, as appropriate.
34
Release
A version of the software product that is ready to be deployed to users or customers. A release can contain new features, bug fixes, and improvements that have been developed and tested by the development team.
35
Story Map
A method of arranging user stories to create a more holistic view of how they fit into the overall user experience. It helps teams to understand how users interact with a product or service, from the beginning to the end. Story maps are often used in agile development, but they can be used in any type of project.
36
Story Mapping
A technique used to visually organize and prioritize the user stories or features of a software product. It is a collaborative approach that helps teams to build a shared understanding of the product and its requirements, and to develop a roadmap for the development process.
37
Iron Triangle of Project Management
A theoretical model based on the characteristics of scope, schedule, and cost, which each constitute one side of the triangle. If any side of the Iron Triangle is not in balance with the other sides, the project will suffer. Also known as the Triple Constraints of Project Management, as all projects are constrained by scope, schedule, and cost.
38
Data Model
A visual representation of the data entities, relationships, and attributes that are used to represent a business domain or system. A data model is used to define the structure and format of the data that is stored and processed by an organization or system.
39
Project Charter
The foundational document for the project; provides political and financial support for the project. The project charter is like the birth certificate for a project. You need it to prove the project exists and to provide basic but extremely important information about the project. The information it contains is generally quite high level; it is the first document developed in an iterative process, so it won’t contain enough information to complete a WBS.