Chapter 5: Capacity Planning Flashcards

(56 cards)

1
Q

Capacity

A

The maximum sustainable flow-rate of output of a process or a system

determines possible throughput

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Long term capacity planning considerations

A

Economies and diseconomies of scale
Capacity timing and sizing
Capacity cushions
Trade off between customer service and capacity utilization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Short term constraint management considerations

A
  • theory of constraints
  • identification and management of bottlenecks
  • product mix decisions using bottlenecks
    -managing constraint in a line process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Output measures of capacity

A

Capacity measured in terms of outputs. Best utilized for individual processes within a firm or when a firm provides a relatively small number of standardize services/ products

Becomes less useful as variety in product mix increases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Input measures of capacity

A

Generally used for low volume, flexible processes

Issue is that demand is generally expressed as an output rate and must be converted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Utilization

A

Aka capacity utilization

The degree to which a resource is currently being used

= Average output rate / max capacity (expressed as a percent)

(= throughput / theoretical capacity)

Output rate and capacity must be measured in the same terms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Maximum capacity for the utilization equation

A

Greatest level of output that a process can reasonably sustain for a longer period using realistic schedules and current equipment

Exceeding maximum capacity can be done for peaks but cannot be sustained

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Economies of scale

A

The average unit cost of a good or service can be reduced by increasing it’s output rate because:

  • spread out fixed costs
  • reducing construction costs
  • cutting costs of purchased materials (volume discounts)
  • finding process advantages (line processes) (can afford to dedicate resources)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Diseconomies of scale

A

Occur when the average cost per unit (at the best operating level) increases as a facility’s size increases

Size can bring complexity, loss of focus, inefficiency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Three dimensions of capacity strategy

A
  • sizing capacity cushions
  • timing and sizing expansion
  • linking process capacity and other operating decisions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Capacity cushions

A

Provide a buffer against uncertainty

Amount of reserve capacity a process uses to handle sudden increase in demand or temporary losses in production capacity.

= 100% - average utilization rate %

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Size of capacity cushion

A

Varys by industry

Often smaller in capital intensive industries and larger where service time is paramount.

Large cushions important when demand varies or future demand is uncertain and resource flexibility is low or if prompt customer service is a competitive priority

But unused capacity costs money

Small cushions may uncover inefficiencies, usually implies less risk and less idle capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Expansionist strategy for expanding capacity

A

Large, infrequent jumps in capacity. Attempts to stay ahead of demand and minimize loss to insufficient capacity

aka capacity lead strategy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Wait-and-see strategy for expanding capacity

A

Smaller, more frequent jumps in capacity. Focus on short term options for increases: lags behind demand

Reduced risk for overexpansion/ obsolete technology but risks being preempted by a competitor

aka capacity lag strategy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Four step procedure for making capacity decisions

A
  1. Estimate future capacity requirement
  2. Identify gaps by comparing requirements with available capacity
  3. Develop alternative plans for reducing gaps
  4. Evaluate each alternative qualitatively and quantitatively before making a final choice
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Capacity requirement

A

What a process’s capacity should be for some future time period to meet the demand of customers (internal or external) given the firm’s desired capacity cushion

Can be measured by output or input

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Planning horizon

A

The set of consecutive time periods considered for planning purposes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

When input measures are appropriate

A
  • Product variety and process divergence is high.
  • product or service mix is changing
  • productivity rates are expected to change
  • significantly learning effects are expected
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Capacity requirement equation

A

For a single service or process, with a time period of a year

= (Processing hours required for years demand) / (hours available from a single capacity unit after deducting the desired capacity cushion)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Alternate capacity requirement equation

A

Number of input units required = (demand forecast * processing time) / (total number of hours available in a year from one unit of capacity * (1-capacity cushion as a decimal))

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Setup time

A

The time required to change a process or operation from making one service or product to another

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Equation for setups per year

A

Number of set ups per year= (Number of units forecast per year / number of units made in each lot requiring setup)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Equation for total setup time

A

= number of setups per year * time per setup

24
Q

Capacity requirement numerator accounting for setup time)

A

For each product

(Demand forecast for year * processing time) + ((demand forecast for the year/ units in each lot)* time per setup)

Can add as many of these as needed together in the numerator to capture all services/ processes

25
Capacity gap
Positive or negative difference between projected demand and current capacity
26
Base case
In making capacity decisions: The act of doing nothing and losing orders from any demand that exceeds current capacity or incur costs because capacity is too late All alternative plans compared to this
27
Qualitative consideration for alternative capacity plans
Uncertainty of demand Competitive reaction Technological change What-if analysis Major when entering new markets/ changing strategy
28
Cash flow
The difference between the flows of funds into and out of an organization over a period of time (including changes in assets and liabilities)
29
Quantitative assessment of capacity alternative
Estimate cash flows attributable to each alternative
30
Integrated resource planning
IRP Long-term capacity plan for utilities to meet the growing forecasted annual energy demand Capacity cushions for peak times
31
Waiting line models
Use probability distributions to provide estimates of average customer wait time, average length of waiting lines, and utilization of the work center. Can be used to choose cost effective capacity (gains from increasing service efficiency against costs to do so)
32
Demand trees
Good for uncertain demand and sequential decisions Can include additional cost incurred or financial benefits expected at each decision point
33
Waiting line model: single-server
Single-channel, single-phase (one server, one line
34
Waiting line model variables
λ: mean arrival rate of customers (inventory). A poisson distribution μ: mean service rate. Exponential distribution ρ: average utilization of the system Assuming mean service rate > mean arrival rate
35
Probability that n customers are in the system (waiting line model)
P(sub n): probability that n customers are in the system = (1-ρ)ρ^n P(sub 0): probability that 0 customers are in the system = 1-ρ
36
Average number of customers in the service system (waiting line model)
L = λ / (μ - λ) Mean arrival rate / (mean service rate - mean arrival rate)
37
Average number of customers waiting in line (waiting line model)
L (sub q) = ρL Average utilization of the system * average number of customers in the service system
38
Average time spent in the system including service (waiting line model)
W = 1 / (μ - λ) 1 / (mean service rate - mean arrival rate)
39
Average waiting time in line (waiting line model)
W(sub q) = ρW Average utilization do the system * average time spent in the system including service
40
Multiple server model (waiting line model)
Customers (inventory) form a single line and choose/ go to one of s servers when one is available Multiple channel, single phase
41
Additional variables for multiple server model
s = identical servers Service distribution is exponential 1/μ mean service time sμ exceeds λ (arrival rate)
42
Littles law
L = λW Average number of customers in the service system = arrival rate * average time spent in system Can always estimate the third variable if have any given two aka inventory = flow rate * flow time
43
Finite source waiting line model
Used if customer population is finite, less than 30
44
Process elements that determine capacity
Nature and mix of flow units (more variety = slower processes) - required activities and buffers - resources allocated to processing flow units -operating procedures used to manage actvities
45
Resource pool
collection of interchangeable resources that can perform an identical set of activities each unit is called a resource unit
46
Theoretical capacity of a resource pool
maximum number of flow units that can be processed by the pool per unit of time the pool may be fully utilized can be computed for the entire process/ resource pool or for each unit (this assumes no waiting or delays) 1/unit load* load batch * scheduled availability (unit load = time per batch)
47
Bottleneck resources
resources pools in a process with the minimum capacity - provide a limit on the theoretical process capacity to increase overall capacity must increase bottleneck capacity
48
Unit load of a resource unit
the sum of the work contents of all activities that utilize that resource unit measured in units of time required per flow unit Units per period or loads per period
49
Load batching
when a resource unit can process several flow unit simultaneously
50
load batch
the number of units a resource unit can process at once
51
scheduled availability of a resource pool
the sum of the scheduled availability of all units in the pool
52
Factors affecting capacity utilization
resource breakdown preventative maintenance setup and breakdown (resource unavailable) low demand or supply starvation/ blockage
53
Potential ways to improve capacity
- increase net availability of resources (reduced set up times, technological improvements, better sequencing, planned maintenance - synchronize flows to decrease idleness - increase theoretical capacity (address bottlenecks)
54
Interdependent product lines
distinct marketing products with some production activities that are integrated/ similar/ symbiotic (using the same bases/ materials/ resources) may enable economies of scale
55
average capacity strategy
add capacity to coincide with AVERAGE growth in demand
56
Techniques to increase short-run capacity
(because forecasts are imperfect) - increase resources - improve resource usage - modify the output - modify the demand is actually easier to increase short run capacity than decrease. generally a decrease in demand causes capacity to go unused