Chapter 7 Flashcards

(39 cards)

1
Q

When is the project cost estimated ?

A

During the initiating phase or when the project charter /proposal is prepared (no detailed plans tho)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which specific activities are defined in the planning phase ?

A
  • estimates of resources are made , durations and costs for each activity
  • resources include people , materials , equipment and facilities
  • estimated activity resources are used to for estimating activity costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The ESTIMATED COST OF AN ACTIVITY ?

A

Based on an estimate of the types of quantities of resources required to perform the activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What elements are included in the estimation of a cost for an activity ? (7)

A
  1. Labour costs
  2. Material costs
  3. Equipment costs
  4. Facilities costs
  5. Subcontractors and consultants costs
  6. Travel costs
  7. Reserve
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Facilities costs?
  2. Subcontractors/consultants costs ?
  3. Travel costs ?
A
  1. Purchasing special facilities or additional space for project team (security reasons -store materials -build/assemble / test project deliverable +. Est cost for renting space)
  2. When project teams or contractors don’t have expertise or resources to do certain project tasks , they may outsource some work to S and C to perform activities (may be possible to outsource specific component tasks)
  3. If required must be included (airfare , lodging and meals)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. Reserve ?
A
  1. Project team /contractor may include an est amount for contingencies to cover unexpected situations that may come up
    • items overlooked when project scope was formed , activities that must be redone or high impact risk probability
    • often seperate budgets set for contingencies at project level rather than specific activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Labour costs ?
  2. Material costs ?
  3. Equipment costs?
A
  1. Est costs for types/ classification of people expected to work on project (based on est work time and rand labour rate for each person / classification)
  2. Est costs of materials for project team /contractor needs to purchase for P (paint , pipes, computers)
  3. Equipment needs to be purchased as part of the project (computers / machinery)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Good practices for cost est ?

A
  • good to have a person responsible for performing activity est the coast associated with activity
  • est costs for activity should be reasonable and realistic
  • start of the project may not be possible to confidently/accurately est costs for all activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Project budgeting process steps ?

A

STEP1 : Determine the total budget cost (TBC)

  • aggregate amount of est costs of all activities to perform and complete a work package or project

STEP2 : Develop a time based budget

  • distribution by time period of the total budgeted cost for work package or project over its expected time span on when specific activities are scheduled to be performed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a TBC?

A

Sum of the est costs of all specific activities that make up that work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If the sum of initial est exceeds sponsor budget ?

A

Reduce costs and recalculate

  • not uncommon but may take several iterations of revision to arrive at an acceptable baseline budget
  • when they budgets for packages are aggregated it cannot exceed total funds from sponsor they budgeted
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How would you reduce costs to get within sponsors budget ?

A
  • may mean making trade-off decision to replace some resources with lower cost / more efficient resources/ subcontracting certain tasks /reducing scope
  • going back to sponsor and asking for additional funds or approval to reduce scope (inform quickly to manage expectations)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a time phased budget ?

A

Distributing each TBC over expected time span of its work package

cost is determined for each period within time span based on when activities are scheduled to be performed

HOW MUCH OF THE BUDGET SHOULD’VE BEEN SPENT AT ANY POINT IN TIME

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The Cumulative Budgeted Cost ? (CBC)

A

also known as PV (planned Value) or BCWS (Budgeted cost of work scheduled)

Amount calculated by adding up the budgeted costs for each time period up to that point in time

Amount budgeted to complete all the work that is scheduled to be performed up to a specific point in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

CBC is used for ?

A

Used to analyse the cost performance of project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How to keep track of cost on a project ?

A

Set up a system to collect , on a regular and timely basis data on costs actually expended

  • include processes , procedures
  • accounting structure established backed on WBS numbering system so each item of actual cost can be charged to appropriate work packages
  • each packaged actual cost can then be summed and compared to CBC
17
Q

Time sheets ?

A

Used to report Labour hours

Individuals working on the project indicate the numbers of the work packages on which they worked and the amount of hours they spent on each work package

  • these are multiplied by hourly cost rate for each person to determine actual rand cost
  • person indicates proper project no. And work package no. On time sheet to ensure actual labour costs are charged to appropriate project
  • when invoices are revived for stuff purchased for project they have to be charged to proper work package no.
18
Q

Commited costs ?

A

Funds that have been obligated for an item that has been ordered or purchase but not yet paid for , thus are not available to be spent elsewhere on the project because they will be needed some time later to pay for item

19
Q

Why are commited costs treated in a special way by accounting system ?

A

So that the accounting system periodically assigns a portion of their total cost to actual cost

20
Q

THE ACTUAL COST OF WORK PERFORMED (ACWP) ?

A

Also known as CAC (cumulative actual cost

Amount of costs actually expended and committed to complete all the work performed up to a specified point in time

21
Q

Calculate earned value ?

A

earned value : budgeted cost of work performed (value of work actually performed)

Calculate : collecting data on % complete for each work package and then converting this to rand amount by multiplying TBC of the work package by % complete

0.3% x R2000 = R600 
Daily budget = R200 
Total expended = R400
22
Q

Prevent premature inflated % completion est.?

A

Keep work packages or activities small in terms of scope and est duration

(activities should not be longer in est duration that the time intervals at which actual project performance will be reviewed and compared to planned progress)

23
Q

Cumulative Earned value (CEV) ?

A

Value of work actually performed up to a specific point in time

CEV= TBC (% of work est to be completed)

24
Q

Steps to Analyse cost performance ?

A

Following is Used to determine wether project is being performed within budget and weather the value of work performed is in line with actual cost.

  1. TBC ( Total budgeted cost )
  2. CBC (Cumulative budgeted cost)
  3. CAC (Cumulative Actual cost)
  4. CEV (Cumulative Earned Value)
25
**COST PERFORMANCE INDEX?**
*Indicator of cost performance and is a measure of **cost efficiency** with which the project is being performed.* CPI = CEV/ CAC
26
**COST VARIANCE** ?
Indicator of cost performance which is different between CEV of **work performed** and CAC, and is expressed in terms of **rands** CV = CEV - CAC
27
When analysing cost performance ?
Important that all data be as current as possible and based on same reporting period
28
**FORECASTED COST AT COMPLETION** (FCAC)
Aka Estimated Cost at completion **ECA** What the total cost will be at the completion of the project or work package based on **actual cost** expended, **earned value of work** performed and **remaining work** to be done
29
**Calculating FCAC (method1)**?
*assumes the work to be performed on remaining portion of project /work package will be done at the same rate of efficiency as worked performed so far* FCAC = TBC / CPI
30
**Calculating FCAC (method2)**?
*assumes regardless of efficiency rate the project /work package has experienced in past, the work to be performed on the raining portion of project /work package will be done according to budget* FCAC= CAC + (TBC-CEV)
31
**Calculating FCAC (method3)**?
*Re-estimating all Costa’s for all remaining work to be performed, then adding this re-estimate to CAC* **can be time consuming but may be necessary is project experiences per distance deviations from plan or extensive changes** FCAC = CAC + Reestimate of remaining work to be performed
32
**TO-COMPLETE PERFORMANCE INDEX** (TCPI) ?
*rate of performance required for the remaining work to complete the project/ work package within TBC* TCPI= (TBC-CEV) = amount of earned value of work remaining needing to be done —————————————————- (TBC-CAC) = amount of budget still left
33
Key to effective cost control ?
Analyse cost performance on a regular and **timely basis**
34
Cost control starts with?
**Establishing a baseline time phased budget** Showing how the costs are expected to be expended during the time span of the project
35
Monitor the actual cost expended and earned value
- Crucial that cost variances and inefficiencies be identified early so corrective action be taken immediately - once project gets out of control may be difficult to complete within budget
36
1. Analysing cost performance to determine which work package may require **corrective action** ?
- identifying those work packages that have negative CV or CPI of less that 0.2 - work packages for which CV or CPI has deteriorated since prior reporting period should be identified - concentrated effort must be applied to work packages with negative variances to reduce cost or improve efficiency of work performed - amount of CV should determine the priority for applying concentrated efforts **(work packages with largest neg CV should be top priority)**
37
Cost control involves ?
1. Analysing cost performance to determine which work package may require **corrective action** 2. Deciding what specific corrective action should be taken 3. Revising the project plan including est durations & costs to incorporate the planned corrective action
38
2. Deciding what specific corrective action should be taken **REDUCE COST OF 2 types of activities**
1. Activities that will be performed in near term 2. Activities that have a large est cost
39
Methods to reduce activity costs ?
- substitute less expensive materials to meet specifications - assign person with greater expertise/ experience to perform / help with activity and get it done more efficiently - increase productivity through improved methods of tech