Chapter 7 - Cost Management Flashcards

(26 cards)

1
Q

ROM

A

Rough Order of Magnitude. Estimates in the range of -25% to + 75%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Definitive estimate range

A

-5% to +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Project Schedule Management Three Point Estimating Calculation

A

tE = (tO + tM + tP)/3

Where
tM: time most likely
tO: time to complete optimistic view
tP: time to complete pessimistic view

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Project Cost Management Three Point Estimating - Triangular Distribution

A

cE = (cO + cM + cP)/3

Where
cM: cost most likely
cO: cost optimistic view
cP: cost pessimistic view

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Project Cost Management Three Point Estimating - Beta Distribution

A

cE = (cO + 4cM + cP)/6

Where
cM: cost most likely
cO: cost optimistic view
cP: cost pessimistic view

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define EVA

A

Earned Value Analysis - a comparison of the performance measurement baseline to the actual schedule and cost performance. It develops and monitors three key dimensions for each work package and control account: PV, EV, AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Define PV

A

Planned value - the authorized budget assigned to scheduled work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define EV

A

earned value - a measure of work performed expressed in terms of the budget authorized for that work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define AC

A

Actual cost - the realized cost incurred for the work performed on an activity during a specific time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define EVM

A

earned value management - is a systematic project management process used to find variances in projects based on the comparison of worked performed and work planned. EVM is used on the cost and schedule control and can be very useful in project forecasting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define ES

A

earned schedule theory - replaces the schedule variance by calculating ES-AT.

If the amount earned is greater than 0, then the project is considered ahead of schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

define and give equation for SPI

A

schedule performance index indicates the efficiency with which work is being accomplished

equation is ES/AT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

define VAC

A

is the explanation (cause, impact, and corrective actions for cost, and schedule, and variance at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

CV equation

A

CV = EV-AC

Where
CV = cost variance
EV = earned value
AC = actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

SV equation

A

SV = EV - PV

Where
SV = schedule variance
EV = earned value
PV = planned value

**NOTE: used with critical path method scheduling and risk management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

VAC equation

A

VAC = BAC - EAC

Where
VAC = variance at completion
BAC = budget at completion
EAC = estimate at completion

17
Q

SPI

A

SPI = EV/PV

Where
SPI = schedule performance index
EV = Earned value
PV = planned value

***Note
SPI measures how efficiently the project team is accomplishing the work. SPI value less than 1 indicates less work was completed than was planned. SPI value greater than 1 indicates that more work was completed than was planned

18
Q

CPI

A

CPI = EV/AC

WHERE
CPI = cost performance index
EV = earned value
AC = actual cost

***Note
CPI is a measure of the cost efficiency of budgeted resources. A CPI less than 1 indicates a cost overrun for work completed, a value greater than 1 indicates a cost underrun of performance to date

19
Q

define EAC

A

estimate at completion (estimated cost of project)

20
Q

define BAC

A

budget at completion (actual cost of project)

21
Q

What is the bottom up EAC equation

A

EAC = AC + Bottom-up ETC

WHERE
EAC = estimate at completion
AC= actual cost
bottom up ETC = bottom up estimate to complete

22
Q

equation for… EAC forecast for ETC work performed at the budgeted rate

A

EAC= AC + (BAC-EV)

WHERE
EAC = estimate at completion
AC = actual cost
BAC = budget at completion
EV = earned value
23
Q

equation for… EAC forecast for ETC work performed at the present CPI

A

EAC = BAC/CPI

WHERE
EAC = estimate at completion
BAC = budget at completion
CPI = cost performance index

24
Q

equation for…. EAC forecast for ETC work considering both SPI and CPI factors

A

EAC = AC + { (BAC-EV) / (CPI x SPI) }

WHERE
EAC = estimate at completion
AC = actual cost
BAC = budget at completion
EV = earned value
CPI = cost performance index
SPI = schedule performance index
25
TCPI equation in order to complete on plan
TCPI = (BAC- EV) / (BAC - AC) ``` WHERE TCPI = to complete performance index BAC = budget at completion EV = Earned value AC = Actual Cost ``` ****Note Greater than 1.0= harder to complete 1.0 = same to complete Less than 1.0 = easier to complete
26
TCPI equation in order to complete the current EAC
TCPI = (BAC- EV) / (EAC - AC) WHERE TCPI = to complete performance index BAC = budget at completion EAC = Estimate at Completion EV = Earned value AC = Actual Cost ****Note Greater than 1.0= harder to complete 1.0 = same to complete Less than 1.0 = easier to complete