Con Tech Flashcards
Name a sustainable method on your project
The use of EPIV valves for the fan Coil units, more energy efficient by avoiding over pumping
Types of external wall
Stone facade
Curtain walling
Brick slips
Brick work
how is the stair constructed
the slab is cut top down- crash matts on floor below.
reviewed with structural engineer to seeif back propping was necessary
then the stair is constructed bottom up
hoarding is put up around where the slab cut is - 60min fire rated due to smoke extract on plant roof not being cut until L8 works
using recycled steel beam on L6 cut out
- Careful/ controlled demolition of slab above beams, to retain shear studs and avoid damaging the beam flanges
- Beams temporarily supported to allow for unbolting, current contractor proposals would be to hang from level 08 beams, or MEWPs would be considered at level 06 to move beams into new position.
- Larger area of slab would be broken out to allow for metal deck to be place and new concrete slab to be poured – this would allow for the composite action be achieved between the beam and concrete, which is critical to control deflection over a long span.
recycled beam on L6 benefits
- Significant carbon saving, as no need to re-produce sections (particularly fabricated sections, which are more carbon intensive), and reduction in materials delivered to site.
- Offers benefits to the buildability, as bringing new long-span steel elements to site will be challenging – the original beams were craned in, which is no longer feasible in the current building. New elements would need to be cut into sections small enough to fit into the goods lift, and reformed with splice connections along the length of the beam.
- Although increasing the scope of slab demolition, this could offer a significant saving overall in terms of cost, programme and carbon.
recycled beam on L6 negatives
- The beams will be cut shorter than the current span, as the connections will need to be removed. This creates complexity in the new connections to be formed once the beams are in their new position.
- Beams could be damaged during demolition.
- The original beams were pre-cambered, which won’t be possible in the proposed condition with beam re-use – may be subject to higher deflections, which needs to be factored into the design.
- The tonnage of these beams is significant, which will prove challenging when trying to remove and reinstall in a new location.
how do you test concrete
cube test, take samples at 7/14 & 21 days then its crushed, to see how it crushes shows the strength
BREEAM Levels
outstanding 85% +
excellent 70-85%
very good 55-70%
good 45-55%
pass 30-45%
unclassified below 30%
BREEAM assessment categories
management
water
energy
transport
health & wellbeing
resources
resilience
land use & ecology
pollution
materials
waste
innovation
BREEAM Standards
new construction
refurbishments & fit out
in use
in community
building safety act
post grenfell tragedy
dame judith hackitts report- building a safe future
new duty holders
principal designer
high risk buildings- 2+ residential units, 7+ storeys or 18m or taller
types of concrete
pre cast
in situ
what are the riba stages
0- strategic defintion
1- preparation and briefing
2- concept design
3- spatial coordination
4- technical design
5- construction
6- handover
7- in use
when doing your master programme how did you know how long to have for you design stages
- validated length with similar projects
- spoke with design team
- spoke with client
steel frame v concrete frame
steel:
off site manufacturing
works for constrained sites
reuse
long lead times
expensive during covid- inflated prices
concrete:
shorter lead times
less expensive
design might prefer a certain type
difference between Shell & Core, CAT A & CAT B
shell & core- weather tight
CAT A- some services are in- major M&E/ first fixes, cant move into it,
CAT B- ready to be moved in, minor client adjustments to be made- FF&E
CAT A risks
BDO- taking at CAT A, main risks is around the services, not having a dedicated riser or extract by the kitchen, not much room for plant on the roof - dictates what can be done with the space
How is a suspended ceiling constructed
Components of a Suspended Ceiling
Grid Framework:
Made of lightweight metal (aluminum or steel), the grid provides the structure for the ceiling panels.
Comprises main runners, cross tees, and perimeter trim.
Ceiling Panels or Tiles:
Typically made of materials like mineral fiber, plasterboard, metal, or plastic.
Installed within the grid framework.
Suspension System:
Wires or hangers are used to suspend the grid framework from the structural ceiling.
Adjustable to ensure the ceiling is level.
Perimeter Trim:
Installed around the edges of the room where the suspended ceiling meets the walls.
Provides a neat finish and supports the grid at the edges.
Step-by-Step Construction Process
1. Preparation
Survey the Space:
Measure the room dimensions and determine the ceiling height.
Identify services to be concealed, such as pipes, wiring, ductwork, or lighting.
Check for any obstructions or load requirements for the ceiling.
Mark Ceiling Height:
Use a laser level or chalk line to mark the desired height of the suspended ceiling on the walls. This will be the reference point for installing the perimeter trim.
2. Install Perimeter Trim
Attach L-shaped perimeter trim to the walls along the marked reference line using screws or nails. This forms the boundary for the grid system.
Ensure the trim is level all the way around the room.
3. Install Suspension System
Mark Suspension Points:
Determine where the suspension wires or hangers will be attached to the structural ceiling. These are typically spaced at regular intervals (600mm to 1200mm depending on the grid size).
Attach Suspension Wires:
Fix wires or rods to the structural ceiling using anchors or screws. These will support the weight of the grid framework.
Ensure the wires are securely fastened and hang vertically.
4. Assemble the Grid Framework
Install Main Runners:
Position the main runners parallel to each other, suspended by the wires. These are the primary structural elements of the grid.
Adjust the suspension wires to ensure the runners are level.
Install Cross Tees:
Attach cross tees perpendicular to the main runners to create a grid pattern. The cross tees divide the grid into sections for the ceiling tiles to fit.
Secure Connections:
Ensure all joints between main runners and cross tees are securely locked into place.
5. Install Ceiling Panels or Tiles
Place Panels in the Grid:
Insert ceiling panels or tiles into the grid framework, resting them on the flanges of the runners and cross tees.
Cut tiles to size where necessary, particularly around edges or obstructions (e.g., pipes or light fittings).
Install Services:
If the ceiling includes lighting, air vents, sprinklers, or other services, install these in the appropriate grid sections before placing the tiles.
6. Final Adjustments
Level the Ceiling:
Check that the suspended ceiling is perfectly level using a laser or spirit level.
Clean Up:
Remove any debris or dust from the installation process.
What is the purpose of a raised access floor
to allow for services to run at low level. Can also provide acoustics beenfits
How would you construct a partition wall to achieve maximum acoustic performance
install acoustic plasterboard & insulation between the stud walls. Ensure it is flooring ceiling and fully sealed, with floo track rubber or foam strops to minimize sound transfer through the floor
How does a pre-action sprinkler differ from a sprinkler system?
“Conventional Sprinkler System: Best for general applications where immediate fire suppression and simplicity are priorities. However, it carries a higher risk of water damage from accidental discharge.
Pre-Action Sprinkler System: Ideal for environments with valuable or sensitive assets where the risk of accidental discharge must be minimized. It provides an extra layer of control but is more expensive and complex.
What is a UPS and what is it’s purpose?
uninteruptible power supply- ensuring uninterrupted power and protecting equipment from electrical disturbances, which is essential for minimizing downtime, safeguarding sensitive systems, and preventing data loss
What is a BMS
building management system - is a centralized control system that monitors and manages the mechanical, electrical, and electromechanical services within a building. It is used to optimize building performance, improve energy efficiency, and ensure occupant comfort and safety.
What is an FCU and how does it work?
fan coilt- 2 pipe or 4 pipe, heats and cools a building. Water is pumped through, there are fans which heat or cool the water to provide heating or cooling. EPIC valves allow for better regulation of water flow, making them more energy efficient by combining pressure-independent operation and integral control. It simplifies installation, reduces maintenance, and enhances occupant comfort, making it ideal for modern HVAC systems.