Contract Practice Flashcards

1
Q

RICS guidance note

A

Defining completion of construction works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the standard recertification period

A

6 months, standard ammendment is to 12 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Types of JCT contract

A

Minor works - less than £500k (traditional procurement)
Intermediate- £500k-£1m (traditional procurement)
Standard building contract -£1m+ (design & build or traditional procurement)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Standard retention

A

3%, minor works is 5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why have retention

A

Withheld from contractor.
At PC drops to 1.5% of contract sum
To incentivise contractor to complete the works
Retention held so if contractor walked away there would be money to cover the cost of completing the defects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contract under hand

A

Doesn’t have to be in writing
Money to be validated
Limitation period is 6yrs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contract deed

A

Has to be in writing
Limitation period is 12yrs
Needs a witness

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

5 requirements of contract

A

Offer
Consideration
Acceptance
Intent to create legal relations
Agree

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who signs the practical completion certificate

A

Contract administrator (traditional) or employers agent (d&b)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How is PC achieved

A

Awarded If fully functional and signed off from parties & building regulations - use practical completion checklist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is sectional completion

A

Must be detailed in contract amendments
IDF rooms are 4 weeks prior to PC
Has the same mechanisms as PC in terms of retention & insurances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is partial possession

A

Not detailed in the contract
Project may be delayed so a section is handed over
Releases same mechanism as sectional / practical completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What happens if PC isn’t awarded

A

Non completion certificate is issued
With detailed reasons why PC wasn’t achieved
Revised PC date
Client can claim liquidated damages if set out in contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are liquidated damages

A

Pre determined calculation of loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are Damages

A

Not set out in contract
Actual loss
Eg if Tesco pc was delayed by a month, damages are a month of revenue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

After signing PC what happens

A

PC certificate is handed over to
Retention is released
Client notifies insurance company

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are rectifications

A

Point in time from PC when the contractor has to rectify snags

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are limitations

A

Point from PC that contractor/ client can sue each other (6 or 12yrs)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Latent defects

A

Notice later on (not obvious) eg cracks in foundations
Can claim within rectification period - why amended to 12months to ensure the project has gone through all seasons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Patent defects

A

Obvious defects. Notice them straight away eg carpet is cut

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is a relevant event

A

Delay
Eg delay in completion due to exceptionally adverse weather
Can’t claim money only extension of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is a relevant matter

A

Money
Loss & expense claim
Eg if client wanted to cut open the works to see if something was complete, contractor could claim to make good the area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Employers agent

A

Design & build contracts
Administer contract in behalf of the client
Can exist before the construction contract is executed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is a contract administrator

A

Traditional
CAs administer contractor impartially
Role only exists once construction contract is executed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is a parent company guarantee
Parent company will sign up to deliver contractual obligations if the contractor goes bust
26
What is a performance bond
Financial guarantee that the contract will be undertaken 10% of contract sum - so project can be retendered if the contractor went bust Get choice over who gets the contract if retendered
27
What is advance payment bond
Protects client in case of contractor deferring in the contract Have one with ergonom
28
When materials are off site what do you have
Vesting certificate Evidence of transfer of payments of goods stored off site Used for insurances to protect the client
29
Retention bond
Alternative to holding retention Good if contractor has Cash flow issues Insurance company provides the bond Not often used
30
What are collateral warranties
Legal document (separate to contract) where 3rd party with an interest to the project has rights Client may have one with design consultants as they have rights over design
31
Step in rights
Allow party to take place of another eg funding party steps into shoes of insolvent party to complete project
32
Third party rights
Statutory right, same as collateral warranties but in the contract
33
3 ways benefits can be transferred in JCT contract
Novation Assignment Collateral warranties
34
Example of assignment
Contractor assigning their right to receive payment to a third party eg a bank. Then bank (third party) is then entitled to receive the payment
35
express v implied terms
express- clear in contract agreed by both parties (contractual) implied- not set out in the contract but implied by common law/ statute
36
local democracy, economic development and construction act 2009
came into force in 2011 amendment from housing grants and regeneration act 1996
37
key provisions of LDED
contracts: requirement for construction contracts to be written payments: pay when certified clauses can no longer be used to prevent paying a subcontractor payment notices: contract must specify that either the payer or payee will issue a payment notice contract requirements: this must be issued no later than 5 days after the payment due date and paid before the final date for payment identified in the contract must clarify the sum that the payer/ee considers due a payment notice must be issued even if the payment is nil payment notices default of payers notice: if the payer is required to issue the payment notice and doesnt the payee is entitled to issue a default payment notice a default payment notice obliges the payer to pay the amount due and allows the payee their statutory right to suspend performance for non payment payless notice: paying parties are required to pay the notified sum or default payment notice by the final date or serve an effective pay less notice. the payer can amend the sum due if its later discovered or the amount notified turns out to be unsound. suspension of performance for non payment: contractors right to suspend carrying out work in the event of non payment
38
types of letter of intent
comfort letter- expresses party's intention to act in a particular way instruction to proceed with consent to spend- instructs work to proceed, sometimes referred to as an if contract. similar to NTE recognition of contract- letter of acceptance, used in FIDIC to formally execute the contract itself. usually marks completion of negotiation between parties
39
letter of intent case law
ampleforth abbey trust v Turner & townsend contractor never signed the contract, whole works were procured using letter of intent. the trust wasnt able to claim liquidated damages under the contract due to late completion of works.
40
difference between bond and collateral warranty
bond is a financial commitment backed up by a third part, collateral warranty passes on contractual obligations bonds are within the contract CW are a side agreement out of the contract
41
case law for collateral warranties
laing o'rouke v parkwood leisure The Court was required to determine whether a collateral warranty was a “construction contract” within the meaning of section 104 of the Housing Grants, Construction and Regeneration Act 1996. Akenhead J found that there was no doubt that this particular collateral warranty was to be treated as a construction contract under section 104.
42
typical clauses of assignment
standard to allow assignment of rights twice without consent should be notified in writing to the other party
43
5 bonds you might use on a project
performance bond retention bond off site materials bond advance payment bond tender bond
44
on demand v conditional performance bond
on demand- money immediately available without needing to meet any preconditions conditional- provide evidence that the contractor hasnt performed to obligations and that they have suffered a loss as a consequence
45
what is a tender bond
provides security against risk of successful bidder failing to enter into contract prevents idle tendering
46
SOE- says you reviewed the collateral warranties tracked and advised where some werent signed - why werent they signed
Collateral warranties need to be signed within 3 weeks of that specific contract being let, this hadnt yet lapsed
47
insolvency - contract termination
have to formally notify the insolvent party of why you are terminating contract (insolvency is a specified default of the contract) insolvent party has 14days to rectify the contract default if this cant be done the contract is terminated
48
the process of administration
Termination of contract, corporate recovery and insolvency guidance note Administration involves the adoption of a procedure that allows a company unable to pay its debts to continue to trade for a further period, during which its assets are protected
49
Difference between CA and PM
CA- named in construction contract PM- scope of services in own contract (not named in JCT)
50
Types of Letter Intent
Comfort letter
51
limitations
52
pricing mechanism of the contract
53
types of contract
NEC FIDIC
54
main difference between JCT and NEC
JCT is more traditional, structured, and risk-focused, suitable for straightforward projects with a clear separation of design and construction responsibilities. NEC is more modern, flexible, and collaborative, ideal for complex projects requiring ongoing project management, communication, and adaptation to change.
55
JCT V NEC (payment provisions)
JCT: Standard payment mechanisms typically based on monthly valuations or milestones. Variations or adjustments can be more time-consuming and formal. NEC: Payment is typically linked to the completion of activities or specific deliverables rather than time-based progress. More flexible with compensation events, which allow for a structured approach to changes in the work or unforeseen circumstances.
56
JCT V NEC (Flexibility and Innovation)
JCT: Tends to be more rigid and traditional, with less room for mid-project changes or flexibility without specific variation clauses. Generally used for projects where the design is fully completed before construction begins, with less flexibility for innovation during the build phase. NEC: Much more flexible, allowing for changes and adjustments during the project without needing to amend the entire contract. The design may evolve during the project, allowing for more innovation and problem-solving on the go.
57
JCT V NEC (Dispute Resolution)
JCT: The contract is more likely to lead to disputes, with dispute resolution processes often requiring formal legal mechanisms (arbitration, adjudication, etc.). Clear legal boundaries on performance and deliverables can create conflicts if there is a mismatch between expectation and execution. NEC: Focuses on early warnings and preventive actions, aiming to avoid disputes from arising in the first place. The collaborative nature of NEC contracts generally leads to fewer disputes, and when disputes do arise, they are more likely to be resolved through negotiation.
58
JCT V NEC (Risk Allocation)
JCT: Generally allocates more risk to the contractor, but it is also more clear-cut in defining each party’s responsibilities. Disputes often arise when the contractor feels that they are being forced to take on risks they didn’t anticipate. NEC: Encourages a shared approach to risk management. The use of risk registers and early warning mechanisms allows for risks to be identified and managed collaboratively. The aim is to avoid disputes by resolving issues before they escalate.
59
JCT V NEC (Approach)
CT: Traditional, risk-averse, and based on a more adversarial approach. Clearly defines the roles and responsibilities of the parties and assigns the risk accordingly. Focuses on the clarity of obligations, often with strict processes to resolve disputes. Designed around the idea that the client provides most of the information, and the contractor's role is to build to the client’s specifications. NEC: Collaborative, proactive, and flexible approach. Emphasizes teamwork and mutual cooperation between all parties. Designed to prevent disputes through good management practices, encouraging early warnings and cooperation. Allows for more flexibility and adjustments during the project.
60
key differences between JCT 2016 &2024
Building Safety Act 2022 and Fire Safety Act 2021: JCT 2024 is expected to address key legislative changes arising from the UK's focus on improving building safety. Compliance with these acts may be woven into contractual obligations, especially in the context of design responsibility and risk electronic signatures Extensions of Time and Force Majeure Clauses: The pandemic highlighted gaps in force majeure and extensions of time provisions. JCT 2024 may provide more explicit guidance on unforeseen events, pandemics, or delays due to public health crises. There may be clearer triggers for entitlement to extensions in circumstances beyond a contractor’s control.
61
difference between reasonable skill and care and fitness for purpose
When demonstrating a reasonable skill and care obligation, all the contractor/consultant is required to show is that they exercised the standard of care to be expected of a reasonably competent professional in their field. fitness for purpose is an absolute obligation and provided the obligation is clearly established or defined by the contract document
62
case law for reasonable skill and care and fitness for purpose
Mt Hojgaard A/S v E.On Climate and Renewables.
63
if traditional, can a contractor be held responsible for a design error
yes, as they should be able to demonstrate reasonable skill and care
64
who holds the risk of adverse weather
the client, unless the contract is ammended
65
if work is called off due to adverse weather can the contractor raise a loss and expense claim?
no, its a relevant event so could request an extension of time
66
types of termination of a construction contract
voluntary and involuntary
67
Please can you describe the change control process.
"1. Identification of Change A change may be identified by the client, contract administrator, or contractor. Reasons for changes include: Design changes. Client requests for additional work. Unforeseen site conditions. Changes to statutory requirements or regulations. Changes typically refer to alterations to the works outlined in the Contract Documents, such as specifications, drawings, or schedules. 2. Instruction of Change The Contract Administrator (or Employer’s Agent in Design and Build contracts) is responsible for issuing instructions to make changes to the works. An instruction may be issued: In writing (preferred for clarity and record-keeping). Verbally (though these should be confirmed in writing as soon as possible). The instruction must clearly describe the nature of the change and its impact on the works. 3. Contractor’s Response Upon receiving the instruction, the contractor evaluates: Impact on Cost: Additional materials, labor, or other expenses. Impact on Time: Possible delays to the project completion date. Impact on Quality: Changes to the specified standard or finish. The contractor may raise concerns if the instruction is unclear, impractical, or inconsistent with the contract. 4. Valuation of Change The change is valued in accordance with the contract terms, usually based on: Schedule of Rates: If included in the contract. Agreed Rates: If the contract specifies fixed rates for particular types of work. Daywork: For works that cannot be priced in advance, based on actual costs incurred. The contract administrator reviews and agrees on the valuation with the contractor. 5. Agreement of Change The Contract Administrator records the agreed impact of the change on: Contract Sum (Cost). Completion Date (Time). Specifications or Scope of Work (Quality). The change is formally documented in variations records, often referred to as a Variation Order. 6. Implementation of Change The contractor carries out the change in accordance with the instruction. The contractor ensures that the change is implemented without compromising the overall progress of the works unless agreed otherwise. 7. Adjustment to Contract The contract sum or completion date is adjusted as necessary to reflect the agreed valuation of the change. Adjustments may include: Extensions of Time: If the change causes delays. Additional Payments: For increased costs associated with the change. The contract administrator formally updates the contract documentation to reflect these adjustments."
68
how did you determine the client was eligible for liqudated damages on Natwest
If there was delay caused by contractor past pc then they would be able to claim LDs
69
what are liquidated damages
Pre determined estimate of loss
70
how did you determine the value of the LDs on NWG
Loss of earnings Rent payments
71
what is acceleration
Contractual mechanism put in place to make up time if there’s delay
72
how do you instruct acceleration in jct
1. Identify the Need for Acceleration Acceleration is usually required when the employer wishes to complete the works earlier than the agreed contractual completion date for reasons such as: Commercial pressures (e.g., opening a facility earlier for revenue generation). Delays that need mitigation (e.g., to avoid late delivery penalties or liquidated damages). Assess whether acceleration is feasible in terms of cost, resources, and technical constraints. 2. Consult with the Contractor Discuss the possibility of accelerating the works with the contractor. Acceleration typically involves: Increased labor and resource deployment. Working overtime or extended shifts. Re-sequencing tasks or using faster construction methods. The contractor must evaluate whether the required acceleration is achievable and any associated risks. 3. Agree Acceleration Terms Acceleration cannot be unilaterally imposed under a JCT contract. It must be agreed upon between the employer and contractor. Key terms to agree on: Scope of Acceleration: Define which aspects of the works will be expedited and the revised completion date. Costs: Negotiate the additional costs for acceleration (e.g., overtime pay, hiring extra labor, equipment costs). Risks: Identify potential risks, such as reduced quality or health and safety concerns, and agree on mitigations. Agreement should be detailed and documented to avoid disputes. 4. Issue a Formal Instruction The Contract Administrator (or Employer’s Agent, in Design and Build contracts) issues a formal Acceleration Instruction to the contractor. This instruction must clearly outline: Revised completion date or milestones. Scope of accelerated works. Agreed costs for acceleration (often treated as a variation). The instruction must follow the change control procedures outlined in the contract, as acceleration is effectively a variation to the original contract terms. 5. Adjust the Contract Documents Update relevant contract documentation to reflect the acceleration agreement: Contract Sum: Adjust to include the agreed additional costs for acceleration. Programme: Revise the construction programme to reflect the accelerated timeline. Completion Date: Record the revised completion date in the contract. Ensure all changes are documented and signed by both parties. 6. Monitor Progress The contract administrator must monitor the contractor’s progress to ensure acceleration measures are implemented effectively and the revised completion date is achieved. Regular reporting and site visits may be required to track progress and address any issues.
73
how is a contract formed
"Offer: The contractor submits a proposal to build the building for £2 million. Acceptance: The developer signs the proposal and agrees to the terms. Consideration: The developer promises to pay £2 million, and the contractor promises to construct the building. Intention: Both parties intend the agreement to be legally binding, as evidenced by the signed contract. Capacity: Both parties are competent adults with the authority to enter into the agreement."
74
What is meant by being signed as a deed and underhand.
deed- 12yr limitation period, witnessed and signed by 2 ppl from each side underhand is 6yr limitation period, signed but no witness