Construction Jobsite manage Flashcards

(43 cards)

1
Q

Who is Most Unlikely To Work With As-Built Drawings

A

Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who is Responsible To Make Sure That The Site Is Ready To Build?

A

The Owner - 18

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Role Of Superintendent-

A

Mobilization - 26

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Contract Documents

A

Project Manual & Drawings - 44

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Construction Specifications Institute Divisions -

A

Division 9 Covers Finishes - 53

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What division would show Project Warranties?

A

Csi Division 1, General Requirements - 56

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Addenda Occur

A

During The Bid Process - 58

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Product Data Sheets are called______, Blueprints Not A______

A

Submittal - 74

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who Prepares Shop Drawings?

A

Fabricator/Manufacturer - 75

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Shop Drawing Flowchart, The Submittal Process in Construction

A

CJM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Submittal Log

A

CJM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do Submittals Effect The Projects ?

A

Schedule And Quality - 89

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why keep Shop Drawings At Jobsite

A

Facilitates proper instalation of materials and equipment - 91

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Use Daily Report To Confirm Justification For?

A

Rain Delays - 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Items To Consider When Having Materials Delivered To The Jobsite Include

A

Labor Force To Unload, Equipment To Unload, And Compliance With Purchase Orders - 103

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Jobsite Space Allocation Identifies?

A

Areas For Materials - 138

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Why Delivere Materials As Close As Possible To Installation Location

A

Delivery labor is cheap - 140

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Laydown Area - Storage Area On Jobsite,

A

Majority Of Laydown Area Is Used To Store Rebar During First 1/3 Of Project - 148

19
Q

The Labor Cost Of A Project Is

A

The Most Unpredictable Expense - 149

20
Q

Site Constraints

A

Controls site layout and equipment used - 153

21
Q

The Superintendent Is Responsible For

A

As-Built Drawings - 156

22
Q

Preconstruction Meeting Agenda

23
Q

Union Labor Agreement

A

A contract that exsists between contractor and Union - 207

24
Q

How many projects does a superintendant manage?

25
Subs Should Be Paid ______, Contractor Approves_____?
On A Timely Basis, Contractor payment - 276
26
If Inspector Discovers Work Being Performed Outside The Permit…..
He May Issue A Stop Work Notice - 304
27
Technical Specifications Effect?
Quality Of Work - 309
28
Finish To Finish Relationship
Is used when two activities shoulkd finish at the same time - 322
29
Building Information Modeling…...
Efficient Method To Transfer Info From Architect To Builder - 391
30
Items Optional In Schedule Of Values
Mobilization, General conditions, Punch list - 426
31
Frontloading
A method of allocating overhead - 435
32
Cash Flow Projections
Relate Schedule Of Values To Construction Schedule - 436
33
Item Included In Application And Certificate Of Payment
Change order summary - 448
34
Contractor applies for payment, Architect Gives….
Payment Draw Request Approval To Owner - 453
35
The Punch list is part of______, and should be completed prior to?
Closeout, Notifying architect or engineer - 460
36
Project closeout Chart
CJM
37
Beneficial Occupancy
Point when facility can be used for intended purpose - 464
38
List Of Substantial Completion Items
Identification, Substantial Comp., Description, Responsibilites, Warranty - 465
39
O & M Training provided by______ ., Manual Per _______, Letter Of Intent Not Part Of ______
Manufacturer Rep, Construction Specifications Institute Format, O&M - 468/469
40
Final Closeout Activities, ________. Date Of Installation ____Included With As-Builts
Required Filings & As-Built Drawings W/Recept, Not - 471
41
Requirement For Warranty is Listed where?
In Specifications - 472
42
American Institute of Architects Document Covering Release Of Lien
G706A - 473
43
Owner Looking For Final Amount During
Closeout Phase - 475