Construction Tech Flashcards
(39 cards)
What are the advantages of a steel frame?
1) Beams span over long distances
2) High strength to weight ratio
3) Recyclable
4) Quick to erect on site
What are the disadvantages of steel?
1) The price of steel can be volatile.
2) Fire protection may be required.
3) Steel frames have lesser acoustic and thermal properties than concrete frames.
What can affect the cost of a steel frame?
1) Number of connections to beams
2) Making the steel fire resistant, with intumescent or boarding it.
3) Improving the acoustic qualities
How can you improve the acoustic qualities of a steel frame?
1) Whilst it might not improve the frame itself, I am aware of being able to install acoustic suspended ceilings to increase the acoustic performance of a building.
2) Insulation in ceilings and walls.
What are the advantages of a concrete frame?
1) The price of concrete is typically more stable than steel.
2) Fire protection is inherent in the structure
3) Provides good sound and heat insulation.
What are the disadvantages of a concrete frame?
1) Takes longer to install on site than steel & timber
2) For concrete’s maximum strength, can take up to 28 days for concrete to cure.
3) Concrete does not span as well as steel.
On the project in Chigwell, why was a timber frame not identified as an option?
I did pose this question to my Client and asked if they would consider a timber frame, but this was quickly shut down. I’m not sure if the Client had issues with timber in the past, but the Client was not willing to entertain timber.
What are the advantages of a timber frame?
1) Sustainable benefits
2) Construction on-site faster than concrete.
3) Structure is relatively lightweight
What are the disadvantages of a timber frame?
1) Can be difficult to source the required sizes and quantities of timber
2) Fire protection may be required.
3) Potential for wet rot, dry rot, woodworm etc.
How can you improve the fire resistance of a timber frame?
1) Fire resistance intumescent
2) Board it with fire-resistant boads.
What are the differences in cost between a steel frame and concrete frame?
For a two storey, circa 20,000ft2 GIA, I would anticipate costs for a concrete frame to be around £200/m2 Q1 2025.
For a steel frame, I would anticipate costs to be around £270/m2 Q1 2025, although there would be additional costs for requirements to enhance the fire resistance and acoustic qualities of the steel frame.
What is CAT A construction?
A very basic form of fit-out for a commercial building, typically only including elements necessary for occupation.
It is a blank canvas for interior and office designers, the next phase is Cat B.
What are the main components of concrete?
1) Cement
2) Aggregate
3) Water
What is reinforced concrete?
Concrete with reinforcements, usually steel bars, rods or mesh.
What should be considered when selecting the type of structural frame?
1) Programme requirements
2) Fire protection
3) Acoustic and thermal properties
4) Market conditions and supply cost
5) Site logistics and general constraints
What is Cat B construction?
CAT B fit out provides a space that is ready to move into and operate.
Can you tell me what a Principal Designer is, and where this role is defined?
The principle designer is a role listed under the CDM regs. The principal designer is the designer with control of the pre-construction phase.
This role is defined under the Building Regs (Building Safety Act)
For Chigwell house, why was a masonry construction not considered in your advice?
Masonry construction (brick) formed the external wall. I advised on the choice of frame.
Can you run through some characteristics that would impact the cost of Steel/concrete frames?
1) Whether it is made on/off site.
2) Reinforcement to concrete
3) Number of connections for steel.
You advised that the cables could be installed high level rather than in a trench. Is this not outside your PI? Especially since it seems that way forward would never have worked.
I advised on the opportunities that could result in a cost saving and brought this to the attention to the design team.
I did not advise the design team to change their design, I advised them that there would be a cost saving by installing the cables at high level rather than in the trenches, it was for the design team to assess if this was feasible.
For the trench, why did it need to be fully opened? Why were the cables not just pulled through?
There was asbestos in the trench that had to be removed.
This also meant that the cables were contaminated, and had to be cleaned and double bagged once removed and couldn’t be pulled through.
On project infrastructure, how did your knowledge of construction tech help with your assessment of labour requirements for the temp flooring?
I was able to break down each element of construction and allocate estimated time frames for the completion of the works to calculate the total duration of install.
What is blue plasterboard?
Acoustic rated plasterboard
Can you tell me the build-up of a stud partition
1) Top and base plate
2) Vertical studs
3) Insulation
4) Plasterboard
5) Pattressing if FCU’s are inside