Construction Technology Flashcards
(98 cards)
1.What are the RIBA stages?
Give a project example
0; Strategic - Site identification 1; Preparation - 2; Concept - Site plan inc indicative layouts 3; Spatial - General arrangements, elevations, 4; Technical - By Contractor if D&B 5; Construction 6; Handover - Practical Completion 7; In-use - Tenanted
- How would the design develop over the stages?
What cost approaches would be taken by the QS at each stage?
0 Strategic - Identify project requirements, feasibility -No design (potential site) Cost Model (£/m2)
1 Preparation - Developer spec, further feasibility, site info and surveys, programme
Order of Cost Estimate
2 Concept - Arch concept design, outline specification
Formal Cost Plan 1
3 Spatial - Developed design and costing
Formal Cost Plan 2
4 Technical - Developed arc, eng, civil design, building systems
Pre Tender Estimate
- What are building regulations?
Provide two examples
Ensure minimum standards for design and construction to ensure the safety of people in and around buildings.
Part L - Conservation of fuel and power
Part M - Facilitate access for disabled people. e.g. ramps, automatic doors
Part B - Fire safety - Sprinklers, risers, smoke alarm, firefighting lift
- Give examples of minimum performance for building regs?
Part B; Fire safety
Advisable to consult with the relevant designer i.e. Architect in respect of detailed requirements required for cost planning.
e.g. FF lift required if the building has a floor 18m above or 10m below vehicle access level.
Previously building Regulations say buildings over 30m constructed since 2007 need sprinklers
*2022 now Blocks of flats with their top storey more than 11m above ground level should be fitted with a sprinkler system throughout the building.
- What are the recent sprinkler changes?
Blocks of flats with their top storey more than 11m above ground level should be fitted with a sprinkler system throughout the building.
6.How would you categorize a building using NRM1?
Give examples of elements in each category
Building Works:
1 Substructure – Foundations, Ground Floor Slab, Piling
2 Superstructure – Frame, Roof, Upper Floors, Walls, Doors
3 Finishes – Wall, Floor, Ceiling
4 Fittings, Furnishings and Equipment (FFE) – Kitchens, Bathrooms, Furniture
5 Services – Heating, Electrics, Ventilation, Lighting, Waste
6 Prefabricated Buildings– Guard House, bath pods (student resi/budget hotel)
7 Work to Existing Buildings – Support to adjacent buildings
8 External Works – Roads, Paving, Planting, External Services (Utilities), Drainage
- How would you build a warehouse?
Ground beams Pad foundations Portal frame Dock levellers Roof sheets Cladding & syphonics Ground floor slab White wall Office fit out M&E Externals: Attenuation Service yard Car park Fencing
- How would you build a house?
Strip foundations DPM Ground floor slab External and internal brick/blockwork Roof Windows & Doors Partitions First fix M&E Plaster Paint Second Fix Kitchen & Bathrooms Externals
- How might ground conditions dictate project foundations?
Weak ground conditions may require specialist foundation solutions
- What are the main types of foundations?
Strip
Pad
Specialist / Piled
- What types of piling are there?
Driven & Bored (Friction & End Bearing), Contiguous, Sheet
- How would you quantify a pile?
mat (m2) Piling rig plant (item) moving rig (nr), piles (nr), testing (item),
- What is prefabrication / MMC?’
What assets is it good for?
What construction needs to be completed prior to any MMC?
Constructed in factories off-site and then are transported to site to be constructed.
Ideal for repetitive structures such as residential, hotels and offices.
Concrete cores and foundations need to be built before any pre-fabrication work can commence.
- MMC Pros?
Program gains can be significant (certainty, not subject to weather, less waste),
Quality is good,
good safety as less people on site.
- MMC Cons?
Larger or individual (not square!) buildings make prefabrication difficult as efficiencies cannot be realised due to transportation.
Offsite production must be perfect or entire process can be undermined (re-building aspect may lose any gains on programme and the process is more expensive than onsite construction).
Only more economical if programme gains are achieved i.e. reduced financing, site preliminaries etc.
- How does it differ to traditional construction? (MMC)
Less trades
Good controlled quality
Good health & safety (less people on site)
- What prefab is used regularly? (Asset class)
Bathrooms for:
Student accommodation
Budget hotel
- Steel pros and cons
Pros;
Fast to construct,
factory quality
castellated beams for services to pass through
Cons;
Poor fire resistance
Long lead times
Can’t be adapted on-site
- Concrete pros and cons
Pros;
Fire resistant
good heat and sound properties
Adaptable on site and is not prone to long lead in times.
Cons;
Labour intensive / Temporary formwork required
Quality issues from weather & labour quality
Services have to be drilled through.
- What is permeable paving?
Allows water to pass through the gaps between the blocks.The water goes through the subbase which also slows down the water accessing the ground.
Pros;
Decreases the total amount of runoff leaving a site
Cons;
Must be used in conjunction with other SUDs (unable to manage storm runoff volumes).
Expensive £150/m2
Require frequent maintenance.
- What are swales?
Channels are sloped into a ‘V’ shape, which make it easy to maintain i.e. cutting machinery for the grass. The slope delays water runoff and reduce the runoff volumes.
- What are soakaways?
Attenuation crates are dug into the ground which hold water before releasing into the ground
- What are attenuation tanks?
Why are they needed when you build a building?
Is there a component used before water enters into the mains system?
Underground surface water storage tank for when flooding occurs resulting in high amounts of water passing through the system to limit the outflow into the mains drainage system.
Accounts building over land that previously would have naturally absorbed rain. Water must go somewhere.
Hydro Brake – Slows the outflow of water run off to manage high volumes (large pre-cast concrete chamber to take high pressure water impact).
- What is the type of frame for a warehouse? Inc components?
Typically used for industrial/distribution buildings that are low rise with large spans.
The structure comprises of columns and rafter steels with bracing and side rails which are possible given most of the external walls do not require windows unlike say residential or office buildings.
Not suited for multiple stories as structure only suitable for bearing the weight of the roof given its long spans.