Procurement & Tendering Flashcards
(157 cards)
What is procurement?
The overall process of delivering the design and construction of a project
What is it important to consider when procuring a project on behalf of a client?
Clients attitude to: Time Quality Cost Risk
What is the traditional procurement route?
Fully developing the design prior to tendering to a main contractor.
Client retains design team as well as the risk of the design.
What is the traditional procurement route?
Fully developing the design prior to tendering to a main contractor.
Client retains design team as well as the risk of the design.
Why might the client wish to procure the works traditionally?
Retain control of the design
Most economic price as design is fully developed
e.g. D&B can be tendered at stage 2/3 where contractor takes risk in completing design
Advantages of traditional?
- Retains control of the design/quality
- Most economical at tender stage (contractor is provided with full outline of client requirements)
- Quicker than D&B for tender review as scope of work is clear and can easily be compared.
Disadvantages of traditional?
- Long program duration (long pre-contract period)
- No engagement with contractor on the design (design and construction are separate)
- Dual point of contact for the client; contractor and design team
- Client retain risk for the design (cost certainty depends on design adequacy)
Contracts for traditional procurement?
JCT minor building contract
Intermediate BC
Standard BC with / without Quantities
What is D&B?
Client Develops Design typically to Stage 3
Employer’s Requirements details how remaining aspects of design should be developed.
The Contractor takes over the design (remaining) and build it with their own (or novated) design team.
Who carries out the design for the contractor?
Typically the Architect and Structural Engineer would be novated to the Contractor.
The Contractor would appoint remaining consultants e.g. M&E engineer
What are advantages of D&B?
- Cost certainty – design risk is passed to the Contractor
- Single point responsibility for design and construction
- Quicker start on site than traditional (design doesn’t have to be fully developed for tender)
What is novation?
A contract which transfers the rights and obligations of one contractual party to a new third party
i.e. design rights and obligations of architect transferred from the client to the contractor.
What are disadvantages of D&B?
- Slower tender analysis compared to traditional
- Harder to compare tender’s dependent on the degree to which the design has been developed
- Contractor is prone to look at ways to reduce costs for the ER proposals – issues with quality dependent on design and ER’s
- Less competition at tender so higher pricing (compared to traditional where the design is fully developed). (Typical number of contractors at tender -Traditional; 5/6, D&B 3/4)
What is management contracting?
- Management Contractor appointed on a fixed management fee (usually a percentage based of the prime cost of the project)
- Early to advise on design, programming & buildability.
- Programme, package and obtain tenders for the works.
- Trade Contractors are in Contract with the Management Contractor.
- Typically associated with complex (untested design) and/or high value projects that may be perceived as too risky for a sole main contractor
Advantages of MC?
- Quick program as design and construction overlaps
- MC technical input alongside design
- Flexibility in making changes to the design before trade packages are let (unlike a lump sum contract)
Disadvantages of MC?
- High level of cost uncertainty until all the packages are let
- Little incentive for MC to reduce costs
How does the MC process work?
- Client appoints MC
- MC develops programme
- MC directs design
- MC selects the trade contractors through competitive tender (direct contractual relationship).
What contract could be used for MC and Trade Contractors?
JCT Management Contract
JCT Trade Contract agreements
What is construction management?
- Similar to MC but key difference is the Client will enter into Contracts with trade Contractors directly
- Client coordinates trades with their own in-house team - e.g. House builders undertaking similar type of works (i.e. repetitive with low risk designs)
What does the CM do?
- Client takes full responsibility for trade contractors (i.e. no third party MC to manage on their behalf)
- Prepare the programme, tender the works packages co-ordinate/supervise the works.
Why might an employer use CM? Ads? Disadvantages?
- Economic (existing trade contract relationships)
- Control program
Dis:
Risk of trade performance
Hold programme risk
What is partnering / framework agreements?
Partnering is a general term covering practices that are designed to promote greater co-operation between all project team participants.
- Collaborative relationships to minimize conflict and promote open communication
-That contract could be between the main contractor and employer, or it could be a multiparty contract embracing the design team and key members of the supply chain.
JCT Constructing Excellence; all parties to encourage collaborative working; risk registers, risk allocation and KPIs
Why might you use a framework agreement?
E.g. Council who need to undertake development works but who do not benefit from in-house teams.
Various consulting parties are qualified to submit a bid which reduces repetition of tendering processes and also facilitates competition e.g. multiple parties can bid which will likely result in overall value to the client
What is a lump sum contract?
Lump sum, fixed priced based on fixed period and fully detailed design.