Construction Technology and Environmental Services Flashcards
(106 cards)
What does RIBA stand for?
Royal Institute of British Architects
Could you please confirm the stages within the RIBA plan of work?
0) Strategic Definition
1) Preparation and Brief
2) Concept Design
3) Spatial Coordination
4) Technical Design
5) Manufacture and Construction
6) Handover
7) Use
What is the benefit of managing projects in line with the RIBA plan of work?
It is an industry recognised standard that is recognised by all parties. Provides clear deliverables at the close of each stage.
Could you please provide an example of how RIBA plan of work has been utilised effectively in one of your projects?
It has been used to inform my Master programme at the project outset. I will then use this programme to receive fee proposals from the consultancy team prior to formal project commencement.
How does the RIBA plan of work help with providing clear guidance?
In provides a defined outcome at the end of each stage which can be referenced by the design team.
What’s the final stage of the RIBA plan of work?
Use.
What is an approved document and please provide an example of one?
Approved documents set out what, in ordinary circumstances, may be accepted as reasonable provision for compliance with the relevant requirements of the Building Regulations to which they refer.
Approved Document B - Fire Safety
What is the connection between approved documents and building regulations?
Approved documents set out what may be acceptable as a reasonable approach to comply with building regulations.
What are the consequences of not adhering to building regulations?
This is a criminal offence and could lead to a fine or an arrest.
Can you please provide an example of typical mechanical and electrical systems found in the buildings that you deal with?
Chillers, VRF, Air Handling Units, Air source heat pumps, Fire Alarm, Lighting Control.
What works to these systems are typically undertaken in projects you are involved with?
I would typically allow to validate the M&E services as part of my design stage which would inform the scope of the M&E work to a degree. Typically, we would replace the on-floor services such as FCU’s, lighting.
Can M&E systems provide other functions than heating, cooling and lighting?
Fire Protection, Noise transmittal (speakers), lifts.
What is the importance of O&M’s?
They provide stakeholders of the project with an accurate record of the works undertaken, products used and any guidance around the future necessary maintenance of the space.
Which stakeholders would typically receive the building O&M’s?
Incoming tenant, client, building manager.
What is the key documentation within building O&M’s?
As built drawings, product maintenance information.
Why would you involve the project team in reviewing O&M’s? Which members of the project team would you involve?
I would involve all key members of the project team.
The project team can review the information included within the O&M’s and ensure this is accurate and aligned with the what is built on site and what was specified within their design.
Why is important that the O&M’s are reflective of the works completed?
Accuracy is important as the O&M’s will likely be used to inform future works / maintenance within the building. Inaccuracy could cause additional cost / health and safety risks.
What is the full name of RIBA stage 4 stage?
Technical Design
How did you know as PM that the structural steels were able to be removed / altered?
I consulted with my structural engineer who had undertaken necessary calculations to ensure that the steels were able to be removed. This was informed by some light opening up works also to verify the record information was correct.
Why did you need to remove the secondary steels at 95 QVS?
This removal was to allow the existing roof to be lowered to accommodate the new roof terrace being installed.
Was there opportunity for re-use of these steels through the building?
This opportunity was assessed however there was no other area within the building where these steels could have been re-used. The main contractor did recycle the steels once removed.
What is a secondary steel?
Secondary components or functional components of steel structure except main stress components such as beams and columns.
Did this new roof terrace require planning approval and why?
The roof terrace did require planning approval as its formation required major works to the external envelope of the building. The terrace was also in very close proximity to the St Paul’s view lines. This was as advised by my planning consultant.
Why was it important the terrace sat below the St Paul’s view lines?
If not we would have been in breach of our planning approval condition received.