Contract Practice Flashcards
(112 cards)
Could you please outline some fundamental aspects of the JCT document Deciding on the appropriate JCT contract 2016 ?
This document addresses procurement strategies, Differing types of contract, Design and Build contracts and Traditional contracts.
Could you please outline some key fundamental elements of the JCT tendering practise note 2017?
This document covers the tender process as a whole relevant to JCT contracts covering items such as:
- Initial Enquiries (PQQ)
- Invitation to Tender and Tender Process
- Assessment and Award.
What is a form of tender
It is a formal acknowledgement that the tenderer understands and accepts the terms of conditions of the tender documents and any other requirements that are stipulated.
What is included within a form of tender?
- Latest return time and date.
- Date, name and address.
- The period of time that is allocated for the works, or an actual completion date if required.
What is included within an invitation to Tender?
- A letter of invitation to tender.
- The form of tender.
Preliminaries. - The form of contract.
- Design Drawings (ER’s)
Could you please outline some of the sections with a JCT contract?
Contract Particulars, Conditions of contract, articles of agreement.
What are the common amendments within a JCT building contract?
- Retention amount (3 - 5%)
- Retention Period (6 months to 12 months)
How does the JCT tendering practise document assist you with tendering practise?
It provides me with the JCT’s expectations relevant to the documentation to form part of a tender process such as a PQQ.
What is the difference between a PQQ and an EOI?
EOI is a document about the tendering party that is prepared by themselves.
A PQQ is a questionnaire that the deign team compiles relevant to the project which the contractor is required to answer.
What other contract forms are you aware of?
NEC
Why do you only have working experience with the JCT form of contract?
The JCT contract is very standard within the construction industry and the particular sector I work within. I have never been involved with a complex engineering project and have not used the NEC contract.
What does NEC stand for?
New Engineering Contract
What does JCT stand for?
Joint Contract Tribunal.
Can you please outline the differences between minor works, Intermediate and Design and Build Contract?
Minor works - Generally used for up to a limit of £250k
Intermediate - Allows sectional completion, more detailed than a minor works contract.
Design and Build - Most detailed, transfer of design risk from client to contractor.
For what scope of work have you used a minor works contract?
A light touch toilet refurbishment.
What is the key difference between a minor work and intermediate contract?
The intermediate form of contract allows works to be complete in sections.
When are NEC contracts typically used?
Infrastructure projects, public work
Please name some key elements of an NEC contract?
- Defined role of a Project Manager.
- Programme included within the contract documents.
What process do you go through when selecting a contract?
I will review my clients key objectives relevant to cost, programme and quality and select the form of contract best suited to meet their requirements.
Which element of time, quality and cost are most important?
They are all important and I aim to manage all of these effectively in my role of project manager. My clients key objectives would dictate the “most” important of these.
How does the choice of contract influence cost , time and quality?
Different forms of contract have different provisions within them to best manage these elements. For example a D&B contract allows for a transfer of design risk thus minimising the likelihood of post contract change thus reducing cost risk.
What do you mean by nature of the works relevant to contract selection?
This would mean any specific client objectives which would dictate any pressures around areas such as programme for example.
What key elements of scope would you assess when choosing the correct form of contract?
Scope of work that would increase cost thus discounting the minor works or intermediate forms.
Also scope relevant to design and quality as this may dictate between D&B and traditional.
How do you know a type of contract is appropriate?
-Scope
- Complexity
- Clients risk appetite
- Value
- Level of design to be undertaken