Contract Practice Flashcards
When should works be valued up until under a JCT 2016 contract?
Valued to the IVD, under the JCT 2011 contract it was the due date.
When would you recommend the client obtains a collateral warranty?
- For longwearing items/packages
- Plant
- Items integral to the building and its functionality
What is are Third Party Rights?
- Allow a 3rd party to enforce specified terms of a contract in the same way as a collateral warranty without the need for a separate contract
Partial possession vs sectional completion
- Section competition is pre-planned and defined in the contract documents, partial possession is not and is a more open ended option
What are the risks associated with a LOI? (Letter of Intent)
- No warranties
- As not a formal contract cannot be found in breach
- No obligation of the contractor to complete the works
- No right to adjudication as HGCRA does not apply
What is Prime cost?
The actual cost of a variation / project plus % of OHP
What is a Provisional sum?
A financial allowance, included within the contract sum for work that is not sufficiently defined to allow the contractor to offer a fixed price
What are some Relevant Events?
Variations
Exceptionally adverse weather
Force Majeure
Deferment of possession of site by the employer
The carrying out of work by the statutory authorities
Loss or damages by the specified perils
Strike or lock out
Civil commotion or terrorism
The exercise of any statutory power after the base date by the UK government
What are some performance bonds?
Parent company guarantees – similar to performance bond backed by holding company
Performance bond – typically 10% of contract sum and used to ensure the contractor completes their obligations to a client
Retention bond – in lieu of taking retention
Advance payment bond – secures payments if the client agrees to pay start-up costs
What is time at large?
Contract completion date passed but no EOT granted
What is the process for an extension of time?
Contractor must issue a notice of delay as soon as it becomes apparent along with all substantiation and back up as soon as is practically possible
Employer must response within 12 weeks from receipt of all information
What does the HGCRA mean?
Right to be paid interim periodically or stage
Right to be informed of the amount due
Right to suspend performance for non-payment
Right to adjudication
Banning pay when paid clauses
What are the differences between an NEC and a JCT contract
NEC uses 6 main options (A-F) whereas the JCT is a suite of contracts
NEC is written in simple (laymans) terms whereas the JCT uses legal wording
NEC does not mention a QS, only a PM
NEC uses compensation events, JCT uses variations
Programme forms part of the NEC contract document
Bill rates are binding within a JCT contract for variations
Variation vs Compensation event – money and time dealt with separately under JCT
A – similar to traditional
F – Similar to management contracting
What should be included in a LOI to ensure it is enforceable?
The Parties The works The price (if agreed) Statement of the intention of the parties to enter into and be bound by a formal contract Date for possession and completion Procedure for calculating payments Insurances provided Maximum expenditure limit Confirmation that the contract created by the LOI will end upon execution of the main contract
Does a performance bond remain the same throughout the project?
Usually reduces to 50% of the sum at Completion
What are the negatives of a LOI?
Can put the client in a weak position during contract negotiation
May lead to complacency
Less robust than a contract
What is a collateral warranty?
Collateral warranties are used as a supporting document to a primary contract where an agreement needs to be put in place with a third party outside of the primary contract.
Sometimes an architect, contractor, or sub-contractor will need to warrant to a funder, tenant or purchaser that it has fulfilled its duties under a building contract.
It can also provide the third-party contractual rights enabling it to claim for losses which would not otherwise be recoverable.
Creates a direct contractual link between parties not linked within the building contract i.e. tenant or funder.
What are the 2 options for valuing variations?
Use the valuation rules
Schedule 2 quotation
What are the difference between the JCT 2011 and 2016 contracts?
Introduced updated CDM regs – CDM Co-Ordinator changed to principle designer
Government Payment Charter - First payment date is now specified in the contract
Monthly Payment cycle continues to operate until the final account is agreed and certified
L&E – EA must respond to initial claims with 28 days and 14 days of subsequent updates
Update in payment terms – IVD 7 days before due date / due date is 7 days after IV recieved
What is novation?
The transfer of benefits and burden in a contract (design team)
The designer is engaged under the same terms by the contractor as they were by the client
Contractor becomes liable for all design carried out by the designers even pre-novation. They have no liability to the client unless collateral warranties are used
What is the difference between a JCT Minor works and D&B contract?
Minor works
Contract Administrator
Does not refer to sections or sectional completion
D&B –
Employers Agent
Sections and sectional completion, stage payment allowed for
Retention 3% in DB and 5% in MW
What section of the JCT D&B contract enables the EA to request a quotation for works prior to instruction?
A Schedule 2 (of the conditions) quotation however contractor not obliged to provide it.
What’s the danger with Free issuing risk material?
Could be damaged by the contractor
Risk is carried by the employer if cause a delay
How long should be allowed for a tender period?
JCT Practice note 2017 –
minimum of 28 days for simple jobs w/ no design
3 – 4 months for more complex design projects