Miscellaneous Flashcards
How much is concrete?
£150/m3
How much is rebar?
£1,200/t
How much is universal steel?
£2,100/t
How much is fabricated steel?
£2,400/t
How much is a blockwork wall?
£50/m2
How much is a paint finish?
£10/m2
How much are cavity barriers?
£50/m
How much is a sedum roof?
£400/m2
How much is Chinese granite paving?
£120/m2
How much is yorkstone paving?
£220/m2
How much is a plasterboard wall?
£60/m2
Typical allowance for sub-contractor prelims?
15% - 25% trade dependent
Typical allowance for main-contractor prelims?
17% - 25% project dependent (complexity)
Typical allowance for D&B risk allowance?
5%
Typical allowance for construction contingency?
5%
Typical allowance for OH&P?
5%
BREEAM requirement for Soho Place & Wedge House?
both excellent
What does the RICS believe are the three disruptive trends for the future of surveying?
Technology – data protection and handling - trust
Sustainability – driving construction to be better and how developments incorporate this
Talent / skills – recruiting the right people to challenge conventions and evolve correctly
Are you aware of any reports regarding teamwork?
The Latham Report – Constructing the Team 1994
How many faculties are there in the RICS?
17 – e.g QS, PM, Auctioneers, Rural, Commercial property, geomatics
RICS Brexit Paper?
RICS response to immigration skills white paper
Brexit: What Next – sets out potential scenarios
What happens if foreign workers leave the UK
What else has the RICS done to prepare for Brexit?
Formed a Joint Institutes Brexit Group – RIBA, CIOB and RTPI
RICS standards are globally applicable so will be relevant regardless of outcome
RICS regulation independent and worldwide so unaffected too
What are the RICS black books for?
Black books are a suite of guidance notes setting the best practice
What are the RICS Guidance notes?
Best practise – not compulsory but in the case of negligence it will be noted if followed