Contracts Flashcards
A new promise to pay a debt after the statute of limitations has run is
enforceable without any new consideration
The nonoccurence of a condition may be excused if
the party who benefits from the condition waives it by words or conduct
(once excused / waived the condition cannot be later raised in a defense)
A material breach of a contract allows for
the non-breaching party to withhold any promised performance and to pursue remedies for the breach, including damages
When the parties expressly agree to a condition precedent (or a concurrent condition) they are generally strictly liable to that condition, meaning
a party must fully comply with that condition before the other party’s performance is due
Under the UCC parole evidence rule, express terms of a written contract can be
(1) explained or (2) supplemented by the following evidence (in order of priority): course of performance (current k), course of dealing (prior k), and trade usage (based on industry)
The non-breaching party’s failure to mitigate
doesn’t give the breaching party a right to sue the non-breaching party for such failure, it only reduces the non-breaching party’s damages recovery
In construction contracts, the general measure of damages for a contractor’s failure to begin or to complete a building project is
the difference between the K price and the cost of construction by another builder, plus any progress payments made to the breaching builder and compensation for the delay in completing the construction
In order for a contract to be voidable for duress, there must be
force or an improper threat that deprives a party of a meaningful choice (generally, threat of civil litigation is not improper unless it is made in bad faith)
Induced by Force = VOID
Induced by Improper Threat = VOIDABLE
There is no substantial performance if
the incomplete performance was a material breach of contract (frustrated the significant purpose of the K)
Substantial performance is less likely to be found when
a party intentionally furnishes services that are materially different from what was promised
Actual damages can be either
direct or consequential
Total (material) breach of an installment contract requires
Nonperformance accompanied by repudiation
Economic waste occurs when
the cost to fix or complete the construction is clearly disproportional to any economic benefit or utility gained as a result
If a party breaches yet substantially performs
the non-breaching party is required to pay whatever remains on the contract price (or perform) but may bring suit later for damages
Requirements contracts satisfy UCC contract formation requirements even without naming specific quantities because
A duty of good faith and fair dealing is imposed in all contracts, whether governed by the UCC or common law
E.g. this means best efforts to supply the goods (for seller) and best efforts to promote their sales (buyer)
A party to an illegal contract may recover restitution damages if that party conferred a benefit on the other party and
(1) was justifiably ignorant of the facts that made the contract illegal
(2) was less culpable than the other party, OR
(3) withdrew before the conduct’s illegal purpose was achieved and did not engage in serious misconduct
A party to a contract must avoid or mitigate damages to the extent possible by
Taking steps that do not involve undue risk, expense, or inconvenience
When a party is suing a third-party beneficiary of a contract, the promisor can
raise any defense against the third party-beneficiary that the promisor had against the original promisee
Compensatory damages are meant to compensate the non-breaching party for
Actual economic losses
Expectation damages are intended to put the non-breaching party
In the same position as if the contract had been performed (must be calculated with reasonable certainty)
Compensatory damages consist of
(1) expectation, (2) consequential, and (3) incidental damages
Note: In real-estate contracts requiring delivery of possession of property, late delivery is a breach that entitles the buyer to expectation damages measured by FMV of the property for the time buyer was denied possession
Consequential damages are a direct result of breach but
need not be the usual result of the breaching party’s conduct (but are otherwise reasonably foreseeable in the event of a breach)
The primary test of whether a communication is an offer is whether an individual receiving the communication
would reasonably believe that he could enter into an enforceable deal by satisfying the condition
Damages are foreseeable if they were
(1) A natural and probable consequence of breach
(2) If they were “in the contemplation of the parties at the time the contract was made” OR
(3) If they were otherwise reasonably foreseeable