Deck 4 Flashcards
What is Project Float?
The amount of time that a project can be delayed without violating the project deadline imposed by the customer, or the delivery date committed to the customer.
What is Padding?
The amount of unreasonable extra time added to the estimate, just to feel confident with the estimate.
What is Program Management?
The application of knowledge, skills, and principles to a program to achieve the program objectives and obtain benefits and control not available by managing program components individually.
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements is known as ___________________.
The application of knowledge, skills, tools, and techniques to project activities to meet project requirements in known as <u>Project Management</u>.
What is Project Management?
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
What is a Procurement Strategy?
The approach by the buyer to determine the project delivery method and the type of legally binding agreement(s) that should be used to deliver the desired results.
What is the event that officially authorizes a project?
The approval of the Project Charter.
What is a Budget?
The approved (cost) estimate for a project, WBS component or a schedule activity.
What is a Cost Baseline?
The approved time-phased budget of the project (excluding any management reserves) that is used to compare actual costs to planned costs in order to determine variance and need for preventive or corrective action.
What is a Schedule Baseline?
The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
What is a Scope Baseline?
The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed using formal change control procedures and is used as a basis for comparison to actual results.
What is a Baseline?
The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
What are Specification Limits?
The area on either side of the mean on a control chart that reflects the customer’s requirements for a product or service. This area may be greater than or less than the area defined by the control limits.
What are Control Limits?
The area within three standard deviations on either side of the mean on a control chart that reflects the expected variation in the data.
What is Planned Value (PV)?
The authorized budget assigned to scheduled work.
When is the Benefits Management Plan developed?
The Benefits Management Plan is developed prior to project initiation.
Which is the best form of power for a Project Manager?
The best form of power depends upon the situation and the maturity level of the project manager. Generally speaking, personal powers (such as Expert and Referent) are better than positional powers (such as Legitimate, Reward and Punitive).
What is Budget at Completion (BAC)?
The budget for all the work on the project. It is also the total planned value for the project.
What is Portfolio Management?
The centralized management of one or more portfolios to achieve strategic objectives.
Who can authorize the use of Management Reserves?
The change control process is used to obtain approval to move the applicable management reserve funds into the cost baseline.
What is the Deming Cycle?
The checklist of the four stages which you must go through to get from “problem-faced” to “problem solved”. The four stages are Plan-Do-Check-Act. It is also known as Shewhart Cycle. It is used for continuous improvement.
What is Schedule Data?
The collection of information for describing and controlling the schedule.
In which document would you find a glossary of common project terminology?
The Communications Management Plan
In which document would you find the template for project status reports?
The Communications Management Plan