DEFINITIONS Flashcards
A set of conditions that is required to be met before deliverables are accepted.
Acceptance Criteria.
Products, results, or capabilities produced by a project and validated by the project customer
or sponsors as meeting their specified acceptance criteria.
Accepted Deliverables
Within the quality management system, ??? is an assessment of correctness
Accuracy
The process of obtaining team members, facilities, equipment, materials, supplies, and other
resources necessary to complete project work.
Acquire Resources
Obtaining human and material resources necessary to perform project activities. ??? implies a cost
of resources, and is not necessarily financial.
Acquisition
A distinct, scheduled portion of work performed during the course of a project.
Activity
Multiple attributes associated with each schedule activity that can be included within the activity
list. ??? ??? include activity codes, predecessor activities, successor activities, logical relationships, leads and
lags, resource requirements, imposed dates, constraints, and assumptions.
Activity Attributes
The time in calendar units between the start and finish of a schedule activity.
Activity Duration
The quantitative assessments of the likely number of time periods that are required to
complete an activity.
Activity Duration Estimates
A documented tabulation of schedule activities that shows the activity description, activity identifier, and
a sufficiently detailed scope of work description so project team members understand what work is to be performed.
Activity List
The realized cost incurred for the work performed on an activity during a specific time period.
Actual Cost (AC)
The time in calendar units between the actual start date of the schedule activity and either the
data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule
activity is complete.
Actual Duration
A project life cycle that is iterative or incremental.
Adaptive Life Cycle
A technique that allows large numbers of ideas to be classified into groups for review and analysis.
Affinity Diagrams.
Any document or communication that defines the initial intentions of a project. This can take the form of
a contract, memorandum of understanding (MOU), letters of agreement, verbal agreements, email, etc.
Agreements.
A technique used to evaluate identified options in order to select the options or approaches to use
to execute and perform the work of the project.
Alternative Analysis.
A technique for estimating the duration or cost of an activity or a project using historical data
from a similar activity or project.
Analogous Estimating
Various techniques used to evaluate, analyze, or forecast potential outcomes based on possible
variations of project or environmental variables and their relationships with other variables.
Analytical Techniques
A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration.
Assumption
A project document used to record all assumptions and constraints throughout the project life cycle.
Assumption Log
Method of measuring quality that consists of noting the presence (or absence) of some characteristic
(attribute) in each of the units under consideration.
Attribute Sampling
The right to apply project resources, expend funds, make decisions, or give approvals.
Authority
A critical path method technique for calculating the late start and late finish dates by working backward
through the schedule model from the project end date.
Backward Pass
A graphic display of schedule-related information. In the typical bar chart, schedule activities or work
breakdown structure components are listed down the left side of the chart, dates are shown across the top, and activity
durations are shown as date-placed horizontal bars.
Bar Chart & Gantt Chart