Excavation 2 Flashcards

(27 cards)

1
Q

What is the general procedure for mass basement excavation?

A
  1. Conduct soil testing and site survey
  2. Choose excavation method based on site conditions
  3. Excavate in layers, supporting as needed
  4. Install drainage and retaining systems
  5. Begin foundation work after reaching design depth
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the five common basement excavation methods?

A

Open-cut method

Top-down method

Bracing method

Anchored method

Island method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the open-cut method?

A

A straightforward excavation technique with two types:

Slope excavation: sloped sides, no retaining walls needed

Cantilevered excavation: uses retaining walls to support terrain and groundwater

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the main advantage and disadvantage of open-cut slope excavation?

A

✅ Less expensive due to no retaining walls
❌ Requires more space for sloping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the drawback of open-cut cantilevered excavation?

A

More expensive and time-consuming due to retaining wall construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the top-down excavation method?

A

Excavation begins after constructing load-bearing walls and a top floor slab, then digging beneath while building above.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Where is the top-down method typically used?

A

In high-rise urban projects to save time and space

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What’s the key benefit of top-down excavation?

A

Upper structure construction can proceed simultaneously with basement excavation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How does the bracing method work?

A

Horizontal struts are placed to support retaining walls, redistributing load and stabilizing the excavation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost comparison of bracing method?

A

Cheaper than top-down, but more expensive than basic open-cut

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does the anchored excavation method involve?

A

Driving steel anchors into strong soil or bedrock through the retaining wall to resist earth pressure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When is the anchored method effective?

A

Only when anchors are embedded in bedrock or dense clay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the island method of excavation?

A

Excavating from the center outward, forming sloped embankments to the retaining walls, used when site has no nearby obstructions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the benefits of the island method?

A

✅ Safe and stable
✅ Combines slope and bracing methods
❌ Limited to specific project sites

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What factors influence the choice of basement excavation method?

A

Type of construction (new site vs. under existing structure)

Soil type (rocky, sandy, clay)

Topography (flat land = more options)

Building size and scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the two most adopted support systems in excavation?

A

Soldier pile and lagging

Soil nailing

16
Q

What is the soldier pile and lagging system?

A

I-beams (soldier piles) are drilled into the ground

Lagging (wood planks) is placed between piles to hold back soil

17
Q

What is the spacing limit between soldier piles?

A

Typically 10 feet between piles

18
Q

What are lagging boards made of?

A

2–4 inch thick timber used between soldier piles

19
Q

What is soil nailing?

A

A technique where the excavated soil is stabilized using grouted steel bars (nails) and shotcrete to hold the slope

20
Q

What are the key steps in soil nailing?

A
  1. Excavate shallow layer
  2. Spray shotcrete on face
  3. Drill and grout nails
  4. Repeat in layers
21
Q

When is soil nailing most effective?

A

Above the groundwater table and in cohesive soils

22
Q

What data is needed for accurate earthwork calculation?

A

NGL (Natural Ground Level) data

Design Level data

Benchmark elevation

23
Q

How is benchmark elevation determined?

A

Using survey equipment (e.g., total station, GPS) and referencing known elevation points or satellites

24
What is the Grid Method of earthwork estimation?
1. Divide site into grid 2. At each node, record existing and proposed elevations 3. Compute cut/fill depth 4. Calculate volume per cell and sum all
25
What is the formula to calculate volume of a grid square?
Volume = Average depth at corners × Area = (d1 + d2 + d3 + d4)/4] × (L × W)
26
Which software is best for accurate earthwork calculations?
Civil 3D (AutoCAD), especially for large-scale projects