Experience Area A - Project Initiation and Predesign Flashcards
What Acts apply to “Project Inititation and Predesign”?
- CGA 1993
- Copyrights Act 1994
- FTA 1986
- RAA 2005 and RAR 2006
What were the NZIA Guide to Architects Charges 2007 and why should they be no longer used?
A guide to the fees a client can expect to pay for core services provided by an NZIA architect member, once the project scope and related architect’s services are adequately defined.
benchmark for NZIA architect members when calculating their fees
Beucase it is seen as ‘cartel’ or insider trading, and can be used to fee cut (although fee cutting is dangerous)
How should you treat the fee if it is a complex project or includes additons/alterations.
Where the Client’s project is highly complex, or calls for specialist skills, or includes alterations and additions, your architect may need to allow for extra fees, typically in the order of** 1.5% to 5.0% **over the usual percentage rate.
How are fees broken up for the different stages (as percentages)?
The portion of the Architect’s fee that may be reasonably assigned to each stage may fall within the following ranges :
Predesign : 2% to 10% median 5%
Concept and Prelim : 4% to 18% median 12%
Developed : 5% to 20% median 13%
Detailed : 30% to 50% median 45%
Procurement : 1% to 20% median 4.5%
Admin and Obs : 5% to 33% median 25%
What are the different types of fees for Architect’s Charges?
Lump Sum, Time Charge, or Percentage Fee bases, or a combination
What are LumpSum Fees?
- Lump Sum Fees are determined by pre-estimating and agreeing on the cost of resources for each section of the Architect’s services.
- Establishing Lump Sum fees is challenging at the project’s outset without a clear understanding of the client’s requirements.
- This fee structure may be realistic once the design is developed and agreed upon, for example, after completing sketch plans.
What are Time Charge Fees?
- Time Charge Fees are applied when the extent of services cannot be easily determined beforehand.
- These fees are calculated by multiplying hours of service by the agreed hourly rate for each service provider, with expenses added.
- The Architect should provide an estimate of the total cost of agreed services calculated this way, but it should not be considered a cap if services are extended beyond the estimate due to circumstances beyond the Architect’s control.
- The Architect must keep full records of time spent
What are Percentage Fees?
- Percentage Fees are calculated by multiplying the adjusted Cost of the Contract Works by the agreed percentage fee rate.
- The adjusted Cost of the Contract Works includes the cost of everything designed, selected, or laid out by the Architect and others, carried out by the contractor as stated in the contract.
- For fee calculation, the cost of old materials is considered as if new, and the cost of goods/services provided by the Client is calculated as if provided by the contractor.
- If the final Cost of the Contract Works is undetermined, the most recent estimate approved by the Client is used for fee calculation.
When should Lump Sums be used? When should they not be used?
Dont use when unsure of the scope.
Can be based on previous expierience of similar projects
When should Time Charge be used? When should they not be used?
When the extent of services cannot be easily determined beforehand.
Typical for early and late stages of the project - because of uncertainty in these projects
Can always use Time Charge
When should Percentage Fees used? When should they not be used?
Generally percentage can always be used.
More useful when there is some certainty to the project scope
There should be right to revise this fee basis if the construction value changes
Why should you always have a written contract?
Terms of Engagement are part of the Architects Code of Ethics
Prevents disputes from arising
Record of what was agreed
Clauses to limit your liability
General clarity
WHAT ELSE
If a client changes the AAS with their lawyer what should you do?
Client generated conditions can pose liability and insurability issues for the
architect.
Check with your lawyer
What are the differences between the 6 year contractual liability and the 10 year long stop.
the contractual liability of the architect is limited in time to 6 years after the breach of contract or contract completion
For claims to which the Building Act 2004 applies the long-step period is 10 years (if in negligence)
In other words:
Limited to 6 years from discovery (but extended to) Ten year-long stop for “reasonable discoverability” (under Building Act)
Contract vs Tort vs Legislation
In contract it is six years from the date of the act or omission.
In tort it is six years from the date the damage is discovered or ought to reasonably have been discovered.
The Building Act 2004 (legislation) provides that no civil action may be commenced more than 10 years after the date of the act or omission, referred to as a “long stop”.
Members should not accept any extension to the time limit beyond the 6 year duration required for contract claims. Any more may mean that claims arising in the extended period are uninsured.
If the client agrees to the 6 years in contract then that is binding, however
Limitations Act 2010 – for building related matters the time scales generally are:
Limited to 6 years from discovery (but extended to)
Ten year-long stop for “reasonable discoverability” (under Building Act)
https://smithpartners.co.nz/litigation/limitation-periods/
6 years and 10 years run in parallel
How long should you keep your doucments for?
Case law between BNZ,Wellington City Council and BECA as a third party- NZACS recommends for 12 years’
Would say 15 years because of Limitations Act 15 year long stop
What are the three legislations in relation to most construction related liability limtations?
Building Act 2004
Limitations Act 2010
Weathertight Homes Resolution Services Act 2006 (WHRS)
What is the limitations of liability (in regards to quantum/money) in the AAS?
$250,000
WHat is the minimum professsional indemnity insurance you should carry under the AAS?
Not less than $250,000
If the client requires longer than six years of PI and more than $250K what should you do?
Where a client wants a longer period than six years, or a greater amount than $250k, the
client has to request that, and the architect agree, and the specific terms need to be
inserted in Section E7 Special Conditions.
This will also change your professional indemnity (typically 6 years after project completition). So Architect will immeditely need to talk to insuer (NZACS)
The AAS notes that “If a greater amount of insurance indemnity is required by the Client, the cost of the additional amount will be at the Client’s expense”
What “late knowledge extension period” for the limitation period of 6 years?
+ 3 years from date of discovery (doesnt need to be next to the 6 year period)
All claims will expire 15 years after the date of the act or omission. This is known as the long stop.
READ THIS AGAIN!!! (last section)
https://smithpartners.co.nz/litigation/limitation-periods/
What is the difference between Torts, Crimes and Contracts?
Torts - Civil Wrong (common law presidence-based)
Crimes - Criminal wrong, legislation based (police are often involved)
Contracts - agreements, mix of common law and legislation
Does NZACS Cover you for more than 6 years? (regarding “late knowledge extension period)
yes
For as long as you are in architectural practice, professional indemnity insurance should be maintained.
Once you cease practice you will need to need to consider continuing with a “run-off “PI Insurance policy. This can extend your previous cover, but with an ever-reducing annual premium which recognises your lessened risk exposure.
I am an architect working for a non-architectural firm. Does my firm need Professional Indemnity Insurance that specifically covers architects/architecture?
Yes; Professional Indemnity Insurance would still be required. If you are an NZIA member you are eligible to apply for the NZACS insurance cover in your name. It won’t include your employer, but it will provide cover to you and any legal liability that you may have in your role as the architect.
Should you tell your clients how much PI insurace you have?
The PI cover you actually have in force – and the terms of that cover – is a confidential matter between you and your insurers: clients have no right to access that information, and you have no obligation to disclose it unless required to do so by the discovery processes as part of court proceedings. Indeed, insurers will be VERY UPSET if you divulge those terms to others!