FAR part 33 Deck 1 (Protests, Disputes and Appeals) Flashcards

DISCLAIMER: This deck was created using Brainscape's AI Software by feeding it small chunks of the FAR itself. It is NOT from any quiz, test or other source. If you find an error while studying contact the creator to fix it. (67 cards)

1
Q

What does Part 33 of the Federal Acquisition Regulation (FAR) cover?

A

Policies and procedures for filing protests and for processing contract disputes and appeals

This part includes various subparts related to protests and disputes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the definition of ‘day’ in the context of FAR Part 33?

A

A calendar day, unless otherwise specified

The computation of any period excludes the day of the act, event, or default.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does ‘filed’ mean in FAR Part 33?

A

The complete receipt of any document by an agency before its close of business

Documents received after close of business are considered filed as of the next day.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who is considered an ‘interested party’ for filing a protest?

A

An actual or prospective offeror whose direct economic interest would be affected by the award or failure to award a contract

This includes those who would be directly impacted by procurement decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What constitutes a ‘protest’ under FAR Part 33?

A

A written objection by an interested party to a solicitation, cancellation, award, or termination of a contract

Protests must include specific allegations regarding improprieties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the three venues for filing protests according to FAR Part 33?

A
  • The agency
  • The Government Accountability Office (GAO)
  • The U.S. Court of Federal Claims

U.S. District Courts do not have bid protest jurisdiction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What must contracting officers do with all protests?

A

Consider all protests and seek legal advice, regardless of the protest venue

This applies to protests submitted before or after award.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What actions can the head of an agency take if a protest reveals noncompliance with law or regulation?

A
  • Take actions recommended by the Comptroller General
  • Pay appropriate costs
  • Require reimbursement from the awardee

These actions are contingent on findings related to the protest.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the time frame for funds available to an agency for a contract when a protest is filed with the GAO?

A

Funds shall remain available for obligation for 100 days after the final ruling on the protest

This is in accordance with 31 U.S.C. 1558.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the recommended approach for an interested party wishing to protest?

A

Seek resolution within the agency before filing a protest with the GAO

This may facilitate a quicker resolution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is required in a protest filed with an agency?

A
  • Name and contact information of the protester
  • Solicitation or contract number
  • Legal and factual grounds for the protest
  • Relevant documents
  • Request for ruling
  • Statement of relief requested
  • Evidence of interested party status
  • Evidence of timeliness

Failure to comply may result in dismissal of the protest.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What happens if a protest is received before award?

A

A contract may not be awarded pending resolution unless justified for urgent reasons

This justification must be approved at a level above the contracting officer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How long does an agency have to resolve a protest after it is filed?

A

35 days

Agencies should make best efforts to meet this timeline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What should agency protest decisions include?

A

Well-reasoned explanations of the agency’s position

These decisions must be communicated to the protester in a way that provides evidence of receipt.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What must a protester do after filing a protest with the GAO?

A

Furnish a copy of the complete protest to the designated official within 1 day

Failure to do so may result in dismissal of the protest.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the consequence of not filing a protest based on alleged improprieties in a solicitation on time?

A

Protests must be filed before bid opening or closing date for proposals

Otherwise, the agency may not consider the merits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the role of the contracting officer upon receipt of a protest?

A

To suspend performance pending resolution of the protest unless justified otherwise

Justifications must be documented and approved at a higher level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the significance of Executive Order 12979 in the context of agency protests?

A

Establishes policy on agency procurement protests

It emphasizes the need for informal resolution efforts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the time frame for an agency to submit a complete report to the GAO after a protest is filed?

A

30 days after notification by phone or 20 days after receipt of an express option determination

The GAO may advise the agency that the protest has been dismissed or authorize a longer period for submission.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What must the procuring agency provide to actual or prospective offerors upon request when a protest is filed?

A

Reasonable access to the protest file

This is subject to applicable protective orders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

When is the protest file not required to be made available?

A

If the GAO dismisses the protest before documents are submitted

Information exempt from disclosure may be redacted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What documents must be included in the protest file?

A
  • The protest
  • The offer submitted by the protester
  • The offer being considered for award
  • All relevant evaluation documents
  • The solicitation
  • The abstract of offers
  • Any other relevant documents

Including those specifically requested by the protester.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is required at least 5 days prior to filing the report if the protester has requested specific documents?

A

The agency must provide a list of released or withheld documents and reasons for withholding

Objections to this disclosure must be filed within 2 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What must the agency report to the GAO include?

A
  • A copy of relevant documents
  • The contracting officer’s signed statement of facts
  • A list of parties receiving documents

The statement should include findings, actions, and recommendations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What should an agency do when it submits its report to the GAO?
Furnish copies of its report to the protester and intervenors ## Footnote Certain documents may be withheld for various reasons, including protective orders.
26
What happens if the protester requests additional documents?
The agency must provide them to the GAO within 2 days of the request ## Footnote This includes documents covered by a protective order.
27
What can the GAO issue to establish terms for document provision?
Protective orders ## Footnote These orders restrict the disclosure of sensitive information.
28
What is the time frame for the GAO to issue its recommendation on a protest?
Within 100 days or 65 days under the express option ## Footnote The GAO may also resolve amended protests within the initial time limit.
29
What must an agency do if it does not implement GAO recommendations within 60 days?
Report the failure to the GAO within 5 days ## Footnote The report must explain the reasons for non-compliance.
30
What costs may the GAO recommend an agency pay to a protester?
* Costs of filing and pursuing the protest * Reasonable attorney, consultant, and expert witness fees * Bid and proposal preparation costs ## Footnote The agency must use procurement funds for these payments.
31
What is the maximum hourly rate for attorney fees unless justified?
$150 per hour ## Footnote Agencies may increase this based on specific recommendations.
32
What should be done before paying a recommended award of costs?
Consult legal counsel ## Footnote This applies to all recommended awards of costs that have not yet been paid.
33
What is the definition of 'accrual of a claim'?
The date when all events fixing liability were known or should have been known ## Footnote Injury must have occurred for liability to be fixed.
34
What does 'alternative dispute resolution (ADR)' mean?
Any voluntary procedure to resolve issues in controversy ## Footnote This includes mediation, arbitration, and other methods.
35
What clause must be inserted in solicitations for contracts exceeding the simplified acquisition threshold?
52.233-2, Service of Protest ## Footnote This is a requirement for contracting officers.
36
What clause must be included in all solicitations and contracts?
52.233-3, Protest After Award ## Footnote The clause may have an Alternate I for cost reimbursement contracts.
37
What is required for liability to be fixed?
Some injury must have occurred. ## Footnote Monetary damages need not have been incurred.
38
Define Alternative dispute resolution (ADR).
Any type of procedure or combination of procedures voluntarily used to resolve issues in controversy, including: * Conciliation * Facilitation * Mediation * Fact-finding * Minitrials * Arbitration * Use of ombudsmen.
39
What does defective certification mean?
A certificate which alters or deviates from the language in 33.207(c) or is not executed by an authorized person. ## Footnote Failure to certify is not deemed a defective certification.
40
What is an issue in controversy?
A material disagreement between the Government and the contractor that: * May result in a claim; or * Is all or part of an existing claim.
41
Define misrepresentation of fact.
A false statement of substantive fact or conduct leading to a false belief about a substantive fact, made with intent to deceive or mislead.
42
What does the Disputes statute provide for?
* Payment of interest on contractor claims * Certification of contractor claims * Civil penalty for fraudulent claims or misrepresentation of fact.
43
To what contracts does the Disputes statute apply?
Any express or implied contract covered by the Federal Acquisition Regulation, except for: * Contracts with foreign governments * Contracts with international organizations if deemed not in the public interest.
44
What is the Government's policy regarding contractual issues?
To resolve all contractual issues in controversy by mutual agreement at the contracting officer's level.
45
What is the time limit for submitting contractor claims?
Within 6 years after accrual of a claim, unless a shorter time period is agreed upon.
46
What certification is required for claims exceeding $100,000?
A certification stating: * Claim is made in good faith * Supporting data are accurate and complete * Amount requested reflects the contract adjustment * Authorized to certify the claim.
47
When does the Government pay interest on contractor claims?
From the date the contracting officer receives the claim or when payment would be due, whichever is later.
48
What happens if a contractor is found to have submitted a fraudulent claim?
The contracting officer shall refer the matter to the agency official responsible for investigating fraud.
49
What is the role of the contracting officer in resolving claims?
To decide or resolve all claims arising under or relating to a contract subject to the Disputes statute.
50
What must a contracting officer do if a claim cannot be settled by mutual agreement?
* Review the facts pertinent to the claim * Secure assistance from legal advisors * Prepare a written decision.
51
What is the appeal process for a contractor dissatisfied with a contracting officer's decision?
The contractor may appeal to the agency board of contract appeals or bring an action in the United States Court of Federal Claims.
52
What must be included in the contracting officer's written decision?
* Description of the claim or dispute * Reference to pertinent contract terms * Statement of factual areas of agreement and disagreement * Statement of contracting officer's decision with rationale.
53
What is the significance of the clause at 52.233-1?
It recognizes the 'all disputes' authority established by the Disputes statute and states requirements and limitations for guidance.
54
What happens if a contracting officer fails to issue a decision within the required time periods?
It will be deemed a decision denying the claim and authorizes the contractor to file an appeal or suit.
55
What is the obligation to continue performance under the Disputes statute?
Contractors may be required to continue contract performance pending final resolution of any claim arising under or relating to the contract.
56
What is the objective of using ADR procedures?
To increase the opportunity for relatively inexpensive and expeditious resolution of issues in controversy.
57
What is the objective of using Alternative Dispute Resolution (ADR) procedures?
To increase the opportunity for relatively inexpensive and expeditious resolution of issues in controversy. ## Footnote ADR aims to resolve disputes without formal litigation.
58
What are the essential elements of ADR?
* Existence of an issue in controversy * A voluntary election by both parties to participate in the ADR process * An agreement on alternative procedures and terms to be used in lieu of formal litigation * Participation in the process by officials of both parties who have the authority to resolve the issue in controversy. ## Footnote These elements ensure that both parties are committed to the ADR process.
59
True or False: ADR procedures can only be used after the issuance of a contracting officer's final decision.
False. ## Footnote ADR procedures may be used at any time that the contracting officer has authority to resolve the issue.
60
What must a contracting officer provide if they reject a contractor's request for ADR proceedings?
A written explanation citing one or more of the conditions in 5 U.S.C. 572(b) or specific reasons that ADR procedures are inappropriate. ## Footnote This ensures transparency in the decision-making process.
61
Fill in the blank: A solicitation shall not require _______ as a condition of award, unless required by law.
arbitration. ## Footnote Arbitration should not be a mandatory condition unless legally mandated.
62
What is required for an agreement to use arbitration?
It must be in writing and specify a maximum award that may be issued by the arbitrator, as well as any other conditions limiting the range of possible outcomes. ## Footnote This helps in setting clear expectations for the arbitration process.
63
When may binding arbitration be agreed to?
Only as specified in agency guidelines. ## Footnote Agencies must provide guidance on the appropriate use of binding arbitration.
64
What clause must be inserted in solicitations and contracts unless specific conditions apply?
Clause at 52.233-1, Disputes. ## Footnote This clause outlines the procedures for handling disputes in contracts.
65
What clause must be inserted in all solicitations and contracts?
Clause at 52.233-4. ## Footnote This clause is standard for all contracts to ensure consistency in dispute resolution.
66
What should be protected during ADR proceedings?
The confidentiality of ADR proceedings. ## Footnote This is consistent with 5 U.S.C. 574.
67
What is the role of a neutral person in ADR procedures?
To facilitate resolution of the issue in controversy using the procedures chosen by the parties. ## Footnote This can help the parties reach a mutually agreeable solution.