Flashcards 1 - 40

(40 cards)

1
Q

Bidders instructions:

A

Describe the company’s qualifying requirements for bidders - their licenses, labor affiliations, qualifications and bonds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Specifications;

A

Enables bidders to understand exactly what they are expected to supply and install.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The purchasing organization should clearly state:

A

its evaluation criteria; how each Criteria is weighted and what and how Proposals will be evaluated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The purpose of the invitation for bid (IFB)?

A

When a system is already designed, the IFB is used to obtain the lowest cost for the equipment, software and installation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The company should be prepared to defend its selection of qualified contractors by having?

A

Written selection criteria and results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The output of the project design phase is called the…..

A

Bid package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the four components of the bid package?

A

Bidders’ instructions
Specifications
Drawings and schedules
Hardware schedules

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The component of the bid package that supplies the security system requirements in sufficient detail so bidders all know equally what is needed?

A

Specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The five most commonly supplied drawings within the bid package are?

A

Plan
Elevation
Detail
Riser diagrams
Conduit and cable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The 3 hardware schedules in the bid package that help in understanding the specific components to be provided?

D-D - CC

A

Data panel schedule
Door hardware schedule and
CCTV camera schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The group that carries out the security system procurement activities?

A

The procurement committee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A bidder’s conference is?

A

All bidders are put in a room and the project manager can explain the procurement requirements to all of them at the same time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A bidder’s conference should include what 7 things:

“Interesting Individuals Introduce Every Detail Thoroughly & Quickly.”

A

• I – Introductory remarks
• I – Introduction of evaluation team and bidders
• I – Introduction of project and key objectives
• E – Explanation of procurement process
• D – Discussion of the purpose, timeline, and evaluation criteria
• T – Tour of the site
• Q – Questions (opportunity to ask)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

To resolve a minor informality or irregularity in the bids, a company should give a bidder a chance to…..

A

Resolve any minor deficiency, such as missing information or attachments, wrong number of copies or missing signatures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The six phases of the PPS Life cycle process are?

“Please Don’t Push It Too Much.”

A

• P – Planning
• D – Design and estimation
• P – Procurement
• I – Installation, operation, and training
• T – Testing and warranty
• M – Maintenance, evaluation, and replacement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How long can the typical PPS implementation process take?

A

18 to 24 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The most important phase of the PPS life cycle is…?

A

The planning phase

18
Q

Which part of the PPS life cycle includes the procurement process?

A

Phase 3, procurement

19
Q

Three common types of procurement actions?

A

Sole source;
Request for proposal
Invitation for bid

20
Q

Three major components of the PPS procurement phase?

A

Form a Procurement committee
Prepare a bid package and
Prequalify contractors

21
Q

The procurement phase includes these 3 things:

A

Conduct a Bidders conference
Review Technical and cost evaluations
Interview and Due diligence results

22
Q

Planning, coordinating and controlling the complex and diverse activities of modern security projects is called…?

A

Project management

23
Q

Documentation that is prepared during the planning stage of procurement management is called…..the

A

Project scope document

24
Q

To ensure a PPS is comprehensive and appropriate, a project managers should….

A

Divide the project into several stages

25
Two key reminders project managers should keep in mind include…?
keep the project on Schedule and under control And Determine and sequence activities
26
When is a project complete?
All Objectives have been achieved.....and A Transfer of knowledge has occurred from the Project team to the Operations personnel
27
Risks (6) involved in Security system procurement? “Late Systems Affect Organizations’ Third-party Risks”
• Late – System delivered late or over budget • Systems – System doesn’t work as required • Affect – System may affect existing systems or processes • Organizations’ – The organization may be unable to recover losses after a contract breach • Third-party – Third-party subcontractors may make claims against the company • Risks – (Summarizes the overarching theme of these issues)
28
The 7 steps that are part of the procurement process?
-Form a procurement committee -Specify hardware and software requirements -id potential integrators -launch a competitive tender program -select a successful bidder -issue a purchase order and -receive and install the products and services
29
A project manager should schedule a bidders’ confernece?
About one week after the Request for proposal is issued.
30
In selecting contractors, what 3 things must be reviewed/accomplished?
Qualifications reviewed Reference checked Interviews with the people who will do the work.
31
Skills and characteristics of a good project manager fall into 2 main areas…..?
Process management skills - Organized, logical, analytical, self-disciplined; People skills - Leadership, supervision, team-building and communications ability
32
What is a pathway to success in project management?
A systematic approach with repeatable and documented work practices
33
What consumes the greatest amount of project management time day to day? The _____ which includes what 4 things?
The control effort which includes: gathering information, reviewing progress, documenting issues and managing the overall work plan.
34
The project manager should hold status meetings at least…?
Weekly
35
Which PPS life cycle phase includes developing a punch list and taking necessary actions to formally accept and commission the system?
The installation, operation and training phase
36
Commissioning is…?
The process of ensuring all systems and components are (DITO-M) Designed, installed, tested, operated and maintained according to the operational requirements of the owner?
37
A punch list is……?
A contract document used in the architectural and building trades to organize the completion of a construction project
38
Who must receive end-user training of the PPS? O - U - M
All personnel involved in operating, upgrading and maintaining the PPS
39
Three types of tests that should be run when commissioning a PPS?
Factory acceptance tests Site acceptance tests Availability or reliability testing
40
What should testing simulate in the PPS commissioning process?
Realistic conditions