Flashcards 41 - 80
(41 cards)
- Within testing and commissioning when should a certificate of completion be issued and a contract considered complete?
After all prescribed testing is complete.
- Equipment performance testing determines these three things?
F-S-D
• F – Functional (Is the equipment working?)
• S – Sensitivity (Is it detecting/responding as needed?)
• D – Design & Performance (Does it meet operational requirements?)
- Personnel Performance testing determines what three things?
-are procedures effective
-do personnel know and follow them
-do personnel & equipment interact effectively
- How does the contractor perform pre-delivery or factory acceptance testing?
-assemble a test system w/all or same components;
-conduct tests to show system performance meets specified requirements
- How does a contractor perform site acceptance testing?
“D-VIP-the T”
- D – Develop a plan to calibrate & test all components
- V – Verify data transmission system operation
- I – Install the system
- P – Place the system in service
- T – Test the system
- How should reliability testing be conducted?
24 hours per day for 15 consecutive calendar days including holidays.
- Six types of post-implementation tests?
“Only Proactive People Seek Lasting Excellence.”
Only - Operational
Proactive - Performance
People - Post -maintenance
Seek - Subsystem
Lasting - Limited scope and
Excellence - Evaluation
- The four phases of reliability testing are….?
Phase I - te______
Phase I - ass______
Phase II - te_____
Phase II - ass_____
Testing
Assessment
- Operational tests are….
A type of post-implementation test performed periodically to prove correct system operation but DOES NOT involve verification of equipment operating specifications
- Post-maintenance tests are….?
A post-implementation test conducted after preventive or remedial maintenance on a security system to make sure the systems are working properly.
- Limited Scope tests are…?
A post-implementation test used to test a complex system that is broken down into several subsystems or segments that are tested separately.
- Performance tests are?
“PIT-VEMS”
“PIT-VEMS”
(Post-Implementation Test - Verifies Equipment Meets Specs and is, therefore, effective.)
- Subsystem tests are…?
A post-implementation test that ensures large parts of the system are all working together as designed.
- Evaluation tests are…?
A P, P-I, I
A periodic, post-implementation, independent test of the security system to validate the vulnerability analysis and ensure overall effectiveness is being maintained.
- The 2 deliverables during the commissioning and warranty of the implementation phase include…?
-testing to ensure the system’s effectiveness and reliability;
- correction of any problems free of charge by the installation contractor during the warranty phase.
- Stage four, close out is the project stage that includes….?
Maintenance,
Evaluation and
Replacement
- How often should evaluation tests be performed?
At least annually
- Stress tests…?
Check people’s or objects’ tolerance to abuse or misuse under stress
- Regression tests are…?
Tests that apply to subsystems, systems or procedures that have been altered to a perform a a new function and must still perform some of their original functions.
- A training manual for a PPS should include what 3 things?
A d-o, a d-d
A - -An agenda
D - defined objectives for each lesson
DD - a detailed description of the subject matter for each lesson.
- Approval of the planned training content and schedule should be obtained from the customer?
At least 30 days before the training date.
- System troubleshooting and maintenance training should cover what 5 things?
-physical layout of each piece of hardware and calibration procedures;
-training and diagnostic procedures;
-Preventive maintenance procedures and schedules…..and
-repair instructions
63.How many site acceptance tests (SAT) are normally conducted for each physical location where system components are being installed?
One
- The 4 goals of preventive maintenance?
K-E-I CV
-Keep equipment and systems operating efficiently;
-extend the operational life of equipment
-identify equipment issues before a failure occurs
-check and verify that all secondary power sources such as standby batteries are fully charged and working.