Formulas Flashcards
(55 cards)
What is Net Present Value (NPV) used for?
NPV is used for project selection. Always select the project with the highest NPV.
How is Net Present Value (NPV) calculated?
NPV = Year 0 Initial Investment + [Cash Flow 1 / (1 + Discount Rate) ^1] + [Cash Flow 2 / (1 + Discount Rate) ^2] + [Cash Flow 3 / (1 + Discount Rate) ^3] …
What is the formula for PERT (Program Evaluation and Review Technique) using Triangular Distribution?
PERT = (Optimistic + Most Likely + Pessimistic) / 3
What is the formula for PERT using Beta Distribution?
PERT = (Optimistic + (4 × Most Likely) + Pessimistic) / 6
How do you calculate Standard Deviation in PERT?
Standard Deviation (SD) = (Pessimistic - Optimistic) / 6
What is the formula for Risk Rating in qualitative risk analysis?
Risk Rating = Probability × Impact (Expressed as a percentage or decimal)
How is Expected Monetary Value (EMV) calculated?
EMV = Probability × Impact (Expressed as a dollar amount)
How do you calculate the number of communication channels?
Communication Channels = n(n-1)/2, where n = number of team members.
How is the Make or Buy Analysis equation structured?
Cost to Make = Cost to Buy (Lease). Solve for X (breakeven point): Initial Cost + (Daily Cost × X) = Cost to Lease + (Daily Lease Cost × X).
What is the formula for calculating Float?
Float = Late Start - Early Start, or Float = Late Finish - Early Finish.
How is Planned Value (PV) calculated?
PV = Budget at Completion (BAC) × Percent of Time Passed.
How is Earned Value (EV) calculated?
EV = Budget at Completion (BAC) × Percent of Work Completed.