Jack Tunnel Design and Construction Flashcards

(37 cards)

1
Q

What does tunnel jacking refer to?

A

The installation of tunnels by pushing them into the ground while excavating from an open face.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Where is tunnel jacking most often used?

A

In soft ground and at shallow depth.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In what ground and length conditions is tunnel jacking generally used?

A

Soft ground for relatively short lengths of tunnel where a tunnel boring machine is not appropriate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What tunnel method is tunnel jacking an alternative to for shallow tunnels?

A

Cut-and-cover method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a secondary application of tunnel jacking?

A

Used to install relatively small tunnel sections within which concrete foundations can be constructed in readiness to receive a bridge superstructure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How can tunnel sections be installed with minimal disruption?

A

Jacked into position with no disruption or slid into position during a limited possession of the overlying facility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Once Tunneling has started?

A

It should be a continuous ‘around the clock’ operation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the first step in constructing a pedestrian subway using tunnel jacking?

A

The tunnel is first fabricated on a jacking base.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is provided at the front of the tunnel during tunnel jacking?

A

A shield

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the function of the shield in tunnel jacking?

A

To allow the contractor to excavate the open face of the tunnel as jacking proceeds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How does the shield enter the ground?

A

Through an opening formed in the headwall.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is used to push the tunnel forward into the soil face?

A

Hydraulic jacks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Where are the jacks located?

A

At the rear of the tunnel and can either push-off the jacking base or off a rear thrust wall.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How is the shield driven upon completion of the jacking?

A

Through the reception pit of steel sheet piles.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How can the shield be compartmentalized?

A

Into cells from which hand excavation can be carried out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is jacking force reduced for long tunnels?

A

** intermediate jacking station** (IJS).

17
Q

How can abutments be constructed using tunnel jacking?

A

Using jacked-in rectangular tunnels to support bridge superstructures.

18
Q

What does the full-size monolithic tunnel section method involve?

A

Constructing tunnel sections in-situ on a high tolerance casting slab adjacent to the final position.

19
Q

How can the tunnel be jacked into position?

A

While excavating the tunnel face or within an open excavation during a brief possession.

20
Q

What tends to happen at shallow depths of cover?

A

The prism of soil above the tunnel moves along as the tunnel is jacked forward.

21
Q

How is a rail track supported?

A

On a grillage of steel beams.

22
Q

What can be used to separate moving tunnels and stationary ground at shallow cover?

A

Flat sheet material or a system of closely spaced steel cables.

23
Q

At greater depths of cover, how is separation from stationary ground achieved?

A

By a drag reducing laminate, such as rubber or polyester sheets, steel cables, or injected lubricating material.

24
Q

What provides the motive force to the tunnel units?

A

Hydraulic rams.

25
What are typical jack ratings for small and large tunnels?
Small tunnels: 100 tons; large tunnels: 500 tons or more.
26
Why is it preferable to reduce friction between the tunnel units and the surrounding ground?
Lower friction results in lower jacking resistance, more uniform friction, and less disturbance to the soil.
27
What are ways to reduce friction between the tunnel units and surrounding ground?
High quality construction tolerances, soil trimming, injection lubrication, and separation layers like steel plates or rubber sheeting.
28
What kind of tunneling technique is tunnel jacking?
A soft ground tunneling technique.
29
What is key to controlling settlements and movements?
Controlling the 'loss of ground' into the tunnel face during installation.
30
What is the shield designed to do?
Support the tunnel face and provide additional support if ground becomes unstable.
31
How can poor quality ground be improved?
By grouting or by ground freezing.
32
What contributes to control of tunnel installation tolerance?
High quality construction, friction control, tunnel guides, tunnel unit length selection, and skilled mining.
33
What is the proper starting point for a jacked box tunnel project?
A comprehensive site investigation.
34
What is the anti-drag system (ADS)?
An array of closely spaced wire ropes stored in the box and anchored at the jacking pit.
35
How is vertical alignment controlled?
By the tolerances to which the jacking base, box, and shield surfaces are constructed.
36
How is the box guided during early stages?
By fixed guides located on the jacking base along both sides of the box.
37
How is face loss controlled in cohesive ground?
By supporting the face with a tunneling shield and careful control of face excavation and box advance.