Q

What does the Sedimentation Pollution Control Act of 1973 apply to?

A

Sedimentation caused by erosion or depositing of soil from construction sites and road maintenance. Does not apply to agriculture, forestry, mining, or emergency activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When does sedimentation occur?

A

When flowing water slows down enough to allow suspended soil particles to settle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is required by 15A NCAC 04B.0108 for erosion control?

A

Erosion control measures shall be planned, designed, and constructed to provide protection from the run off of that 10 year storm.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When must erosion and sedimentation control plans be filed under 15A NCAC 04B.0118(a)?

A

At least 30 days prior to beginning such activity, with three copies filed with the local government or Commission.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What must erosion and sedimentation control plans include under 15A NCAC 04B.0118(c)?

A

An authorized statement of financial responsibility and ownership signed by the person financially responsible for the land-disturbing activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who conducts inspections under 15A NCAC 04B.0120?

A

The staff of the Department of Environment, Health, and Natural Resources or other qualified persons authorized by them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is the width of a buffer zone measured under 15A NCAC 04B.0125(a)?

A

From the edge of the water to the nearest edge of the disturbed area, with 25% of the strip nearest the land-disturbing activity containing natural or artificial means of confining visible siltation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the buffer zone requirement for trout waters under 15A NCAC 04B.0125(b)?

A

Minimum width of 25 feet from the top of the bank or enough width to confine visible siltation within the first 25% of the buffer zone, whichever is greater.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the requirements for diversion dikes for perimeter protection?

A

At least 2’ across at the top and 18” high.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the required capacity for sediment basins?

A

Designed with a storage capacity of 1800 cf/acre.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How deep must silt fence fabric be buried?

A

12 inches below grade.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the minimum tensile strength required for silt fence fabric?

A

30 PSI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How deep must ground be scarified for seedbed preparation?

A

At least 4 inches deep.