Knowledge Sheet & Fundamentals Flashcards
(148 cards)
Project Charter
Identifies and authorizes a PM to achieve project objectives. Includes high level objectives, milestone, and budget
Business Case
Explains how project meets market demand, business need, customer requests, technological advancement, legal requirement, ecological impact, or social need.
Project Management Plan
A formal plan documenting how the project will be managed, executed, and controlled.
Scope Statement
Document stating the project requirements by describing objectives, deliverables, and acceptance criteria
Scope Baseline
Project Scope Statement, WBS, and WBS dictionary
Control Account
Provides a way to manage and control costs, schedule, and scope at a higher level than a work package.
Each work package is assigned to a single Control Account.
Work package
Lowest level in WBS. Can be completed without the need for more information or input
Activity list
Created from WBS; a list of activities within each work package.
PERT estimate formulas
Program Evaluation and Review Technique = Beta Distribution Duration Estimate
Types of 3-Point Estimates
- Beta Distribution Duration Estimate (weighted average)
- Triangular Distribution Duration Estimate (average)
Scenario Inputs for Estimates
P = Pessimistic scenario
M = Most Likely scenario
O = Optimistic scenario
Beta Distribution Duration Estimate
(P + 4M + O) / 6
Triangular Distribution Duration Estimate Formula
(P + M + O) / 3
Standard Deviation of an Activity
(P - O) / 6
Variance of Activity
[(P - O) / 6]2
Project Network Diagram
A diagram of the shedule activities in the order in which they must be performed.
Critical Path
The path of schedule ativities where the delay of any one activity would delay the projet finish
Float
Late Start - Early Start
or
Late Finish - Early Finish
Cost Baseline
Aggregated cost of activities to complete project + contingency reserves
Planned Value
The value of the work planned to be completed to a point in time or project completion
PV = Planned % Complete x BAC
Earned Value
As of today, what is the estimated value of the work actually accomplished?
EV = Actual % Complete x BAC
Actual Cost
The actual cost of all the work completed to a point in time
Budget at Completion
BAC = Cost Baseline
Cost Variance
The difference between the value of work completed to a point in time and the actual costs to the same point in time.
CV = EV - AC