M6 CONCEPTS Flashcards
(36 cards)
involves identifying all the necessary activities essential for successfully completing a project
Project Planning
entails establishing the sequential order of these planned activities, allocating realistic durations to each, and determining their start and finish dates.
Project Scheduling
to monitor the volume, expenses, and schedule of work needed for the project’s successful completion
Project Control
an integration of the individual plans developed by each of the functional areas of the organization involved in the project
Project Sumary Plan
- actual work planned (Work Package)
- represents the process of doing something
- consumes resources and time
Task
- signifies a moment in time
- usually the instant when something is started or finished
Event
- an event which signifies a major occurrence
- signifies progress and is an important measure of project performance
Milestone
Two General Methods commonly used in Project Planning
- Bar Chart - Gantt Chart
- Critical Path Method - Network Analysis System
- a graphical time-scale of the schedule.
- an effective technique for overall project scheduling
- Developed by Henry L. Gantt (1861-1919) during World War I
Bar Chart (Gantt Chart)
Uses of Gantt Charts
- Assessment of status of work elements
- Manpower planning
- Resource allocation
- Budgeting
Disadvantages of Gantt Chart
- does not show work element interrelationships (effects of delayed elements to others)
- effects of delay
- which activities can be postponed
Sometimes called precedence networks, it is considered an analytical tool as well as a presentation material. Through the logical relationships established between linked activities, the dependence and impacts of delays or problems can be traced.
Logic Diagrams
o comprehensive method for project planning, scheduling, and controlling
o coordinating work showing interdependences of activities
Network Analysis System (NAS)
Within the context of NAS, is the performance of a task required to complete the project
Activity
diagrams that represent the relationship of activities to complete the project Network
Networks
amount of time an activity may be delayed without delaying project completion
Total Float (TF)
TF = LF - EF or TF = LS - ES
The amount of time an activity may be delayed without delaying the early start time of the immediately following activity.
Free Float (FF) or Slack
FF(i) = ES(j) - EF(i)
A series of interconnected activities through the network diagram, with each activity having zero, free and total float time. Determines the minimum time to complete the project.
Critical Path
An activity (represented by a dotted line on the arrow network diagram) that indicates that any activity following the [Blank] cannot be started until the activity or activities preceding the [Blank] are completed. Does not require any time.
Dummy Activity
o developed in 1956 by the DuPont Company
o Common in the engineering and construction industry
o provides interrelationships of activities and scheduling of costs and resources
o is an effective technique for overall project scheduling and detailed scheduling of construction
Critical Path Method (CPM)
TRUE OR FALSE
CPM is deterministic, it uses one (1) time estimate
TRUE
Assumptions of CPM
- The estimated completion time for a project can be shortened by applying additional resources to key activities.
- Assumes that the time to perform any activity is variable, depending on the amount of effort of the resources applied to it .
- a graphical representation of the status of accomplishment of a project, as formally defined here.
- This is also the most common indicator of progress to the Client or Contractor tracking the work.
- This tool would also become the basis for periodic cash flow.
S-curve
The purpose is for the clients to know terms of payments. This is produce when the schedule is combined with cash-flow.
Periodic Cash Flow