M6 CONCEPTS Flashcards

(36 cards)

1
Q

involves identifying all the necessary activities essential for successfully completing a project

A

Project Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

entails establishing the sequential order of these planned activities, allocating realistic durations to each, and determining their start and finish dates.

A

Project Scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

to monitor the volume, expenses, and schedule of work needed for the project’s successful completion

A

Project Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

an integration of the individual plans developed by each of the functional areas of the organization involved in the project

A

Project Sumary Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • actual work planned (Work Package)
  • represents the process of doing something
  • consumes resources and time
A

Task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  • signifies a moment in time
  • usually the instant when something is started or finished
A

Event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  • an event which signifies a major occurrence
  • signifies progress and is an important measure of project performance
A

Milestone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Two General Methods commonly used in Project Planning

A
  1. Bar Chart - Gantt Chart
  2. Critical Path Method - Network Analysis System
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  • a graphical time-scale of the schedule.
  • an effective technique for overall project scheduling
  • Developed by Henry L. Gantt (1861-1919) during World War I
A

Bar Chart (Gantt Chart)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Uses of Gantt Charts

A
  • Assessment of status of work elements
  • Manpower planning
  • Resource allocation
  • Budgeting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Disadvantages of Gantt Chart

A
  • does not show work element interrelationships (effects of delayed elements to others)
  • effects of delay
  • which activities can be postponed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Sometimes called precedence networks, it is considered an analytical tool as well as a presentation material. Through the logical relationships established between linked activities, the dependence and impacts of delays or problems can be traced.

A

Logic Diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

o comprehensive method for project planning, scheduling, and controlling
o coordinating work showing interdependences of activities

A

Network Analysis System (NAS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Within the context of NAS, is the performance of a task required to complete the project

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

diagrams that represent the relationship of activities to complete the project Network

A

Networks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

amount of time an activity may be delayed without delaying project completion

A

Total Float (TF)

TF = LF - EF or TF = LS - ES

17
Q

The amount of time an activity may be delayed without delaying the early start time of the immediately following activity.

A

Free Float (FF) or Slack

FF(i) = ES(j) - EF(i)

18
Q

A series of interconnected activities through the network diagram, with each activity having zero, free and total float time. Determines the minimum time to complete the project.

A

Critical Path

19
Q

An activity (represented by a dotted line on the arrow network diagram) that indicates that any activity following the [Blank] cannot be started until the activity or activities preceding the [Blank] are completed. Does not require any time.

A

Dummy Activity

20
Q

o developed in 1956 by the DuPont Company
o Common in the engineering and construction industry
o provides interrelationships of activities and scheduling of costs and resources
o is an effective technique for overall project scheduling and detailed scheduling of construction

A

Critical Path Method (CPM)

21
Q

TRUE OR FALSE

CPM is deterministic, it uses one (1) time estimate

22
Q

Assumptions of CPM

A
  • The estimated completion time for a project can be shortened by applying additional resources to key activities.
  • Assumes that the time to perform any activity is variable, depending on the amount of effort of the resources applied to it .
23
Q
  • a graphical representation of the status of accomplishment of a project, as formally defined here.
  • This is also the most common indicator of progress to the Client or Contractor tracking the work.
  • This tool would also become the basis for periodic cash flow.
24
Q

The purpose is for the clients to know terms of payments. This is produce when the schedule is combined with cash-flow.

A

Periodic Cash Flow

25
# **Type of S-curve** Client- more initial resources Contractor- paid for work that has less necessary value
Front Loaded S-curve
26
# **Type of S-curve** Client: + pays little at the beginning. - quality of job may be compromised Contractor: + is always ahead - shells out own resources at the onset.
End Loaded S-curve
27
* developed in 1957 for the Polaris Missile System Program * principally developed for projects where there is much **uncertainty** * uncertainty in the duration is addressed by using **three (3) time estimates**
Program/Project Evaluation and Review Technique (PERT)
28
minimum time an activity could take (when the situation goes well) - normal effort level
Optimistic Time (a or t_o)
29
maximum time an activity could take (bad luck is encountered every step of the way) –excludes environmental snags {disasters, strikes, etc}
Pessimistic Time (b or t_p)
30
normal time for job completion time which would occur most frequently if the job were repeated over and over
Most likely Time (m or t_m)
31
* when the maximum effort is applied so that the activity can be completed in the shortest possible time * represents the shortest duration and the greatest cost
Crashed Condition
32
represents the time-cost relationship or the marginal trade-off of cost-to-time for the activity
Cost Slope
33
represents the point on the distribution where there Is a 50% chance of completion.
Expected Time (t_e)
34
Formula for Expected Time (t_e)
t(e) = (a + 4m + b)/6 or t(e) = [t(o) + 4t(m) + t(p)]/6
35
Formula for Variance
var = [(b-a)/6]^2 or var = [(t(p) - t(o))/6]^2 | sd = [t(p) - t(o)]/6
36
Formula for Z score
Z = [t_estimate - t(e)]/sd