M7 CONCEPTS Flashcards

(27 cards)

1
Q

the set of procedures and management practices used to collect information about the performance achieved or forecasted in a project and the developing organization, based on a set of performance metrics.

A

Project Monitoring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  • make adjustments to meet project goals project control involves the following processes:
  • analyzing the causes of performance problems,
  • designing changes to address problems that are determined to need attentions, and
  • implementing those changes through control actions.
A

Project Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Quantitatively measures actual performance against the plan and acts as early warning systemto diagnose major problems while management action can still be effective in achieving solutions.

A

Project Control System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

a structure where the total cost for the project including the direct costs plus indirect costs, contingency reserve, and profit.

A

Cost Breakdown Structure (CBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

rovide a reference standard against which to compare actual or forecast results.

A

Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What has already happened.

A

Actuals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is expected to happen to the project and its elements in the future

A

Forecasts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How far actual and forecast results differ from those which were planned or estimated.

A

Variances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Anticipated or unexpected circumstances that account for the actual and forecast behavior of the project and its operations, and especially that explain significant variances from the plan.

A

Reasons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Actions and allowable practices for Project Control

A
  1. Selectivity and Sub-reporting
  2. Variances
  3. Management by Exception
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

TRUE OR FALSE

Milestone dates are required for the start only of each subcontractor’s work

A

FALSE

required for START and COMPLETION

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TRUE OR FALSE

Note that subcontractors are employees of the general contractor, and their work must be excluded in the total project schedule.

A

FALSE

NOT employees of the general contractor, their work must be INCLUDED

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

TRUE OR FALSE

To have an effective cost control, the trends of the cost must be established as soon as possible, and be compared against both the planned and the actual progress so that management can take remedial action if required.

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

provides the analytical methods and procedures for monitoring, analyzing, forecasting, and controlling the costs on a construction project.

A

Cost Engineering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

basic document against which the cost engineer measures and compares actual progress.

A

Control Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

o shows the integrated relationship of
the basic components of a project:
* scope (work),
* budget (cost), and
* schedule (time)
o A good summary level report for
the status of the overall project.

A

Integrated Cost/Schedule/Work Graph

17
Q

Project Control Conditions

A

a. Over budget and behind schedule
b. Under budget and behind schedule
c. Under budget and ahead of schedule
d. Over budget and ahead of schedule

18
Q

For management to have a clear vision ahead and be able to anticipate problems, reports must look to the future as well as document the past.

A

Forecasting and Trending

19
Q

Information reported must be received in time so that, if necessary, corrective action may be taken on those operations that generated the information.

A

Feedback Time

20
Q
  • utilized to determine the overall percentage of completion for the entire project
  • can be connected to the project budget, represented in work hours or cost.
A

Earned Value System

21
Q

Formula of Scheduled Variance (SV)

22
Q

Formula for Schedule Performance Index (SPI)

23
Q

Formula for Cost Variance (CV)

24
Q

Formula for Cost Performance Index (CPI)

25
# **TRUE OR FALSE** a positive variance (CV or SV) and an index of 1.0 (in CPA or SPI) or greater are favorable performance indicators
TRUE
26
Formula for Estimate To Complete (ETC)
ETC = (BAC - BCWP)/CPI
27
Formula for Estimate At Completion (EAC)
EAC = (ACWP + ETC)